UK Interconnector Regulatory Framework[Draft]

How subsea electricity interconnectors are regulated, consented, and financed in Great Britain.

Last updated: March 2026 · Sources: Ofgem, DESNZ, NESO, legislation.gov.uk

Operational10 interconnectors
Total Capacity~10.3 GW
In Pipeline7 projects
Pipeline (2032)>18 GW

Key Regime

Cap-and-floorOfgem's bespoke framework (since 2014). Guarantees minimum revenue (floor) while capping upside (cap). Applied via application windows.

Key Bodies

OfgemDESNZNESOCrown EstateMMOPINS

Key Regulatory Bodies

BodyRoleKey Functions
OfgemEnergy regulatorCap-and-floor regime, interconnector licensing (Electricity Act 1989 s6), access rules, revenue assessment
Department for Energy Security and Net ZeroGovernment departmentDCO decisions for NSIPs (England & Wales), National Policy Statements (EN-1, EN-5, designated Jan 2026), Capacity Market
National Energy System OperatorSystem operatorNetwork Options Assessment (suspended pending CSNP), grid connections, CSNP development (due 2028), connections reform
The Crown Estate / Crown Estate ScotlandSeabed managerSeabed leases for cables within 12 nm, conflict checks, Whole of Seabed Programme
Marine Management Organisation / Marine ScotlandMarine licensingMarine licences under MCAA 2009 for cable laying, trenching, rock placement. Can be deemed within DCO
The Planning InspectorateDCO examinationExamines NSIP applications (6-month examination), recommends to Secretary of State
Natural England / Natural Resources Wales / NatureScotEnvironmental adviceEIA, HRA, and EPS licensing. Statutory consultees during pre-application and examination

Post-Brexit, the UK no longer participates in ACER or ENTSO-E governance. NESO engages bilaterally with ENTSO-E for system planning coordination. UK projects may still appear in the TYNDP through cooperative information sharing.

The Cap-and-Floor Regime

Introduced in August 2014, the cap-and-floor is Ofgem's bespoke regulatory framework for electricity interconnectors. It sits between full merchant risk and full cost-of-service regulation, designed to encourage investment while protecting consumers.

How Cap & Floor Works

Assessed over 5-year periods across a 25-year regime. Cap based on cost of equity (CAPM), floor based on cost of debt. Availability incentive adjusts cap by +/- 2%.

Assessment Process

Projects go through a multi-stage assessment:

StageWhat Happens
Initial Project Assessment (IPA)Ofgem assesses the needs case — is the project in consumers' interest? Multiple projects assessed together per window.
Final Project Assessment (FPA)Cost efficiency assessed, preliminary cap and floor levels set. Each project assessed individually.
Post Construction Review (PCR)Triggered when 85–95% of capex incurred (around start of operations). Ofgem updates the financial model. Final cap/floor levels confirmed.
End of Period Assessment (EPA)Every 5 years: cumulative revenues compared to cap/floor. Top-ups or clawbacks calculated.

Application Windows

WindowYearProjects ApprovedNotable Outcomes
Pilot2013Nemo Link (1 GW, GB-Belgium)First EPA completed July 2024. Revenue exceeded cap by £185m.
Window 12014NSL, IFA2, Viking Link, FAB Link, GreenlinkNSL + IFA2 + Viking Link all operational. FAB Link delayed (FID target end 2025). Greenlink operational Jan 2025.
Window 22016NeuConnect, GridLink, NorthConnectNeuConnect under construction (2028). GridLink stalled (CRE rejection). NorthConnect cancelled (Norwegian govt).
Window 32022-23Tarchon, MaresConnect, LirICExpanded criteria: security of supply, decarbonisation, deliverability. 4 projects rejected (AQUIND, Aminth, Cronos, NU-Link).
No Window 4 announced. Ofgem and DESNZ are developing a "future delivery approach" for strategically aligned interconnectors. Future assessment will be integrated into NESO's CSNP (due end of 2028).

