German Offshore Wind Grid Connections[Draft]
How offshore wind transmission assets are planned, constructed, and financed in Germany under the centralised TSO model.
Last updated: March 2026 · Sources: BSH, BNetzA, TenneT, 50Hertz, Amprion · Fact-checked 2026-03-16 (5 iterations)
Key Regime
Centralised TSO Model — TSOs (TenneT, 50Hertz, Amprion) build and operate grid connections. Costs socialised via the offshore grid levy (§17f EnWG).
Key Bodies
Key Regulatory Bodies
| Body | Role | Key Functions |
|---|---|---|
| BSH | Maritime & hydrographic authority | Site planning (FEP), offshore wind permitting in EEZ, environmental assessment (StUK4), maritime spatial planning, PINTA data hub |
| Bundesnetzagentur (BNetzA) | Federal energy regulator | Offshore wind auctions, confirms NEP/grid development plan, TSO revenue regulation (ARegV), central site pre-investigation authority (§11 WindSeeG) |
| BMWE | Federal ministry | Drafts key legislation (WindSeeG, EnWG, EEG), sets 30/40/70 GW targets, NSEC participation, bilateral energy agreements (Bornholm Energy Island) |
| BfN | Nature conservation authority | Statutory consultee for EEZ permitting, species and habitat impact assessment (harbour porpoise, seabirds, Natura 2000), noise mitigation advice |
| WSV | Waterways & shipping admin | Navigational safety assessment, formal agreement (Einvernehmen) required for plan approvals under §69 WindSeeG |
| TenneT | TSO (North Sea) | Builds and operates North Sea grid connections (~8.9 GW operational). Seven 2 GW ±525 kV HVDC systems planned |
| 50Hertz | TSO (Baltic Sea + North Sea) | Baltic Sea connections (~1.8 GW operational). Ostwind 4 (first Baltic 525 kV HVDC). LanWin3 (North Sea). Multi-terminal hub with TenneT near Heide |
| Amprion | TSO (North Sea, newer) | BalWin1 and BalWin2 (2×2 GW, ±525 kV HVDC). Grid interconnection points at Wehrendorf and Westerkappeln |
| Länder (Federal States) | State-level authorities | Permit cables in territorial waters (12 nm), onshore cable routes, converter station planning. Key states: Lower Saxony, Schleswig-Holstein, Mecklenburg-Vorpommern |
Primary Regime — Centralised TSO Model
Germany operates a centralised, proactive TSO model for offshore wind grid connections — fundamentally different from the UK’s OFTO competitive tender model. The state plans sites, pre-investigates them, auctions development rights, and the responsible TSO builds the grid connection at its own cost.
How It Works
| Step | Actor | Description |
|---|---|---|
| 1. Site planning | BSH | Designates offshore wind sites and grid connection systems in the Flächenentwicklungsplan (FEP) |
| 2. Pre-investigation | BNetzA / BSH | Central preliminary investigation: geotechnical, environmental, wind, and oceanographic surveys in the EEZ |
| 3. Auction | BNetzA | Developers bid for wind farm development rights on centrally pre-investigated sites |
| 4. Grid connection | TSO | Responsible TSO (TenneT, 50Hertz, or Amprion) designs, procures, constructs, and operates the offshore grid connection |
| 5. Wind farm | Developer | Winning bidder builds the wind farm and connects to the TSO’s offshore platform via inter-array cables |
Key Legislation
| Law | Scope |
|---|---|
| WindSeeG | Primary offshore wind act: site planning, auctions, grid connection obligations, 30/40/70 GW targets |
| EnWG | Energy industry act: TSO grid connection duty (§17d), delay compensation (§17e), offshore grid levy (§17f) |
| EEG | Renewable energy act: priority grid connection, feed-in remuneration framework |
| ROG | Spatial planning act: legal basis for maritime spatial planning in the EEZ |
| NABEG | Grid acceleration act: accelerated planning procedures for transmission lines |
| SeeAnlG | Offshore installations act: pre-WindSeeG permitting regime (legacy) |
