UK Interconnector Regulatory Framework[Draft]
How subsea electricity interconnectors are regulated, consented, and financed in Great Britain.
Last updated: March 2026 · Sources: Ofgem, DESNZ, NESO, legislation.gov.uk
Key Regime
Cap-and-floor — Ofgem's bespoke framework (since 2014). Guarantees minimum revenue (floor) while capping upside (cap). Applied via application windows.
Key Bodies
Key Regulatory Bodies
| Body | Role | Key Functions |
|---|---|---|
| Ofgem | Energy regulator | Cap-and-floor regime, interconnector licensing (Electricity Act 1989 s6), access rules, revenue assessment |
| Department for Energy Security and Net Zero | Government department | DCO decisions for NSIPs (England & Wales), National Policy Statements (EN-1, EN-5, designated Jan 2026), Capacity Market |
| National Energy System Operator | System operator | Network Options Assessment (suspended pending CSNP), grid connections, CSNP development (due 2028), connections reform |
| The Crown Estate / Crown Estate Scotland | Seabed manager | Seabed leases for cables within 12 nm, conflict checks, Whole of Seabed Programme |
| Marine Management Organisation / Marine Scotland | Marine licensing | Marine licences under MCAA 2009 for cable laying, trenching, rock placement. Can be deemed within DCO |
| The Planning Inspectorate | DCO examination | Examines NSIP applications (6-month examination), recommends to Secretary of State |
| Natural England / Natural Resources Wales / NatureScot | Environmental advice | EIA, HRA, and EPS licensing. Statutory consultees during pre-application and examination |
Post-Brexit, the UK no longer participates in ACER or ENTSO-E governance. NESO engages bilaterally with ENTSO-E for system planning coordination. UK projects may still appear in the TYNDP through cooperative information sharing.
The Cap-and-Floor Regime
Introduced in August 2014, the cap-and-floor is Ofgem's bespoke regulatory framework for electricity interconnectors. It sits between full merchant risk and full cost-of-service regulation, designed to encourage investment while protecting consumers.
How Cap & Floor Works
Assessed over 5-year periods across a 25-year regime. Cap based on cost of equity (CAPM), floor based on cost of debt. Availability incentive adjusts cap by +/- 2%.
Assessment Process
Projects go through a multi-stage assessment:
| Stage | What Happens |
|---|---|
| Initial Project Assessment (IPA) | Ofgem assesses the needs case — is the project in consumers' interest? Multiple projects assessed together per window. |
| Final Project Assessment (FPA) | Cost efficiency assessed, preliminary cap and floor levels set. Each project assessed individually. |
| Post Construction Review (PCR) | Triggered when 85–95% of capex incurred (around start of operations). Ofgem updates the financial model. Final cap/floor levels confirmed. |
| End of Period Assessment (EPA) | Every 5 years: cumulative revenues compared to cap/floor. Top-ups or clawbacks calculated. |
Application Windows
| Window | Year | Projects Approved | Notable Outcomes |
|---|---|---|---|
| Pilot | 2013 | Nemo Link (1 GW, GB-Belgium) | First EPA completed July 2024. Revenue exceeded cap by £185m. |
| Window 1 | 2014 | NSL, IFA2, Viking Link, FAB Link, Greenlink | NSL + IFA2 + Viking Link all operational. FAB Link delayed (FID target end 2025). Greenlink operational Jan 2025. |
| Window 2 | 2016 | NeuConnect, GridLink, NorthConnect | NeuConnect under construction (2028). GridLink stalled (CRE rejection). NorthConnect cancelled (Norwegian govt). |
| Window 3 | 2022-23 | Tarchon, MaresConnect, LirIC | Expanded criteria: security of supply, decarbonisation, deliverability. 4 projects rejected (AQUIND, Aminth, Cronos, NU-Link). |
Offshore Hybrid Assets (OHA)
Alongside Window 3, Ofgem approved two OHA pilot projects (November 2024): LionLink (1.8 GW, Netherlands) and Nautilus (1.4 GW, Belgium). These combine interconnection with offshore wind transmission. Regulatory framework: RAB-based for the offshore converter platform + narrow cap-and-floor for the cable element. Developers estimate combined savings of \u00A31.2bn in capacity mechanism payments for 2032 (developer estimate, not an Ofgem-adopted figure).
