German Offshore Wind Grid Connections[Draft]

How offshore wind transmission assets are planned, constructed, and financed in Germany under the centralised TSO model.

Last updated: March 2026 · Sources: BSH, BNetzA, TenneT, 50Hertz, Amprion · Fact-checked 2026-03-16 (5 iterations)

Installed Capacity~9.7 GW
2030 Target30 GW
2045 Target70 GW
NEP Total Pipeline~70.7 GW

Key Regime

Centralised TSO Model TSOs (TenneT, 50Hertz, Amprion) build and operate grid connections. Costs socialised via the offshore grid levy (§17f EnWG).

Key Bodies

BSHBNetzABMWETenneT50HertzAmprion

Key Regulatory Bodies

BodyRoleKey Functions
BSHMaritime & hydrographic authoritySite planning (FEP), offshore wind permitting in EEZ, environmental assessment (StUK4), maritime spatial planning, PINTA data hub
Bundesnetzagentur (BNetzA)Federal energy regulatorOffshore wind auctions, confirms NEP/grid development plan, TSO revenue regulation (ARegV), central site pre-investigation authority (§11 WindSeeG)
BMWEFederal ministryDrafts key legislation (WindSeeG, EnWG, EEG), sets 30/40/70 GW targets, NSEC participation, bilateral energy agreements (Bornholm Energy Island)
BfNNature conservation authorityStatutory consultee for EEZ permitting, species and habitat impact assessment (harbour porpoise, seabirds, Natura 2000), noise mitigation advice
WSVWaterways & shipping adminNavigational safety assessment, formal agreement (Einvernehmen) required for plan approvals under §69 WindSeeG
TenneTTSO (North Sea)Builds and operates North Sea grid connections (~8.9 GW operational). Seven 2 GW ±525 kV HVDC systems planned
50HertzTSO (Baltic Sea + North Sea)Baltic Sea connections (~1.8 GW operational). Ostwind 4 (first Baltic 525 kV HVDC). LanWin3 (North Sea). Multi-terminal hub with TenneT near Heide
AmprionTSO (North Sea, newer)BalWin1 and BalWin2 (2×2 GW, ±525 kV HVDC). Grid interconnection points at Wehrendorf and Westerkappeln
Länder (Federal States)State-level authoritiesPermit cables in territorial waters (12 nm), onshore cable routes, converter station planning. Key states: Lower Saxony, Schleswig-Holstein, Mecklenburg-Vorpommern

Primary Regime Centralised TSO Model

Germany operates a centralised, proactive TSO model for offshore wind grid connections fundamentally different from the UKs OFTO competitive tender model. The state plans sites, pre-investigates them, auctions development rights, and the responsible TSO builds the grid connection at its own cost.

How It Works

StepActorDescription
1. Site planningBSHDesignates offshore wind sites and grid connection systems in the Flächenentwicklungsplan (FEP)
2. Pre-investigationBNetzA / BSHCentral preliminary investigation: geotechnical, environmental, wind, and oceanographic surveys in the EEZ
3. AuctionBNetzADevelopers bid for wind farm development rights on centrally pre-investigated sites
4. Grid connectionTSOResponsible TSO (TenneT, 50Hertz, or Amprion) designs, procures, constructs, and operates the offshore grid connection
5. Wind farmDeveloperWinning bidder builds the wind farm and connects to the TSO’s offshore platform via inter-array cables

Key Legislation

LawScope
WindSeeGPrimary offshore wind act: site planning, auctions, grid connection obligations, 30/40/70 GW targets
EnWGEnergy industry act: TSO grid connection duty (§17d), delay compensation (§17e), offshore grid levy (§17f)
EEGRenewable energy act: priority grid connection, feed-in remuneration framework
ROGSpatial planning act: legal basis for maritime spatial planning in the EEZ
NABEGGrid acceleration act: accelerated planning procedures for transmission lines
SeeAnlGOffshore installations act: pre-WindSeeG permitting regime (legacy)
BNatSchGNature conservation act: species and habitat protection in the EEZ
UVPGEnvironmental impact assessment act