| BNatSchG | Nature conservation act: species and habitat protection in the EEZ |
| UVPG | Environmental impact assessment act |
Comparison: Germany vs UK
| Feature | Germany (TSO Model) | UK (OFTO Model) |
|---|---|---|
| Who builds grid connection | TSO (TenneT / 50Hertz / Amprion) | Wind farm developer |
| Who operates grid connection | TSO (permanent) | OFTO (25-year licence, competitively tendered) |
| Cost recovery | Offshore grid levy (socialised) | TNUoS charges (socialised) |
| Grid connection risk | TSO bears construction risk | Developer bears construction risk |
| Delay compensation | TSO pays developer (EnWG §17e) | N/A — developer owns the asset |
| Site planning | Centralised (BSH FEP) | Developer-led (applies for connection) |
Alternative & Legacy Routes
Pre-WindSeeG Regime (SeeAnlG, pre-2017)
Before the WindSeeG entered into force on 1 January 2017, offshore wind projects were permitted under the Seeanlagengesetz (SeeAnlG). Developers applied directly to BSH for individual site permits and arranged grid connections with TenneT. This led to an uncoordinated “first come, first served” process with significant delays and mismatches between wind farm and grid connection readiness.
Two-Track Auction System (WindSeeG)
| Track | Site Investigation | Auction Mechanism | Notes |
|---|---|---|---|
| Track 1 | BSH conducts all surveys on behalf of BNetzA | Qualitative criteria + negative bidding (willingness-to-pay). No market premium — zero-subsidy or pay for concession | Qualitative criteria include green hydrogen use, training quotas, PPA commitments, biodiversity measures |
| Track 2 | Developers conduct own surveys | Originally lowest market premium; since 2023, zero-cent bids common with dynamic bidding for tie-breaking | Developers retain more risk but also more flexibility |
2025 Auction Failure
In August 2025, Germany’s second offshore wind auction of the year attracted zero bids for two centrally pre-investigated North Sea sites (N-10.1, N-10.2, 2.5 GW combined). Root causes included uncapped negative bidding, rising capital costs, supply chain pressures, and declining capture price forecasts.
2026 Auction Suspension
On 28 January 2026, the federal cabinet approved a drafting aid to suspend all 2026 offshore wind auctions and shift them to 2027. On 30 January 2026, BSH amended the FEP 2025 accordingly. The final auction design for 2027 — including whether Contracts for Difference (CfDs) will be introduced — remains under development.
Consenting & Permitting
BSH is the sole competent authority for offshore wind consenting in the German EEZ. The consenting route depends on whether the site was centrally pre-investigated.
| Route | Statutory Timeline | Applies To |
|---|---|---|
| Plangenehmigung (simplified plan approval) | 12 months (extendable +3 months) | Centrally pre-investigated sites (post-WindSeeG Track 1) |
| Planfeststellungsbeschluss (full plan approval) | 18 months (extendable +3 months) | Non-centrally pre-investigated or legacy sites (Track 2 / SeeAnlG) |
Environmental Impact Assessment (UVP)
| Requirement | Authority | Legislation |
|---|---|---|
| Environmental Impact Assessment (UVP) | BSH | UVPG — mandatory for wind farms >20 turbines or turbines >50m |
| Natura 2000 Assessment (FFH-VP) | BSH with BfN consultation | BNatSchG §34 |
| Marine species assessment | BSH with BfN consultation | BNatSchG — harbour porpoise, seabirds |
| Noise mitigation during construction | BSH | Threshold: 160 dB SEL at 750m from source (pile driving) |
Environmental Monitoring (StUK4)
BSH publishes the “Standard Investigation of the Impacts of Offshore Wind Turbines on the Marine Environment” (StUK4), prescribing baseline surveys and operational monitoring for benthos, fish, marine mammals (harbour porpoise, seals), resting and migrating birds, and bats.