Merchant Exemption Route
As an alternative to cap-and-floor, developers can seek exemptions from certain regulatory requirements (historically under EU Regulation 714/2009 Article 17, now retained in UK law). Under this route, developers bear full upside and downside — no consumer underwriting.
The merchant route has diminished in practical viability post-Brexit. Many European TSOs cannot participate in merchant projects, and the TCA preserves existing exemptions but new applications follow a modified UK domestic process. Ofgem developed cap-and-floor specifically to overcome the limitations of this approach.
Consenting & Permitting
In England and Wales, interconnectors above 132 kV are classified as Nationally Significant Infrastructure Projects (NSIPs) under the Planning Act 2008 and require a Development Consent Order (DCO). In Scotland, energy infrastructure is consented under section 36 of the Electricity Act 1989 plus marine licensing.
DCO Process
Pre-application
1-3 years
Consultation, EIA, HRA
Acceptance
28 days
PINS quality check
Pre-examination
~3 months
Parties register
Examination
6 months
Written & oral hearings
Recommendation
3 months
Examiner reports to SoS
Decision
3 months
Secretary of State decides
DCO process under the Planning Act 2008. Total concept to energisation: ~6-10 years.
Additional Consents Required
| Consent | Authority | Legislation |
|---|---|---|
| Marine Licence | MMO / Marine Scotland | Marine and Coastal Access Act 2009, Part 4. Can be deemed within DCO. |
| Environmental Impact Assessment | Secretary of State | Infrastructure Planning (EIA) Regulations 2017. Mandatory for NSIPs. |
| Habitats Regulations Assessment | Secretary of State | Conservation of Habitats and Species Regulations 2017. |
| EPS Licence | Natural England / NRW / NatureScot | Applied for after planning permission. Protects cetaceans and marine turtles. |
| Seabed Lease | Crown Estate / CES | Required for cables within 12 nm. Conflict check → survey consent → lease. |
Bilateral Agreements
UK interconnectors are typically developed as commercial joint ventures between transmission operators/developers, not through formal intergovernmental treaties. However, government-level engagement is important for securing regulatory approvals in both countries and coordinating seabed access.
| Partner | Interconnectors | Status |
|---|---|---|
| Norway | NSL (operational), NorthConnect (cancelled) | Norwegian govt committed to no new interconnectors in current or next parliamentary terms. |
| Belgium | Nemo Link (operational), Nautilus (OHA pilot) | Joint regulation: Ofgem + CREG. Nautilus connects to Princess Elisabeth Energy Island. |
| France | IFA, IFA2, ElecLink (operational), GridLink (stalled), AQUIND (redetermination) | GridLink blocked by French regulator CRE (2022). AQUIND under redetermination after 2022 refusal quashed. |
| Denmark | Viking Link (operational) | JV National Grid / Energinet. World's longest land+subsea interconnector (475 mi). |
| Germany | NeuConnect (construction), Tarchon (W3 approved) | NeuConnect expected 2028. Tarchon by Copenhagen Infrastructure Partners. |
| Ireland | EWIC (operational), Greenlink (operational), MaresConnect (W3 approved) | EWIC owned by EirGrid. MaresConnect: N. Wales to Republic of Ireland. |
| N. Ireland | Moyle (operational), LirIC (W3 approved) | Moyle operated by Mutual Energy (since 2001). LirIC by Transmission Investment. |
North Seas Energy Cooperation
The UK re-engaged with NSEC via an MoU (December 2022). At the January 2026 North Sea Summit, leaders reaffirmed 300 GW offshore renewables target, with a third through collaborative cross-border projects. UK OHA projects (LionLink, Nautilus) are part of this cooperation.