Comparison: Germany vs UK

FeatureGermany (TSO Model)UK (OFTO Model)
Who builds grid connectionTSO (TenneT / 50Hertz / Amprion)Wind farm developer
Who operates grid connectionTSO (permanent)OFTO (25-year licence, competitively tendered)
Cost recoveryOffshore grid levy (socialised)TNUoS charges (socialised)
Grid connection riskTSO bears construction riskDeveloper bears construction risk
Delay compensationTSO pays developer (EnWG §17e)N/A — developer owns the asset
Site planningCentralised (BSH FEP)Developer-led (applies for connection)

Alternative & Legacy Routes

Pre-WindSeeG Regime (SeeAnlG, pre-2017)

Before the WindSeeG entered into force on 1 January 2017, offshore wind projects were permitted under the Seeanlagengesetz (SeeAnlG). Developers applied directly to BSH for individual site permits and arranged grid connections with TenneT. This led to an uncoordinated first come, first served process with significant delays and mismatches between wind farm and grid connection readiness.

Two-Track Auction System (WindSeeG)

TrackSite InvestigationAuction MechanismNotes
Track 1BSH conducts all surveys on behalf of BNetzAQualitative criteria + negative bidding (willingness-to-pay). No market premium — zero-subsidy or pay for concessionQualitative criteria include green hydrogen use, training quotas, PPA commitments, biodiversity measures
Track 2Developers conduct own surveysOriginally lowest market premium; since 2023, zero-cent bids common with dynamic bidding for tie-breakingDevelopers retain more risk but also more flexibility

2025 Auction Failure

In August 2025, Germanys second offshore wind auction of the year attracted zero bids for two centrally pre-investigated North Sea sites (N-10.1, N-10.2, 2.5 GW combined). Root causes included uncapped negative bidding, rising capital costs, supply chain pressures, and declining capture price forecasts.

2026 Auction Suspension

On 28 January 2026, the federal cabinet approved a drafting aid to suspend all 2026 offshore wind auctions and shift them to 2027. On 30 January 2026, BSH amended the FEP 2025 accordingly. The final auction design for 2027 including whether Contracts for Difference (CfDs) will be introduced remains under development.

In December 2025, the Bundestag amended the WindSeeG to allow longer project implementation periods and transpose EU RED III requirements. CfDs were widely expected but were not included in the final text after political opposition.

Consenting & Permitting

BSH is the sole competent authority for offshore wind consenting in the German EEZ. The consenting route depends on whether the site was centrally pre-investigated.

RouteStatutory TimelineApplies To
Plangenehmigung (simplified plan approval)12 months (extendable +3 months)Centrally pre-investigated sites (post-WindSeeG Track 1)
Planfeststellungsbeschluss (full plan approval)18 months (extendable +3 months)Non-centrally pre-investigated or legacy sites (Track 2 / SeeAnlG)

Environmental Impact Assessment (UVP)

RequirementAuthorityLegislation
Environmental Impact Assessment (UVP)BSHUVPG — mandatory for wind farms >20 turbines or turbines >50m
Natura 2000 Assessment (FFH-VP)BSH with BfN consultationBNatSchG §34
Marine species assessmentBSH with BfN consultationBNatSchG — harbour porpoise, seabirds
Noise mitigation during constructionBSHThreshold: 160 dB SEL at 750m from source (pile driving)

Environmental Monitoring (StUK4)

BSH publishes the Standard Investigation of the Impacts of Offshore Wind Turbines on the Marine Environment (StUK4), prescribing baseline surveys and operational monitoring for benthos, fish, marine mammals (harbour porpoise, seals), resting and migrating birds, and bats.