Additional Consents
| Consent | Authority | Notes |
|---|---|---|
| Territorial waters cable permit | Länder (state) mining/planning authority | For cable sections within 12 nm |
| Onshore cable & converter station | Varies by Land (state-level planning authority) | Procedural route varies by federal state |
| Shipping safety assessment | WSV | Navigational safety for wind farm layout |
| Aviation obstruction lighting | Luftfahrtbundesamt | Required for turbines >100m |
| Seabed cable crossing agreements | BSH / cable owners | For crossing existing subsea cables or pipelines |
Typical Timeline (Centrally Pre-Investigated Site)
| Phase | Duration | Description |
|---|---|---|
| FEP designation + site pre-investigation | 3–5 years | BSH-led, before auction |
| Auction award | — | BNetzA conducts tender |
| Plangenehmigung (plan approval) | 12 months (statutory) | Developer submits application, BSH reviews |
| Final Investment Decision | 6–12 months | Post-approval |
| Construction | 2–3 years | Wind farm + internal cabling |
| Grid connection commissioning | Per FEP schedule | TSO builds in parallel |
| Total (auction to power) | ~5\u20137 years | Depends on grid connection readiness |
Grid Connection & System Planning
Flächenentwicklungsplan (FEP / Site Development Plan)
Published by BSH (first edition 28 June 2019, current: FEP 2025 amended January 2026). The FEP is the master planning document that designates offshore wind sites, specifies which grid connection system serves each site, and sets commissioning timelines synchronised between wind farm and grid connection.
| FEP 2025 Parameter | Value |
|---|---|
| New sites for auction (2025–2028) | 10 sites, 12 GW total |
| New North Sea areas identified | N-9, N-12, N-13 (8 GW expected) |
| New areas scheduled for operation | 6 GW by end of 2034 |
Netzentwicklungsplan (NEP / Grid Development Plan)
Prepared biennially by the four German TSOs (TenneT, 50Hertz, Amprion, TransnetBW) and confirmed by BNetzA. Since 2017, the previously separate Offshore-Netzentwicklungsplan (O-NEP) has been integrated into the main NEP.
2 GW Standard Platform Programme
The next generation of German offshore grid connections uses a standardised 2 GW ±525 kV HVDC platform design, replacing the previous ~900 MW±320 kV standard. Benefits include higher capacity per connection (2× improvement), reduced platform count, standardised design enabling serial production, and lower per-MW connection costs.
| Programme | Key Details |
|---|---|
| TenneT 2 GW Programme | Seven 2 GW systems for German North Sea (plus seven for Netherlands). First platforms: BalWin4 and LanWin1 (2029–2030). Major contracts: McDermott (BalWin4/LanWin1), Dragados (LanWin2/LanWin4/LanWin5). Cables: NKT, Nexans (525 kV HVDC) |
| 50Hertz Ostwind 4 | First 2 GW 525 kV HVDC system in Baltic Sea. GE Vernova converter (with Drydocks World). NKT cables (~110 km DC cable system). Location: 30 km NE of Rügen Island |
Multi-Terminal Hub (50Hertz + TenneT)
50Hertz and TenneT are cooperating on an innovative multi-terminal HVDC hub near Heide, Schleswig-Holstein. This connects 4 GW of North Sea offshore wind by 2032 via ~200 km of 525 kV DC underground cable from Heide to Klein Rogahn (near Schwerin) in Mecklenburg-Vorpommern — the first German multi-terminal offshore hub, enabling future meshed grid concepts.