Offshore Hybrid Assets (OHA)

Alongside Window 3, Ofgem approved two OHA pilot projects (November 2024): LionLink (1.8 GW, Netherlands) and Nautilus (1.4 GW, Belgium). These combine interconnection with offshore wind transmission. Regulatory framework: RAB-based for the offshore converter platform + narrow cap-and-floor for the cable element. Developers estimate combined savings of \u00A31.2bn in capacity mechanism payments for 2032 (developer estimate, not an Ofgem-adopted figure).

Merchant Exemption Route

As an alternative to cap-and-floor, developers can seek exemptions from certain regulatory requirements (historically under EU Regulation 714/2009 Article 17, now retained in UK law). Under this route, developers bear full upside and downside — no consumer underwriting.

InterconnectorCapacityRouteStatus
BritNed1 GWGB-NetherlandsMerchant exemption. JV National Grid / TenneT.
ElecLink1 GWGB-France (Channel Tunnel)Merchant exemption. Getlink Group. Operational May 2022.
IFA2 GWGB-FrancePre-regulatory. National Grid / RTE. Operational since 1986.

The merchant route has diminished in practical viability post-Brexit. Many European TSOs cannot participate in merchant projects, and the TCA preserves existing exemptions but new applications follow a modified UK domestic process. Ofgem developed cap-and-floor specifically to overcome the limitations of this approach.

Consenting & Permitting

In England and Wales, interconnectors above 132 kV are classified as Nationally Significant Infrastructure Projects (NSIPs) under the Planning Act 2008 and require a Development Consent Order (DCO). In Scotland, energy infrastructure is consented under section 36 of the Electricity Act 1989 plus marine licensing.

DCO Process

Pre-application

1-3 years

Consultation, EIA, HRA

Acceptance

28 days

PINS quality check

Pre-examination

~3 months

Parties register

Examination

6 months

Written & oral hearings

Recommendation

3 months

Examiner reports to SoS

Decision

3 months

Secretary of State decides

DCO process under the Planning Act 2008. Total concept to energisation: ~6-10 years.

Additional Consents Required

ConsentAuthorityLegislation
Marine LicenceMMO / Marine ScotlandMarine and Coastal Access Act 2009, Part 4. Can be deemed within DCO.
Environmental Impact AssessmentSecretary of StateInfrastructure Planning (EIA) Regulations 2017. Mandatory for NSIPs.
Habitats Regulations AssessmentSecretary of StateConservation of Habitats and Species Regulations 2017.
EPS LicenceNatural England / NRW / NatureScotApplied for after planning permission. Protects cetaceans and marine turtles.
Seabed LeaseCrown Estate / CESRequired for cables within 12 nm. Conflict check → survey consent → lease.
The Planning and Infrastructure Bill (tabled 2025) aims to accelerate NSIP consenting times. DESNZ has pledged decisions on 150+ major infrastructure projects in the current Parliament.

Bilateral Agreements

UK interconnectors are typically developed as commercial joint ventures between transmission operators/developers, not through formal intergovernmental treaties. However, government-level engagement is important for securing regulatory approvals in both countries and coordinating seabed access.

PartnerInterconnectorsStatus
NorwayNSL (operational), NorthConnect (cancelled)Norwegian govt committed to no new interconnectors in current or next parliamentary terms.
BelgiumNemo Link (operational), Nautilus (OHA pilot)Joint regulation: Ofgem + CREG. Nautilus connects to Princess Elisabeth Energy Island.
FranceIFA, IFA2, ElecLink (operational), GridLink (stalled), AQUIND (redetermination)GridLink blocked by French regulator CRE (2022). AQUIND under redetermination after 2022 refusal quashed.
DenmarkViking Link (operational)JV National Grid / Energinet. World's longest land+subsea interconnector (475 mi).
GermanyNeuConnect (construction), Tarchon (W3 approved)NeuConnect expected 2028. Tarchon by Copenhagen Infrastructure Partners.
IrelandEWIC (operational), Greenlink (operational), MaresConnect (W3 approved)EWIC owned by EirGrid. MaresConnect: N. Wales to Republic of Ireland.
N. IrelandMoyle (operational), LirIC (W3 approved)Moyle operated by Mutual Energy (since 2001). LirIC by Transmission Investment.