Additional Consents

ConsentAuthorityNotes
Territorial waters cable permitLänder (state) mining/planning authorityFor cable sections within 12 nm
Onshore cable & converter stationVaries by Land (state-level planning authority)Procedural route varies by federal state
Shipping safety assessmentWSVNavigational safety for wind farm layout
Aviation obstruction lightingLuftfahrtbundesamtRequired for turbines >100m
Seabed cable crossing agreementsBSH / cable ownersFor crossing existing subsea cables or pipelines

Typical Timeline (Centrally Pre-Investigated Site)

PhaseDurationDescription
FEP designation + site pre-investigation3–5 yearsBSH-led, before auction
Auction awardBNetzA conducts tender
Plangenehmigung (plan approval)12 months (statutory)Developer submits application, BSH reviews
Final Investment Decision6–12 monthsPost-approval
Construction2–3 yearsWind farm + internal cabling
Grid connection commissioningPer FEP scheduleTSO builds in parallel
Total (auction to power)~5\u20137 yearsDepends on grid connection readiness

Grid Connection & System Planning

Flächenentwicklungsplan (FEP / Site Development Plan)

Published by BSH (first edition 28 June 2019, current: FEP 2025 amended January 2026). The FEP is the master planning document that designates offshore wind sites, specifies which grid connection system serves each site, and sets commissioning timelines synchronised between wind farm and grid connection.

FEP 2025 ParameterValue
New sites for auction (2025–2028)10 sites, 12 GW total
New North Sea areas identifiedN-9, N-12, N-13 (8 GW expected)
New areas scheduled for operation6 GW by end of 2034

Netzentwicklungsplan (NEP / Grid Development Plan)

Prepared biennially by the four German TSOs (TenneT, 50Hertz, Amprion, TransnetBW) and confirmed by BNetzA. Since 2017, the previously separate Offshore-Netzentwicklungsplan (O-NEP) has been integrated into the main NEP.

NEP Strom 20232037/2045 confirmed by BNetzA: 25,980 MW of offshore transmission capacity scheduled across 16 grid connection systems between 2026 and 2032. Of these: 11 systems at 2 GW (±525 kV HVDC), 4 systems at 1 GW (±320 kV HVDC), and 1 AC system.

2 GW Standard Platform Programme

The next generation of German offshore grid connections uses a standardised 2 GW ±525 kV HVDC platform design, replacing the previous ~900 MW±320 kV standard. Benefits include higher capacity per connection (2× improvement), reduced platform count, standardised design enabling serial production, and lower per-MW connection costs.

ProgrammeKey Details
TenneT 2 GW ProgrammeSeven 2 GW systems for German North Sea (plus seven for Netherlands). First platforms: BalWin4 and LanWin1 (2029–2030). Major contracts: McDermott (BalWin4/LanWin1), Dragados (LanWin2/LanWin4/LanWin5). Cables: NKT, Nexans (525 kV HVDC)
50Hertz Ostwind 4First 2 GW 525 kV HVDC system in Baltic Sea. GE Vernova converter (with Drydocks World). NKT cables (~110 km DC cable system). Location: 30 km NE of Rügen Island

Multi-Terminal Hub (50Hertz + TenneT)

50Hertz and TenneT are cooperating on an innovative multi-terminal HVDC hub near Heide, Schleswig-Holstein. This connects 4 GW of North Sea offshore wind by 2032 via ~200 km of 525 kV DC underground cable from Heide to Klein Rogahn (near Schwerin) in Mecklenburg-Vorpommern the first German multi-terminal offshore hub, enabling future meshed grid concepts.

Financial & Commercial Framework

Offshore Grid Levy (Offshore-Netzumlage)

ParameterDetail
Introduced2013
Legal basisEnWG §17f, administered under EnFG §§10–11
Purpose (original)Fund compensation to wind farm operators for grid connection delays/disruptions
Purpose (expanded 2019)Also covers TSO costs of constructing and operating offshore connection lines
Paid byAll electricity consumers, added to electricity price
Rate (2025)0.816 ct/kWh
Rate (2026)0.941 ct/kWh
Set byFour German TSOs jointly; published by 25 October each year
Published atnetztransparenz.de

Grid Connection Delay Compensation (§17e EnWG)

ParameterDetail
TriggerWind farm ready but prevented from feeding in for >10 consecutive days due to delayed grid connection, outage, or maintenance
Compensation rate90% of remuneration the operator would have received (from day 11)
Liability capTSO liability capped under §17e; excess costs socialised via offshore grid levy
Recent amendmentDeductibles removed for offshore wind farm operators; implementation periods extended

Wind Farm Revenue Framework

PeriodMechanism
Pre-2017 projectsFixed feed-in tariffs (FiT) under EEG
Post-2017 Track 1Zero-subsidy / negative bidding model (2017–2025). 2026 auctions suspended; new design (potentially CfDs) under development for 2027
Post-2017 Track 2Market premium via competitive auction; since 2023, zero-cent bids common with dynamic bidding for tie-breaking

Grid Connection Cost Allocation

TSOs bear 100% of offshore grid connection costs (converter platforms, export cables to shore, onshore converter stations). These costs are recovered via the offshore grid levy, socialised across all electricity consumers. Wind farm developers bear costs of inter-array cables from turbines to the TSOs offshore platform.