Financial & Commercial Framework
Offshore Grid Levy (Offshore-Netzumlage)
| Parameter | Detail |
|---|---|
| Introduced | 2013 |
| Legal basis | EnWG §17f, administered under EnFG §§10–11 |
| Purpose (original) | Fund compensation to wind farm operators for grid connection delays/disruptions |
| Purpose (expanded 2019) | Also covers TSO costs of constructing and operating offshore connection lines |
| Paid by | All electricity consumers, added to electricity price |
| Rate (2025) | 0.816 ct/kWh |
| Rate (2026) | 0.941 ct/kWh |
| Set by | Four German TSOs jointly; published by 25 October each year |
| Published at | netztransparenz.de |
Grid Connection Delay Compensation (§17e EnWG)
| Parameter | Detail |
|---|---|
| Trigger | Wind farm ready but prevented from feeding in for >10 consecutive days due to delayed grid connection, outage, or maintenance |
| Compensation rate | 90% of remuneration the operator would have received (from day 11) |
| Liability cap | TSO liability capped under §17e; excess costs socialised via offshore grid levy |
| Recent amendment | Deductibles removed for offshore wind farm operators; implementation periods extended |
Wind Farm Revenue Framework
| Period | Mechanism |
|---|---|
| Pre-2017 projects | Fixed feed-in tariffs (FiT) under EEG |
| Post-2017 Track 1 | Zero-subsidy / negative bidding model (2017–2025). 2026 auctions suspended; new design (potentially CfDs) under development for 2027 |
| Post-2017 Track 2 | Market premium via competitive auction; since 2023, zero-cent bids common with dynamic bidding for tie-breaking |
Grid Connection Cost Allocation
TSOs bear 100% of offshore grid connection costs (converter platforms, export cables to shore, onshore converter stations). These costs are recovered via the offshore grid levy, socialised across all electricity consumers. Wind farm developers bear costs of inter-array cables from turbines to the TSO’s offshore platform.
Bilateral & International Cooperation
North Seas Energy Cooperation (NSEC)
Germany is a member of the NSEC (established 2016). Members: Belgium, Denmark, France, Germany, Ireland, Luxembourg, the Netherlands, Norway, and the European Commission. Germany hosted the third international North Sea Summit in Hamburg on 26 January 2026.
Key Bilateral Agreements
| Partner | Agreement | Project |
|---|---|---|
| Denmark | Bilateral agreement signed 26 January 2026 at Hamburg Summit | Bornholm Energy Island: 3 GW total offshore wind connected to Germany and Denmark. 2 GW HVDC link to Germany (50Hertz), separate link to Zealand (Energinet). Target: 2034 |
| Denmark | MoU for Amprion hybrid interconnector | Planned hybrid DE-DK North Sea interconnector |
| Belgium | Part of NSEC framework | Planned DE-BE hybrid offshore link |
| Netherlands | Cooperation via NSEC | Potential multi-terminal offshore hub concepts |
Germany signed an Offshore Realisation Agreement (November 2022) setting the ambition at 50 GW installed by 2035 — exceeding the WindSeeG statutory minimum of 40 GW.
Historical Evolution
BSH permits alpha ventus (then 'Borkum West')
First German offshore wind farm permitted under SeeAnlG.First offshore grid connection
TenneT completes alpha ventus grid connection (60 MW, 110 kV AC, ~67 km cable via Norderney).Alpha ventus fully commissioned
Germany’s first offshore wind farm: 12 × 5 MW turbines, 60 MW total. First HVDC offshore grid connection: BorWin1 (400 MW) commissioned December 2010.Offshore grid levy introduced
Offshore-Netzumlage introduced to fund grid connection delay compensation.Rapid grid connection expansion
DolWin1, HelWin1, HelWin2, SylWin1, BorWin2 commissioned. German offshore wind crosses 3 GW installed.WindSeeG enters into force
Centralised site planning and two-track auction system. First auctions produce zero-subsidy bids (He Dreiht, Gode Wind 3+4).FEP published & 7.5 GW installed
First Flächenentwicklungsplan published by BSH. BorWin3 (900 MW) commissioned. Offshore grid levy expanded to cover construction/operation costs.Targets raised & Realisation Agreement
WindSeeG amended: targets raised to 30/40/70 GW (2030/2035/2045). Offshore Realisation Agreement signed: 50 GW by 2035.First negative-bidding auctions
First negative-bidding auctions for centrally pre-investigated sites. DolWin6 (900 MW) commissioned.DolWin5 commissioned; 9.2 GW installed
DolWin5 (900 MW) commissioned. Ostwind 2 fully operational (750 MW Baltic Sea).BorWin5 commissioned; auction failure
BorWin5 (900 MW) commissioned. August: second auction receives zero bids (2.5 GW). Alpha ventus consortium decides on decommissioning. Total: ~9.7 GW. December: Bundestag amends WindSeeG.Auctions suspended; Hamburg Summit
28 January: cabinet approves suspension of 2026 auctions. 26 January: Hamburg North Sea Summit — Bornholm Energy Island bilateral agreement signed. Ostwind 3 (300 MW) expected September 2026.