Grid Connection & System Planning
NESO (established 2024, succeeding National Grid ESO) is responsible for system planning and grid connections. The Network Options Assessment (NOA) for Interconnectors recommended 29 GW total GB-Europe capacity by 2036 but has been suspended pending the CSNP.
| Planning Instrument | Status | Timeline |
|---|---|---|
| NOA for Interconnectors | Suspended | Awaiting CSNP. Last assessment: March 2024 (recommended 29 GW by 2036). |
| CSNP | In development | Methodology by April 2026. tCSNP2 refresh June 2026. Full CSNP by end 2028. |
| SSEP | In development | Pathway options summer 2026. Final SSEP Autumn 2027. |
| Connections Reform | Active | NESO leading reform to accelerate grid connections. |
Capacity Market Participation
Interconnectors participate in the GB Capacity Market but are "de-rated" — their contribution is discounted to reflect import availability risk during stress events.
| Interconnector | Capacity | De-rating Factor |
|---|---|---|
| IFA (France) | 2 GW | 62% |
| IFA2 (France) | 1.1 GW | 64% |
| ElecLink (France) | 1 GW | 68% |
| BritNed (Netherlands) | 1.2 GW* | 67% |
| Nemo Link (Belgium) | 1 GW | 68% |
| NSL (Norway) | 1.4 GW | 70% |
| Viking Link (Denmark) | 1.4 GW | 63% |
| NeuConnect (Germany) | 1.4 GW | 63% |
| Moyle (N. Ireland) | 0.5 GW | 60% |
| EWIC (Ireland) | 0.5 GW | 60% |
| Greenlink (Ireland) | 0.5 GW | 60% |
Financial & Commercial Framework
The primary revenue source for interconnectors is congestion rent — the electricity price differential between connected markets. Revenue increases with the average price spread and volatility.
| Parameter | Value | Notes |
|---|---|---|
| Regime length | 25 years | From commercial operations date. |
| Assessment period | 5 years | End of Period Assessment compares cumulative revenue to cap/floor. |
| IDC rate (2025-26) | 5.37% | Vanilla, real-CPIH. Mid-point of 4.17%-6.57% WACC range. |
| Inflation measure | CPIH | Changed from RPI for Window 3. CPI as interim proxy. |
| Cost of debt benchmark | iBoxx BBB 15yr+ | UK Non-financial. |
| Availability incentive | +/- 2% | Cap adjusts based on availability performance. |
Regulated vs Merchant
| Aspect | Cap-and-Floor | Merchant/Exempt |
|---|---|---|
| Consumer underwriting | Yes (floor) | No |
| Revenue cap | Yes | No |
| Revenue risk | Bounded (dead band) | Full upside and downside |
| Typical developers | TSOs, infrastructure investors | Private investors, TSO JVs |
| Examples | NSL, IFA2, Viking Link, Nemo Link | BritNed, ElecLink |
Historical Evolution
IFA: First GB-France Interconnector
2 GW link between GB and France. Pre-dates both merchant exemption and cap-and-floor frameworks.Moyle Interconnector
500 MW GB-Northern Ireland link. Operated by Mutual Energy under a regulated model.BritNed: Merchant Era
1 GW GB-Netherlands under EU merchant exemption (Article 17, Regulation 714/2009). JV between National Grid and TenneT.Cap-and-Floor Introduced
Ofgem launches the regime as a "third way" between merchant risk and full regulation. Nemo Link selected as pilot. Window 1 opens.Window 2 Opens
NeuConnect, GridLink, and NorthConnect apply. All three granted cap-and-floor in principle (January 2018).Nemo Link Operational
First cap-and-floor interconnector enters service. 1 GW GB-Belgium.Brexit: Market Decoupling
UK leaves EU Internal Energy Market. Explicit auctions replace implicit market coupling. Estimated ~\u00A3560m/year additional generation costs. NSL and IFA2 become operational.Energy Act & OHA Framework
Energy Act 2023 introduces Multi-Purpose Interconnectors (MPIs) as new asset class. Ofgem launches OHA pilot scheme. ElecLink operational.Window 3 & Cancellations
Viking Link operational (world's longest). NorthConnect cancelled by Norwegian government. GridLink stalled after CRE rejection.Window 3 Decisions
Three projects approved (Tarchon, MaresConnect, LirIC), four rejected. Two OHA pilots approved (LionLink, Nautilus). Nemo Link first EPA: revenue exceeded cap by \u00A3185m.Current: Strategic Transition
NOA suspended pending CSNP. No Window 4 announced. MRLVC still not implemented (TCA extended to March 2027). De-rating methodology under review. North Seas Energy Cooperation re-engagement.