Estimated total offshore grid connection investment: 160 billion (cumulative, to meet 2045 targets).

Bilateral & International Cooperation

North Seas Energy Cooperation (NSEC)

Germany is a member of the NSEC (established 2016). Members: Belgium, Denmark, France, Germany, Ireland, Luxembourg, the Netherlands, Norway, and the European Commission. Germany hosted the third international North Sea Summit in Hamburg on 26 January 2026.

Hamburg Declaration (January 2026): North Sea countries agreed to integrate and network up to 100 GW of generation capacity across borders. Joint Declarations of Intent signed on interconnected offshore renewable energy grid and North Sea infrastructure cooperation.

Key Bilateral Agreements

PartnerAgreementProject
DenmarkBilateral agreement signed 26 January 2026 at Hamburg SummitBornholm Energy Island: 3 GW total offshore wind connected to Germany and Denmark. 2 GW HVDC link to Germany (50Hertz), separate link to Zealand (Energinet). Target: 2034
DenmarkMoU for Amprion hybrid interconnectorPlanned hybrid DE-DK North Sea interconnector
BelgiumPart of NSEC frameworkPlanned DE-BE hybrid offshore link
NetherlandsCooperation via NSECPotential multi-terminal offshore hub concepts

Germany signed an Offshore Realisation Agreement (November 2022) setting the ambition at 50 GW installed by 2035 exceeding the WindSeeG statutory minimum of 40 GW.

Historical Evolution

  1. BSH permits alpha ventus (then 'Borkum West')

    First German offshore wind farm permitted under SeeAnlG.
  2. First offshore grid connection

    TenneT completes alpha ventus grid connection (60 MW, 110 kV AC, ~67 km cable via Norderney).
  3. Alpha ventus fully commissioned

    Germanys first offshore wind farm: 12 × 5 MW turbines, 60 MW total. First HVDC offshore grid connection: BorWin1 (400 MW) commissioned December 2010.
  4. Offshore grid levy introduced

    Offshore-Netzumlage introduced to fund grid connection delay compensation.
  5. Rapid grid connection expansion

    DolWin1, HelWin1, HelWin2, SylWin1, BorWin2 commissioned. German offshore wind crosses 3 GW installed.
  6. WindSeeG enters into force

    Centralised site planning and two-track auction system. First auctions produce zero-subsidy bids (He Dreiht, Gode Wind 3+4).
  7. FEP published & 7.5 GW installed

    First Flächenentwicklungsplan published by BSH. BorWin3 (900 MW) commissioned. Offshore grid levy expanded to cover construction/operation costs.
  8. Targets raised & Realisation Agreement

    WindSeeG amended: targets raised to 30/40/70 GW (2030/2035/2045). Offshore Realisation Agreement signed: 50 GW by 2035.
  9. First negative-bidding auctions

    First negative-bidding auctions for centrally pre-investigated sites. DolWin6 (900 MW) commissioned.
  10. DolWin5 commissioned; 9.2 GW installed

    DolWin5 (900 MW) commissioned. Ostwind 2 fully operational (750 MW Baltic Sea).
  11. BorWin5 commissioned; auction failure

    BorWin5 (900 MW) commissioned. August: second auction receives zero bids (2.5 GW). Alpha ventus consortium decides on decommissioning. Total: ~9.7 GW. December: Bundestag amends WindSeeG.
  12. Auctions suspended; Hamburg Summit

    28 January: cabinet approves suspension of 2026 auctions. 26 January: Hamburg North Sea Summit Bornholm Energy Island bilateral agreement signed. Ostwind 3 (300 MW) expected September 2026.