Current Grid Connection Systems
Operational — North Sea (TenneT)
| System | Code | Capacity | Technology | Commissioned |
|---|---|---|---|---|
| alpha ventus | NOR-2-1 | 62 MW | 110 kV AC | 2009 |
| BorWin1 | NOR-6-1 | 400 MW | ±150 kV HVDC | Dec 2010 |
| Riffgat | NOR-0-1 | 113 MW | 155 kV AC | 2014 |
| BorWin2 | NOR-6-2 | 800 MW | ±300 kV HVDC | 2015 |
| DolWin1 | NOR-2-2 | 800 MW | ±320 kV HVDC | 2015 |
| HelWin1 | NOR-4-1 | 576 MW | ±250 kV HVDC | 2015 |
| HelWin2 | NOR-4-2 | 690 MW | ±320 kV HVDC | 2015 |
| SylWin1 | NOR-5-1 | 864 MW | ±320 kV HVDC | 2015 |
| DolWin2 | NOR-3-1 | 916 MW | ±320 kV HVDC | 2016 |
| Nordergründe | NOR-0-2 | 111 MW | 155 kV AC | 2017 |
| DolWin3 | NOR-2-3 | 900 MW | ±320 kV HVDC | 2018 |
| BorWin3 | NOR-8-1 | 900 MW | ±320 kV HVDC | 2019 |
| DolWin6 | NOR-3-3 | 900 MW | ±320 kV HVDC | 2023 |
| DolWin5 | NOR-1-1 | 900 MW | ±320 kV HVDC | Oct 2024 |
| BorWin5 | NOR-7-1 | 900 MW | ±320 kV HVDC | Dec 2025 |
| Total North Sea | ~8.9 GW |
Operational — Baltic Sea (50Hertz)
| System | Code | Capacity | Technology | Commissioned |
|---|---|---|---|---|
| Baltic 1 | OST-3-1 | 51 MW | 150 kV AC | 2011 |
| Baltic 2 | OST-3-2 | 288 MW | 150 kV AC | 2015 |
| Ostwind 1 | OST-1-1/1-2/1-3 | 750 MW | 150/220 kV AC | 2018–2019 |
| Ostwind 2 | OST-2-1/2-2/2-3 | 750 MW | 220 kV AC | 2023–2024 |
| Total Baltic Sea | ~1.8 GW |
Under Construction / Approved
| System | Code | TSO | Capacity | Technology | Expected |
|---|---|---|---|---|---|
| Ostwind 3 | OST-1-4 | 50Hertz | 300 MW | 220 kV AC | 30 Sep 2026 |
| BorWin6 | NOR-7-2 | TenneT | 980 MW | ±320 kV HVDC | 1 Oct 2027 |
| DolWin4 | NOR-3-2 | Amprion | 900 MW | ±320 kV HVDC | 2028 |
| BorWin4 | NOR-6-3 | Amprion | 900 MW | ±320 kV HVDC | 2028 |
| Gennaker | OST-6-1 | 50Hertz | 927 MW | AC | 2028 |
| BalWin4 | NOR-9-3 | TenneT | 2,000 MW | ±525 kV HVDC | 2029 |
| BalWin1 | NOR-9-1 | Amprion | 2,000 MW | ±525 kV HVDC | 2030 |
| LanWin1 | NOR-12-1 | TenneT | 2,000 MW | ±525 kV HVDC | 2030 |