Current UK Interconnectors
Operational (~10.3 GW)
| Name | Capacity | Route | Since | Regime |
|---|---|---|---|---|
| IFA | 2 GW | GB-France | 1986 | Pre-regulatory |
| Moyle | 0.5 GW | GB-N. Ireland | 2001 | Regulated |
| BritNed | 1 GW | GB-Netherlands | 2011 | Merchant exemption |
| EWIC | 0.5 GW | GB-Ireland | 2012 | Regulated |
| Nemo Link | 1 GW | GB-Belgium | 2019 | Cap-and-floor (pilot) |
| IFA2 | 1 GW | GB-France | 2021 | Cap-and-floor (W1) |
| North Sea Link | 1.4 GW | GB-Norway | 2021 | Cap-and-floor (W1) |
| ElecLink | 1 GW | GB-France | 2022 | Merchant exemption |
| Viking Link | 1.4 GW | GB-Denmark | 2023 | Cap-and-floor (W1) |
| Greenlink | 0.5 GW | GB-Ireland | 2025 | Cap-and-floor (W1) |
Under Construction
| Name | Capacity | Route | Expected | Regime |
|---|---|---|---|---|
| NeuConnect | 1.4 GW | GB-Germany | 2028 | Cap-and-floor (W2) |
Approved / In Development
| Name | Capacity | Route | Expected | Regime |
|---|---|---|---|---|
| FAB Link | 1.25 GW | GB-France (via Channel Is.) | ~2028 | Cap-and-floor (W1) |
| LionLink | 1.8 GW | GB-Netherlands (OHA) | Early 2030s | OHA pilot |
| Nautilus | 1.4 GW | GB-Belgium (OHA) | Early 2030s | OHA pilot |
| Tarchon | 1.4 GW | GB-Germany | By 2032 | Cap-and-floor (W3) |
| MaresConnect | 0.75 GW | GB (N. Wales)-Ireland | By 2032 | Cap-and-floor (W3) |
| LirIC | 0.7 GW | GB (Scotland)-N. Ireland | By 2032 | Cap-and-floor (W3) |
Stalled / Cancelled
| Name | Capacity | Route | Status | Reason |
|---|---|---|---|---|
| GridLink | 1.4 GW | GB-France | Stalled | French regulator CRE rejected investment request (2022) |
| NorthConnect | 1.4 GW | GB-Norway | Cancelled | Norwegian government rejected licence (2023) |
| AQUIND | 2 GW | GB-France | Stalled | DCO refused Jan 2022; refusal quashed; under redetermination (PINS report Oct 2025) |
Supranational Dimension
Post-Brexit Position
The UK no longer participates in the EU PCI/PMI process. UK projects are ineligible for PCI designation or associated benefits (accelerated permitting, CEF funding). The revised TEN-E Regulation (2022) introduced Projects of Mutual Interest (PMI) for third countries, but no UK-EU bilateral agreement exists for this purpose.
TCA Energy Provisions
Title VIII of the Trade and Cooperation Agreement provides a framework for cross-border electricity trading. Annex ENER-4 sets out Multi-Region Loose Volume Coupling (MRLVC) requirements — but MRLVC is still not implemented as of March 2026. The April 2022 deadline was missed. Current trading uses explicit auctions, which are less efficient than previous EU market coupling. TCA energy provisions extended to 31 March 2027.
Estimated cost of current arrangements vs. previous: ~\u00A3560m/year in additional generation costs (~1.5% of total).
Multi-Purpose Interconnectors
The Energy Act 2023 introduced MPIs as a new asset class with a separate electricity licence, defined as subsea cables combining interconnection with offshore transmission. MPI holders must be certified by Ofgem for ownership unbundling. The enduring regime is still under development, informed by the OHA pilot scheme. Ofgem preferred "implicit trading with offshore bidding zones" after consultation.