Polish Offshore Wind Grid Connections

Transmission ModelDeveloper Builds
TSOPSE
SupportTwo-sided CfD (25 yr)
Pipeline~18 GW (official target)
Developer-Builds ModelHVAC Nearshore / HVDC Far-shoreFirst OWF COD 2026EU State Aid Approved

Poland is developing a major offshore wind sector in the Baltic Sea, with no projects yet operational and the first (Baltic Power, 1,140 MW) expected to reach COD in H2 2026. The regulatory framework centres on the Offshore Wind Act (2021), which established a two-phase CfD support scheme and streamlined permitting.

Unlike Germany, the Netherlands, or Denmark, Poland uses a developer-builds model: wind farm developers build and own all offshore transmission assets (export cables and substations). PSE (the TSO) builds only the onshore grid infrastructure to receive power.

The first-phase pipeline of 5.9 GW (6 projects) is fully under construction. The first competitive CfD auction in December 2025 awarded a further 3.4 GW, with auctions planned for 2027, 2029, and 2031 targeting 18 GW by 2040. Poland has identified 33 GW of offshore wind potential.

Key Regulatory Bodies

BodyRoleKey Functions
Ministry of Climate & Environment (MKiŚ)Primary policymakerDrafted the Offshore Wind Act. Sets capacity targets, auction volumes, and CfD parameters.
URE (Energy Regulatory Office)Energy regulatorIssues Phase I CfD decisions (Art. 16 + Art. 18). Announces, organises, and conducts Phase II auctions. The minister (not URE) sets maximum strike prices.
Ministry of Infrastructure (MI)Maritime authorityGrants PSZW location permits for artificial islands in the EEZ. Prepares the Maritime Spatial Plan (adopted by Council of Ministers).
PSETransmission system operatorIssues grid connection conditions and agreements. Builds onshore substations and transmission lines. Produces the Transmission System Development Plan.
Maritime Office in Gdynia (Urząd Morski)Maritime permitsProcesses cable-laying permits (PUUK in territorial sea; UUUK agreements in EEZ).
RDOŚ (Gdańsk / Szczecin)Environmental authorityIssues environmental decisions for offshore wind projects. Conducts EIA procedures covering impacts on marine ecosystems.
PSEW (Polish Wind Energy Association)Industry bodyKey advocacy organisation. Publishes offshore wind potential studies and policy recommendations.

Developer-Builds Transmission Model

Poland operates a developer_full transmission model. The wind farm developer is responsible for all offshore transmission infrastructure: export cables, offshore substations, and the developer's onshore substation. PSE builds only the transmission grid infrastructure (400 kV substations and overhead lines) that connects the developer's assets to the national grid.

PSE is investing PLN 4.5 billion (~EUR 1 billion) in onshore grid infrastructure across Pomeranian Province to accommodate offshore wind, including new substations at Choczewo and Krzemienica.

Grid Connection Process

PSZW Location Permit

Ministry of Infrastructure grants seabed right in EEZ

Cable Permits (PUUK/UUUK)

PUUK for territorial sea; UUUK agreement for EEZ

Environmental Decision

RDOŚ Gdańsk conducts EIA — up to 26 months

Grid Connection Agreement

PSE issues conditions and signs binding agreement

CfD Award

URE issues CfD (Phase I) or awards via auction (Phase II)

Building Permit

Regional authority approves construction

PSE Onshore Connection Nodes

NodePlanned CapacityStatusProjects Served
Choczewo5.0 GWOperational (Dec 2025)Baltic Power, Baltica 2/3, BC-Wind, Baltic East, Baltica 1
ŻarnowiecLinked to Choczewo via 400 kVExpanded, operationalConnected to Choczewo
Krzemienica4.4 GWUnder construction (Redzikowo)Bałtyk 1, Baltica 9+/FEW Baltic II
Słupsk Wierzbięcino1.4 GWExisting, expandedBałtyk 2, Bałtyk 3

Technology Choices

All Phase I projects (nearshore, 2340 km from coast) use HVAC at 220275 kV. For Phase II, the Bałtyk 1 project (80 km offshore, 1,560 MW) will be Poland's first HVDC offshore wind connection, justified by distance and capacity. An OWC/ABL Group study recommended HVDC for all far-shore Polish projects.

CfD Support Scheme

Poland's offshore wind support uses two-sided Contracts for Difference, approved by the European Commission under EU State Aid rules (SA.62629, EUR 22.5 billion total scheme). Support runs for 25 years from first electricity delivery. The strike price is indexed annually by the Polish consumer price index (CPI).