| LanWin2 | NOR-12-2 | TenneT | 2,000 MW | ±525 kV HVDC | 2030 |
| Ostwind 4 | OST-2-4 | 50Hertz | 2,000 MW | ±525 kV HVDC | 2031 |
| BalWin3 | NOR-9-2 | TenneT | 2,000 MW | ±525 kV HVDC | 2031 |
| LanWin4 | NOR-11-2 | TenneT | 2,000 MW | ±525 kV HVDC | 2031 |
| LanWin5 | NOR-13-1 | TenneT | 2,000 MW | ±525 kV HVDC | 2031 |
| BalWin2 | NOR-10-1 | Amprion | 2,000 MW | ±525 kV HVDC | 2032 |
| LanWin3 | NOR-11-1 | 50Hertz | 2,000 MW | ±525 kV HVDC | 2032 |
| BalWin5 | NOR-9-4 | TenneT | 2,000 MW | ±525 kV HVDC | 2033 |
Planned Hybrid Projects
| System | TSO | Capacity | Expected | Notes |
|---|---|---|---|---|
| Bornholm Energy Island (DE leg) | 50Hertz | 2,000 MW | Mid-2030s | Bilateral DE-DK. Siemens Energy converter (Sep 2025). ~173 km route. NKT cables (3,500 km total across all BEI links). World’s first hybrid DC interconnector |
NEP 2025 Zubaunetz — Future Grid Connection Systems
The NEP 2037/2045 (version 2025, 2nd draft, March 2026) identifies the additional offshore grid connection systems (ONAS) required beyond the Startnetz to reach the statutory target of at least 70 GW by 2045 (§1(2) WindSeeG). For the first time, the TSOs applied offshore optimisation measures developed with the Fraunhofer Institute for Wind Energy Systems (IWES): adjusted area layouts reduce wake effects, raising full-load hours to ~3,900 h/year; mandatory overplanting (20% above ONAS capacity); and investigation of increasing ONAS transmission from 2.0 to 2.2 GW. The result: the same energy yield (238 TWh in Scenario B 2045) can be achieved with 4–7 fewer ONAS than the confirmed NEP 2023 — saving billions in converter, cable, and installation costs that have risen sharply due to supply chain pressures.
No ONAS commissioning is planned for 2035 — the TSOs intentionally schedule a gap year to relieve strained supply chains after the concentrated 2028–2033 build-out. Two ONAS then commission in 2036 to compensate. This draft awaits BNetzA confirmation; the tables below reflect the 2nd draft (Scenario B 2045 as maximum envelope).