Current Grid Connection Systems

Operational North Sea (TenneT)

SystemCodeCapacityTechnologyCommissioned
alpha ventusNOR-2-162 MW110 kV AC2009
BorWin1NOR-6-1400 MW±150 kV HVDCDec 2010
RiffgatNOR-0-1113 MW155 kV AC2014
BorWin2NOR-6-2800 MW±300 kV HVDC2015
DolWin1NOR-2-2800 MW±320 kV HVDC2015
HelWin1NOR-4-1576 MW±250 kV HVDC2015
HelWin2NOR-4-2690 MW±320 kV HVDC2015
SylWin1NOR-5-1864 MW±320 kV HVDC2015
DolWin2NOR-3-1916 MW±320 kV HVDC2016
NordergründeNOR-0-2111 MW155 kV AC2017
DolWin3NOR-2-3900 MW±320 kV HVDC2018
BorWin3NOR-8-1900 MW±320 kV HVDC2019
DolWin6NOR-3-3900 MW±320 kV HVDC2023
DolWin5NOR-1-1900 MW±320 kV HVDCOct 2024
BorWin5NOR-7-1900 MW±320 kV HVDCDec 2025
Total North Sea~8.9 GW

Operational Baltic Sea (50Hertz)

SystemCodeCapacityTechnologyCommissioned
Baltic 1OST-3-151 MW150 kV AC2011
Baltic 2OST-3-2288 MW150 kV AC2015
Ostwind 1OST-1-1/1-2/1-3750 MW150/220 kV AC2018–2019
Ostwind 2OST-2-1/2-2/2-3750 MW220 kV AC2023–2024
Total Baltic Sea~1.8 GW

Under Construction / Approved

SystemCodeTSOCapacityTechnologyExpected
Ostwind 3OST-1-450Hertz300 MW220 kV AC30 Sep 2026
BorWin6NOR-7-2TenneT980 MW±320 kV HVDC1 Oct 2027
DolWin4NOR-3-2Amprion900 MW±320 kV HVDC2028
BorWin4NOR-6-3Amprion900 MW±320 kV HVDC2028
GennakerOST-6-150Hertz927 MWAC2028
BalWin4NOR-9-3TenneT2,000 MW±525 kV HVDC2029
BalWin1NOR-9-1Amprion2,000 MW±525 kV HVDC2030
LanWin1NOR-12-1TenneT2,000 MW±525 kV HVDC2030
LanWin2NOR-12-2TenneT2,000 MW±525 kV HVDC2030
Ostwind 4OST-2-450Hertz2,000 MW±525 kV HVDC2031
BalWin3NOR-9-2TenneT2,000 MW±525 kV HVDC2031
LanWin4NOR-11-2TenneT2,000 MW±525 kV HVDC2031
LanWin5NOR-13-1TenneT2,000 MW±525 kV HVDC2031
BalWin2NOR-10-1Amprion2,000 MW±525 kV HVDC2032
LanWin3NOR-11-150Hertz2,000 MW±525 kV HVDC2032
BalWin5NOR-9-4TenneT2,000 MW±525 kV HVDC2033

Planned Hybrid Projects

SystemTSOCapacityExpectedNotes
Bornholm Energy Island (DE leg)50Hertz2,000 MWMid-2030sBilateral DE-DK. Siemens Energy converter (Sep 2025). ~173 km route. NKT cables (3,500 km total across all BEI links). World’s first hybrid DC interconnector

NEP 2025 Zubaunetz Future Grid Connection Systems

The NEP 2037/2045 (version 2025, 2nd draft, March 2026) identifies the additional offshore grid connection systems (ONAS) required beyond the Startnetz to reach the statutory target of at least 70 GW by 2045 (§1(2) WindSeeG). For the first time, the TSOs applied offshore optimisation measures developed with the Fraunhofer Institute for Wind Energy Systems (IWES): adjusted area layouts reduce wake effects, raising full-load hours to ~3,900 h/year; mandatory overplanting (20% above ONAS capacity); and investigation of increasing ONAS transmission from 2.0 to 2.2 GW. The result: the same energy yield (238 TWh in Scenario B 2045) can be achieved with 47 fewer ONAS than the confirmed NEP 2023 saving billions in converter, cable, and installation costs that have risen sharply due to supply chain pressures.