North Seas Energy Cooperation

The UK re-engaged with NSEC via an MoU (December 2022). At the January 2026 North Sea Summit, leaders reaffirmed 300 GW offshore renewables target, with a third through collaborative cross-border projects. UK OHA projects (LionLink, Nautilus) are part of this cooperation.

Grid Connection & System Planning

NESO (established 2024, succeeding National Grid ESO) is responsible for system planning and grid connections. The Network Options Assessment (NOA) for Interconnectors recommended 29 GW total GB-Europe capacity by 2036 but has been suspended pending the CSNP.

Planning InstrumentStatusTimeline
NOA for InterconnectorsSuspendedAwaiting CSNP. Last assessment: March 2024 (recommended 29 GW by 2036).
CSNPIn developmentMethodology by April 2026. tCSNP2 refresh June 2026. Full CSNP by end 2028.
SSEPIn developmentPathway options summer 2026. Final SSEP Autumn 2027.
Connections ReformActiveNESO leading reform to accelerate grid connections.

Capacity Market Participation

Interconnectors participate in the GB Capacity Market but are "de-rated" — their contribution is discounted to reflect import availability risk during stress events.

InterconnectorCapacityDe-rating Factor
IFA (France)2 GW62%
IFA2 (France)1.1 GW64%
ElecLink (France)1 GW68%
BritNed (Netherlands)1.2 GW*67%
Nemo Link (Belgium)1 GW68%
NSL (Norway)1.4 GW70%
Viking Link (Denmark)1.4 GW63%
NeuConnect (Germany)1.4 GW63%
Moyle (N. Ireland)0.5 GW60%
EWIC (Ireland)0.5 GW60%
Greenlink (Ireland)0.5 GW60%
*BritNed: 1.0 GW nameplate capacity; 1.2 GW connection capacity per DESNZ de-rating table. T-4 auction for 2029/30 delivery year. DESNZ Auction Parameters (July 2025)

Financial & Commercial Framework

The primary revenue source for interconnectors is congestion rent — the electricity price differential between connected markets. Revenue increases with the average price spread and volatility.

ParameterValueNotes
Regime length25 yearsFrom commercial operations date.
Assessment period5 yearsEnd of Period Assessment compares cumulative revenue to cap/floor.
IDC rate (2025-26)5.37%Vanilla, real-CPIH. Mid-point of 4.17%-6.57% WACC range.
Inflation measureCPIHChanged from RPI for Window 3. CPI as interim proxy.
Cost of debt benchmarkiBoxx BBB 15yr+UK Non-financial.
Availability incentive+/- 2%Cap adjusts based on availability performance.

Regulated vs Merchant

AspectCap-and-FloorMerchant/Exempt
Consumer underwritingYes (floor)No
Revenue capYesNo
Revenue riskBounded (dead band)Full upside and downside
Typical developersTSOs, infrastructure investorsPrivate investors, TSO JVs
ExamplesNSL, IFA2, Viking Link, Nemo LinkBritNed, ElecLink

Historical Evolution

  1. IFA: First GB-France Interconnector

    2 GW link between GB and France. Pre-dates both merchant exemption and cap-and-floor frameworks.
  2. Moyle Interconnector

    500 MW GB-Northern Ireland link. Operated by Mutual Energy under a regulated model.
  3. BritNed: Merchant Era

    1 GW GB-Netherlands under EU merchant exemption (Article 17, Regulation 714/2009). JV between National Grid and TenneT.
  4. Cap-and-Floor Introduced

    Ofgem launches the regime as a "third way" between merchant risk and full regulation. Nemo Link selected as pilot. Window 1 opens.
  5. Window 2 Opens

    NeuConnect, GridLink, and NorthConnect apply. All three granted cap-and-floor in principle (January 2018).
  6. Nemo Link Operational

    First cap-and-floor interconnector enters service. 1 GW GB-Belgium.
  7. Brexit: Market Decoupling

    UK leaves EU Internal Energy Market. Explicit auctions replace implicit market coupling. Estimated ~\u00A3560m/year additional generation costs. NSL and IFA2 become operational.
  8. Energy Act & OHA Framework

    Energy Act 2023 introduces Multi-Purpose Interconnectors (MPIs) as new asset class. Ofgem launches OHA pilot scheme. ElecLink operational.
  9. Window 3 & Cancellations

    Viking Link operational (world's longest). NorthConnect cancelled by Norwegian government. GridLink stalled after CRE rejection.
  10. Window 3 Decisions

    Three projects approved (Tarchon, MaresConnect, LirIC), four rejected. Two OHA pilots approved (LionLink, Nautilus). Nemo Link first EPA: revenue exceeded cap by \u00A3185m.
  11. Current: Strategic Transition

    NOA suspended pending CSNP. No Window 4 announced. MRLVC still not implemented (TCA extended to March 2027). De-rating methodology under review. North Seas Energy Cooperation re-engagement.