Phase I CfD by Administrative Decision (5.9 GW)

ParameterDetail
Allocation methodIndividual decision by President of URE (not auction)
Application deadline31 March 2021 (Art. 13(1))
Maximum strike pricePLN 319.60/MWh (EUR 71.82/MWh)
Support duration25 years from first electricity delivery
Projects allocated7 projects totalling 5.9 GW (URE issued 7 support decisions)
IndexationAnnual CPI adjustment

Phase II Competitive CfD Auctions

ParameterDetail
MechanismTwo-sided CfD via competitive auction
First auction17 December 2025 — 4 GW offered, 3.4 GW awarded (3 projects)
Strike pricesPLN 476.88–492.32/MWh (EUR 113–117/MWh)
Delivery deadline7 years from auction close
Support duration25 years

Future Auction Schedule

YearPlanned CapacityStatus
20254 GWCompleted
20274 GWPlanned
20292 GWPlanned
20312 GWPlanned

Consenting & Permitting

Key Permits in Sequence

StepPermitAuthorityNotes
1PSZW (Artificial Islands Permit)Ministry of InfrastructureFoundational seabed right. Competitive procedure if multiple applicants. Prerequisite for CfD.
2Cable permits: PUUK / UUUKMaritime Office (PUUK) / Maritime admin (UUUK)PUUK for territorial sea; UUUK agreement for EEZ cables.
3Environmental Decision (EIA)RDOŚ GdańskUp to 26 months from EIA report submission. Covers benthos, fish, birds, marine mammals, protected areas.
4Grid Connection AgreementPSEInitial grid connection conditions required before CfD auction participation.
5Water Law ConsentWody PolskieWater-law permit for infrastructure affecting water bodies.
6Building PermitRegional authorityFor offshore infrastructure and onshore cable/substation routes.
The Offshore Wind Act provides for immediate enforceability of environmental decisions, water-law consents, and building permits meaning construction can begin before any appeals are resolved.

Supply Chain Plan

Developers must submit a supply chain plan with their CfD application, describing planned activities to develop the Polish supply chain and reporting a local content ratio (Polish CAPEX / total CAPEX). There is no mandatory minimum percentage reporting and engagement are required, but no specific numerical target is enforced.

Grid Connection & System Planning

PSE produces the Transmission System Development Plan (updated to 2032), which identifies the onshore infrastructure required for offshore wind. The plan assumes three primary connection nodes in Pomeranian Province with a total capacity exceeding 10.9 GW.

Maritime Spatial Planning

The Maritime Spatial Development Plan, adopted June 2021, allocates 2,340 km² of Polish EEZ (~10% of total) for offshore wind. A 2025 study identified 20 additional areas (2,171.5 km²) that could support a further 17.7 GW, bringing total identified potential to 33 GW.

Planning InstrumentOwnerKey Content
Transmission System Development Plan (20232032)PSEDefines three onshore connection nodes (Choczewo 5.0 GW, Krzemienica 4.4 GW, Słupsk 1.4 GW). PLN 4.5 bn investment programme.
Maritime Spatial Development PlanMinistry of InfrastructureAllocates ~2,000 km² for offshore wind. Adopted June 2021.
PEP2040 (National Energy Policy)Ministry of Climate & EnvironmentSets 5.9 GW target by 2030, 11 GW by 2040. Auction schedule of 12 GW across 2025–2031.

Financial Framework

ParameterPhase IPhase II
Allocation methodAdministrative CfD decision by URECompetitive two-sided CfD auction
Strike priceMax PLN 319.60/MWh (~EUR 72/MWh)Auction bids: PLN 477–492/MWh (~EUR 113–117/MWh)
Support duration25 years25 years
IndexationAnnual CPIAnnual CPI
Total scheme valueEUR 22.5 bn (EU State Aid approved)
Delivery deadlineSpecified in individual decisions7 years from auction close

The two-sided CfD mechanism means developers pay back to the state when electricity market prices exceed the strike price, and receive compensation when market prices fall below it providing stable, predictable revenue for 25 years.

Phase I strike prices (~EUR 72/MWh, set in 2021) are significantly lower than Phase II auction prices (~EUR 113117/MWh, December 2025), reflecting global offshore wind cost inflation between 2021 and 2025.

Historical Evolution

  1. First maritime areas designated

    Polish maritime areas in the Baltic Sea first designated for offshore wind energy research and development.
  2. Strategic priority announced

    Government announces offshore wind as a strategic priority in national energy policy, triggering legislative preparation.
  3. Offshore Wind Bill published

    Offshore Wind Bill published (15 January). Government announces PLN 130 billion investment plan for offshore wind (September).
  4. Offshore Wind Act enacted

    Act enacted (17 Dec 2020, published 3 Feb 2021). Maritime Spatial Plan adopted (June). Phase I CfD decisions issued for 5.9 GW. EU State Aid approval (May). PSE announces EUR 1 billion grid investment.
  5. Act amended

    Offshore Wind Act amended (17 August, effective 1 October). Phase II auction mechanism detailed and refined.
  6. Construction era begins

    FID for Baltica 2 (Jan) and Bałtyk 2 & 3 (May). PSE confirms Choczewo and Żarnowiec substations ready (Dec). First CfD auction awards 3.4 GW (17 Dec).
  7. First COD expected

    Baltic Power expected COD (H2 2026) — Poland’s first offshore wind farm. Offshore construction begins on Bałtyk 2 & 3.