No ONAS commissioning is planned for 2035 the TSOs intentionally schedule a gap year to relieve strained supply chains after the concentrated 20282033 build-out. Two ONAS then commission in 2036 to compensate. This draft awaits BNetzA confirmation; the tables below reflect the 2nd draft (Scenario B 2045 as maximum envelope).

Key change from NEP 2023: Several system codes were renumbered. BorWin7 moved from NOR-21-1 to NOR-6-4; LanWin6 from NOR-13-2 to NOR-12-3; NOR-13-2 is now LanWin8 (not LanWin6). NOR-5-2 (Sylt cluster) has been reinstated after being absent from the 2023 plan. NOR-15-1, NOR-18-1, NOR-19-3, NOR-20-1, and all NOR-x-* placeholder systems from the 2023 plan have been dropped.

North Sea Zubaunetz (Table 24, NEP 2025 2nd Draft)

SystemCodeTSONVP (Onshore)kmMWScenario B 2045
BorWin7NOR-6-4AmprionKusenhorst4512,0002034
LanWin6NOR-12-350HertzPöschendorf3082,0002034
LanWin7NOR-12-4TenneTPöschendorf3422,0002034
NOR-14-2AmprionRommerskirchen6332,0002036
NOR-16-1TenneTHardebek3652,0002036
NOR-16-250HertzBBS (SH)4382,0002037
NOR-14-1TenneTGroßenmeer3102,0002037
NOR-16-3AmprionRommerskirchen6442,0002037
NOR-16-4AmprionKriftel8482,0002038
NOR-17-1AmprionRied9162,0002039
NOR-17-2TenneTNüttermoor3672,0002039
LanWin8NOR-13-250HertzBBS (SH)4282,0002040
NOR-5-2AmprionNiederrhein5082,0002041
NOR-19-1TenneTEsens3792,0002042
NOR-19-2AmprionEsens3952,0002043
NOR-5-3AmprionSechtem6472,0002044

Baltic Sea Zubaunetz (Table 25, NEP 2025 2nd Draft)

No new Baltic Sea connections are planned in the 2037 scenarios. In all 2045 scenarios, an additional 1 GW is assumed in the Mecklenburg-Vorpommern coastal waters, pending completion of the state spatial development plan. Wind farm areas for these systems have not yet been designated.

CodeTSONVP (Onshore)CapacityTechnologyExpected
OST-x-150HertzGnewitz250 MWAC2039
OST-x-250HertzGnewitz250 MWAC2039
OST-x-350HertzKemnitz250 MWAC2040
OST-x-450HertzKemnitz250 MWAC2040

Capacity Summary

CategoryCountCapacity
Operational North Sea15~8.9 GW
Operational Baltic Sea4~1.8 GW
Under construction / approved (Startnetz + Gennaker)16~25.0 GW
Planned hybrid (Bornholm DE leg)12.0 GW
NEP 2025 Zubaunetz North Sea1632.0 GW
NEP 2025 Zubaunetz Baltic Sea41.0 GW
Total pipeline56~70.7 GW
Government targets: 30 GW installed by 2030, 40 GW by 2035 (statutory minimum; 50 GW ambition via Offshore Realisation Agreement), and 70 GW by 2045.

Supranational Dimension

EU Regulatory Framework

FrameworkRelevance
TEN-E Regulation (EU 2022/869)PCI/PMI designation for cross-border offshore projects (e.g. Bornholm Energy Island). Cross-border cost allocation (PS-CBCA) mechanisms
Revised RED IIIPartially transposed via December 2025 WindSeeG amendment. Offshore renewable acceleration area provisions
EU Offshore RE Strategy (2020)EU target: 300 GW offshore wind by 2050 across all EU sea basins
EU MSP DirectiveImplemented via German Maritime Spatial Plan (Raumordnungsplan 2021)
EU EIA Directive (2011/92/EU)Transposed into UVPG

ENTSO-E Offshore Network Development Plan (ONDP)

The first ONDP (published 2024 as part of TYNDP) identified the Northern Seas corridor as requiring approximately 274 GW of offshore wind capacity by 2040. Germanys 16+ grid connection systems are central to the North Sea and Baltic corridors. Estimated total European offshore transmission CAPEX: ~400 billion (20252050).