Current UK Interconnectors

Operational (~10.3 GW)

NameCapacityRouteSinceRegime
IFA2 GWGB-France1986Pre-regulatory
Moyle0.5 GWGB-N. Ireland2001Regulated
BritNed1 GWGB-Netherlands2011Merchant exemption
EWIC0.5 GWGB-Ireland2012Regulated
Nemo Link1 GWGB-Belgium2019Cap-and-floor (pilot)
IFA21 GWGB-France2021Cap-and-floor (W1)
North Sea Link1.4 GWGB-Norway2021Cap-and-floor (W1)
ElecLink1 GWGB-France2022Merchant exemption
Viking Link1.4 GWGB-Denmark2023Cap-and-floor (W1)
Greenlink0.5 GWGB-Ireland2025Cap-and-floor (W1)

Under Construction

NameCapacityRouteExpectedRegime
NeuConnect1.4 GWGB-Germany2028Cap-and-floor (W2)

Approved / In Development

NameCapacityRouteExpectedRegime
FAB Link1.25 GWGB-France (via Channel Is.)~2028Cap-and-floor (W1)
LionLink1.8 GWGB-Netherlands (OHA)Early 2030sOHA pilot
Nautilus1.4 GWGB-Belgium (OHA)Early 2030sOHA pilot
Tarchon1.4 GWGB-GermanyBy 2032Cap-and-floor (W3)
MaresConnect0.75 GWGB (N. Wales)-IrelandBy 2032Cap-and-floor (W3)
LirIC0.7 GWGB (Scotland)-N. IrelandBy 2032Cap-and-floor (W3)

Stalled / Cancelled

NameCapacityRouteStatusReason
GridLink1.4 GWGB-FranceStalledFrench regulator CRE rejected investment request (2022)
NorthConnect1.4 GWGB-NorwayCancelledNorwegian government rejected licence (2023)
AQUIND2 GWGB-FranceStalledDCO refused Jan 2022; refusal quashed; under redetermination (PINS report Oct 2025)
By 2032, if all approved projects complete, GB could have ~1415 operational interconnectors with over 18 GW capacity. NESO's optimal range is 29 GW by 2036.

Supranational Dimension

Post-Brexit Position

The UK no longer participates in the EU PCI/PMI process. UK projects are ineligible for PCI designation or associated benefits (accelerated permitting, CEF funding). The revised TEN-E Regulation (2022) introduced Projects of Mutual Interest (PMI) for third countries, but no UK-EU bilateral agreement exists for this purpose.

TCA Energy Provisions

Title VIII of the Trade and Cooperation Agreement provides a framework for cross-border electricity trading. Annex ENER-4 sets out Multi-Region Loose Volume Coupling (MRLVC) requirements — but MRLVC is still not implemented as of March 2026. The April 2022 deadline was missed. Current trading uses explicit auctions, which are less efficient than previous EU market coupling. TCA energy provisions extended to 31 March 2027.

Estimated cost of current arrangements vs. previous: ~\u00A3560m/year in additional generation costs (~1.5% of total).

Multi-Purpose Interconnectors

The Energy Act 2023 introduced MPIs as a new asset class with a separate electricity licence, defined as subsea cables combining interconnection with offshore transmission. MPI holders must be certified by Ofgem for ownership unbundling. The enduring regime is still under development, informed by the OHA pilot scheme. Ofgem preferred "implicit trading with offshore bidding zones" after consultation.

This reference is provided for informational purposes. Regulatory frameworks are complex and subject to change. Always consult primary sources and professional advisors for decisions. Last reviewed March 2026.