North Sea Zubaunetz (Table 24, NEP 2025 2nd Draft)
| System | Code | TSO | NVP (Onshore) | km | MW | Scenario B 2045 |
|---|---|---|---|---|---|---|
| BorWin7 | NOR-6-4 | Amprion | Kusenhorst | 451 | 2,000 | 2034 |
| LanWin6 | NOR-12-3 | 50Hertz | Pöschendorf | 308 | 2,000 | 2034 |
| LanWin7 | NOR-12-4 | TenneT | Pöschendorf | 342 | 2,000 | 2034 |
| — | NOR-14-2 | Amprion | Rommerskirchen | 633 | 2,000 | 2036 |
| — | NOR-16-1 | TenneT | Hardebek | 365 | 2,000 | 2036 |
| — | NOR-16-2 | 50Hertz | BBS (SH) | 438 | 2,000 | 2037 |
| — | NOR-14-1 | TenneT | Großenmeer | 310 | 2,000 | 2037 |
| — | NOR-16-3 | Amprion | Rommerskirchen | 644 | 2,000 | 2037 |
| — | NOR-16-4 | Amprion | Kriftel | 848 | 2,000 | 2038 |
| — | NOR-17-1 | Amprion | Ried | 916 | 2,000 | 2039 |
| — | NOR-17-2 | TenneT | Nüttermoor | 367 | 2,000 | 2039 |
| LanWin8 | NOR-13-2 | 50Hertz | BBS (SH) | 428 | 2,000 | 2040 |
| — | NOR-5-2 | Amprion | Niederrhein | 508 | 2,000 | 2041 |
| — | NOR-19-1 | TenneT | Esens | 379 | 2,000 | 2042 |
| — | NOR-19-2 | Amprion | Esens | 395 | 2,000 | 2043 |
| — | NOR-5-3 | Amprion | Sechtem | 647 | 2,000 | 2044 |
Baltic Sea Zubaunetz (Table 25, NEP 2025 2nd Draft)
No new Baltic Sea connections are planned in the 2037 scenarios. In all 2045 scenarios, an additional 1 GW is assumed in the Mecklenburg-Vorpommern coastal waters, pending completion of the state spatial development plan. Wind farm areas for these systems have not yet been designated.
| Code | TSO | NVP (Onshore) | Capacity | Technology | Expected |
|---|---|---|---|---|---|
| OST-x-1 | 50Hertz | Gnewitz | 250 MW | AC | 2039 |
| OST-x-2 | 50Hertz | Gnewitz | 250 MW | AC | 2039 |
| OST-x-3 | 50Hertz | Kemnitz | 250 MW | AC | 2040 |
| OST-x-4 | 50Hertz | Kemnitz | 250 MW | AC | 2040 |
Capacity Summary
| Category | Count | Capacity |
|---|---|---|
| Operational North Sea | 15 | ~8.9 GW |
| Operational Baltic Sea | 4 | ~1.8 GW |
| Under construction / approved (Startnetz + Gennaker) | 16 | ~25.0 GW |
| Planned hybrid (Bornholm DE leg) | 1 | 2.0 GW |
| NEP 2025 Zubaunetz North Sea | 16 | 32.0 GW |
| NEP 2025 Zubaunetz Baltic Sea | 4 | 1.0 GW |
| Total pipeline | 56 | ~70.7 GW |
Supranational Dimension
EU Regulatory Framework
| Framework | Relevance |
|---|---|
| TEN-E Regulation (EU 2022/869) | PCI/PMI designation for cross-border offshore projects (e.g. Bornholm Energy Island). Cross-border cost allocation (PS-CBCA) mechanisms |
| Revised RED III | Partially transposed via December 2025 WindSeeG amendment. Offshore renewable acceleration area provisions |
| EU Offshore RE Strategy (2020) | EU target: 300 GW offshore wind by 2050 across all EU sea basins |
| EU MSP Directive | Implemented via German Maritime Spatial Plan (Raumordnungsplan 2021) |
| EU EIA Directive (2011/92/EU) | Transposed into UVPG |
ENTSO-E Offshore Network Development Plan (ONDP)
The first ONDP (published 2024 as part of TYNDP) identified the Northern Seas corridor as requiring approximately 274 GW of offshore wind capacity by 2040. Germany’s 16+ grid connection systems are central to the North Sea and Baltic corridors. Estimated total European offshore transmission CAPEX: ~€400 billion (2025–2050).
PCI/PMI Projects Involving Germany
| Project | Status | Notes |
|---|---|---|
| Bornholm Energy Island (DE-DK) | Approved | PCI status, CEF Energy grant (September 2025 announcement) |
| GriffinLink (DE-GB) | Approved | TenneT/NGESO 2 GW hybrid interconnector concept (late 2030s target) |
NSEC Hamburg Summit (2026)
Germany hosted the January 2026 Hamburg Summit, which produced a joint target to integrate and network up to 100 GW of generation capacity across borders, mandated Offshore TSO Collaboration (OTC) for 2030–2040 project proposals, and multiple bilateral Declarations of Intent on interconnected offshore grids.