Current Offshore Wind Grid Systems

Phase I Under Construction / Development (~5.9 GW)

ProjectDeveloperCapacityTechnologyOffshore Subs.Grid PointCOD
Baltic PowerOrlen / Northland Power1,140 MWHVAC 230 kV2Choczewo 400 kVH2 2026
Baltica 2PGE / Ørsted1,498 MWHVAC 275 kV4Choczewo 400 kV2027
Baltica 3PGE / Ørsted1,045 MWHVAC 275 kVShared w/ B2Choczewo 400 kV~2029
Bałtyk 2Polenergia / Equinor720 MWHVAC 220 kV1Słupsk 400 kV2027–2028
Bałtyk 3Polenergia / Equinor720 MWHVAC 220 kV1Słupsk 400 kV2028
BC-WindOcean Winds390 MWHVAC 275 kV1Choczewo 400 kV2028

Phase II CfD Auction Winners (3,435 MW)

ProjectDeveloperCapacityTechnologyGrid PointCOD
Bałtyk 1Polenergia / Equinor1,560 MWHVDC (first in PL)Krzemienica 400 kVBy 2032
Baltica 9PGE975 MWTBDKrzemienica areaBy 2032
Baltic EastOrlen900 MWHVACChoczewo area2032

Awaiting Future Auction

ProjectDeveloperCapacityGrid PointNotes
Baltica 1PGE896 MWChoczewo 400 kVDid not win Dec 2025 auction. Targeting 2027 auction.

Supranational Dimension

Poland's offshore wind sector operates within the EU regulatory framework, with the CfD scheme approved under EU State Aid rules (SA.62629).

FrameworkRelevance to Poland
EU State Aid (SA.62629)EUR 22.5 bn CfD scheme approved May 2021. Covers both Phase I administrative decisions and Phase II competitive auctions.
BEMIP (Baltic Energy Market Interconnection Plan)Poland participates in Baltic Sea energy market cooperation, including offshore wind grid coordination.
Baltic InteGridEU-funded study exploring meshed offshore grid in the Baltic Sea. Identified Poland as the anchor country with the highest Baltic Sea offshore wind potential (28 GW by 2050).
ENTSO-E TYNDPPoland’s offshore wind expansion features in the Ten-Year Network Development Plan for cross-border grid reinforcement.
EU Electricity Market Design ReformTwo-sided CfDs promoted at EU level (December 2025 EU Grids Package) align with Poland’s existing model.

Reform & Future Outlook

Poland's offshore wind framework is relatively new (enacted 2021) and is evolving rapidly as the first projects approach commissioning and the auction pipeline expands.

AreaCurrent StatusExpected Evolution
Auction expansion12 GW planned across 4 auctions (2025–2031)Government considering increasing to 14+ GW. 20 new areas (17.7 GW) identified for future designation.
HVDC adoptionBałtyk 1 will be Poland’s first HVDC OWFFar-shore Phase II/III projects likely to adopt HVDC as standard for projects 50+ km from coast.
Grid infrastructurePSE building Krzemienica; Choczewo/Żarnowiec operationalAdditional onshore nodes may be needed for 20+ GW target. Grid reinforcement in central Poland for power evacuation.
Meshed offshore gridNo current plansBaltic InteGrid study explored concept. Could become relevant at 18–33 GW scale.
Hybrid interconnectorsNo projects identifiedPotential for combined wind export + interconnector projects as Baltic Sea offshore grid density increases.

Key Sources

Fact Check

This page is fact-checked using automated verification. Two iterations are run against the research document, with findings independently verified before corrections are applied.

IterationDateErrors ReportedVerified & FixedFalse PositivesSummary
22026-03-151055Precision: maritime area 2,340 km², Phase I total ~5.9 GW, Art. 16/18 nuance, ministry role tightened, maritime authority clarified, Harmony Link update.
12026-03-1517125Key fixes: Phase I = 7 projects, deadline 31 Mar 2021, auction schedule 12 GW, Baltic Power 1,140 MW, Baltica 3 1,045 MW, added ZARE, corrected URE/Minister roles, cable permit terminology.

This page is for informational purposes only. It reflects the regulatory framework as understood at the time of research (March 2026) and may not capture the latest changes. Always consult primary sources for binding regulatory requirements.