Regime Reform & Future Direction
Auction Reform (for 2027)
Following the zero-bid outcome for N-10.1 and N-10.2 in August 2025, the federal government suspended all 2026 offshore wind auctions. The final auction design for 2027 is under development. CfDs remain widely expected following Denmark’s similar pivot after its own failed negative-bidding auction, but have not yet been legislated.
| Reform Area | Status |
|---|---|
| 2026 auctions | Suspended entirely; shifted to 2027 |
| 2027 volumes and design | TBC — to be defined in a future FEP amendment |
| CfDs | Widely expected but not yet legislated |
| Industry calls (BDEW, BWO) | CfDs, supply chain support, inflation indexation, risk-sharing mechanisms |
| Negative bidding | Industry consensus: “dead” as an auction model |
Decommissioning Framework
Alpha ventus (2027–2028 dismantling) will be Germany’s first offshore wind farm decommissioning. BSH must approve the decommissioning concept. Estimated cost: ~€50 million. BSH published a decommissioning and follow-up use status report in January 2026.
Future Grid Architecture
Germany is transitioning from radial connections to multi-terminal hubs (Heide hub, Bornholm Energy Island), with potential for a meshed offshore HVDC grid in the North Sea. Coordination with Dutch, Danish, and Belgian offshore grids via NSEC and BNetzA reform of grid tariff model are advancing in parallel.
Key Sources
Fact Check
This page was fact-checked using automated verification (OpenAI gpt-5.4 with web search). Two iterations were run against the research document, with findings independently verified before corrections were applied.
| Iteration | Date | Errors Reported | Verified & Fixed | False Positives | Summary |
|---|---|---|---|---|---|
| 5 | 2026-03-16 | N/A | 20+ | 0 | Rebased all Zubaunetz tables from NEP 2023 to NEP 2025 2nd draft (Mar 2026). Verified against Tables 20–25 of Kap. 5 Offshore-Netz. BorWin7 NOR-21-1→NOR-6-4, LanWin6 NOR-13-2→NOR-12-3, new LanWin7 (NOR-12-4), NOR-13-2→LanWin8, NOR-5-2 reinstated. Dropped NOR-15-1/18-1/19-3/20-1 and all NOR-x-*. Added Baltic OST-x-1–x-4. Fixed BorWin4 2029→2028, BalWin2 2031→2032. Added NVP locations, route lengths, optimisation context. |
| 4 | 2026-03-16 | N/A | 16 | 0 | Added FEP/NEP grid connection codes to all tables from FEP 2020 and NEP 2023 Projektsteckbriefe. Fixed TSO: DolWin4/BorWin4 are Amprion. Added precise dates from TenneT/50Hertz. |
| 3 | 2026-03-16 | 22 | 11 | 11 | Added missing projects: BorWin4 (900 MW), BalWin5 (2.2 GW, TenneT), Gennaker/OST-6-1 (927 MW, 50Hertz). Fixed grid connection capacities: alpha ventus 60→62 MW, Baltic 1 48→51 MW. Updated construction count 13→16 and capacity sum. |
| 2 | 2026-03-15 | 10 | 7 | 3 | Bornholm capacity inconsistency fixed, removed unsupported NSEC co-chair claim, BSH maritime spatial plan attribution, permitting timelines as statutory targets, compensation formula corrected, offshore levy EnFG differentiation added. |
| 1 | 2026-03-15 | 22 | 11 | 11 | Key fixes: BorWin5→He Dreiht (not Nordseecluster A), DolWin6 official NC 1/NC 2 terminology, NEP naming corrected, O-NEP integration date (2017 not 2023), Hamburg Summit 100 GW wording, Bornholm date 2034. |