PCI/PMI Projects Involving Germany

ProjectStatusNotes
Bornholm Energy Island (DE-DK)ApprovedPCI status, CEF Energy grant (September 2025 announcement)
GriffinLink (DE-GB)ApprovedTenneT/NGESO 2 GW hybrid interconnector concept (late 2030s target)

NSEC Hamburg Summit (2026)

Germany hosted the January 2026 Hamburg Summit, which produced a joint target to integrate and network up to 100 GW of generation capacity across borders, mandated Offshore TSO Collaboration (OTC) for 20302040 project proposals, and multiple bilateral Declarations of Intent on interconnected offshore grids.

Regime Reform & Future Direction

Auction Reform (for 2027)

Following the zero-bid outcome for N-10.1 and N-10.2 in August 2025, the federal government suspended all 2026 offshore wind auctions. The final auction design for 2027 is under development. CfDs remain widely expected following Denmarks similar pivot after its own failed negative-bidding auction, but have not yet been legislated.

Reform AreaStatus
2026 auctionsSuspended entirely; shifted to 2027
2027 volumes and designTBC — to be defined in a future FEP amendment
CfDsWidely expected but not yet legislated
Industry calls (BDEW, BWO)CfDs, supply chain support, inflation indexation, risk-sharing mechanisms
Negative biddingIndustry consensus: “dead” as an auction model

Decommissioning Framework

Alpha ventus (20272028 dismantling) will be Germanys first offshore wind farm decommissioning. BSH must approve the decommissioning concept. Estimated cost: ~50 million. BSH published a decommissioning and follow-up use status report in January 2026.

Future Grid Architecture

Germany is transitioning from radial connections to multi-terminal hubs (Heide hub, Bornholm Energy Island), with potential for a meshed offshore HVDC grid in the North Sea. Coordination with Dutch, Danish, and Belgian offshore grids via NSEC and BNetzA reform of grid tariff model are advancing in parallel.

Fact Check

This page was fact-checked using automated verification (OpenAI gpt-5.4 with web search). Two iterations were run against the research document, with findings independently verified before corrections were applied.

IterationDateErrors ReportedVerified & FixedFalse PositivesSummary
52026-03-16N/A20+0Rebased all Zubaunetz tables from NEP 2023 to NEP 2025 2nd draft (Mar 2026). Verified against Tables 20–25 of Kap. 5 Offshore-Netz. BorWin7 NOR-21-1→NOR-6-4, LanWin6 NOR-13-2→NOR-12-3, new LanWin7 (NOR-12-4), NOR-13-2→LanWin8, NOR-5-2 reinstated. Dropped NOR-15-1/18-1/19-3/20-1 and all NOR-x-*. Added Baltic OST-x-1–x-4. Fixed BorWin4 2029→2028, BalWin2 2031→2032. Added NVP locations, route lengths, optimisation context.
42026-03-16N/A160Added FEP/NEP grid connection codes to all tables from FEP 2020 and NEP 2023 Projektsteckbriefe. Fixed TSO: DolWin4/BorWin4 are Amprion. Added precise dates from TenneT/50Hertz.
32026-03-16221111Added missing projects: BorWin4 (900 MW), BalWin5 (2.2 GW, TenneT), Gennaker/OST-6-1 (927 MW, 50Hertz). Fixed grid connection capacities: alpha ventus 60→62 MW, Baltic 1 48→51 MW. Updated construction count 13→16 and capacity sum.
22026-03-151073Bornholm capacity inconsistency fixed, removed unsupported NSEC co-chair claim, BSH maritime spatial plan attribution, permitting timelines as statutory targets, compensation formula corrected, offshore levy EnFG differentiation added.
12026-03-15221111Key fixes: BorWin5→He Dreiht (not Nordseecluster A), DolWin6 official NC 1/NC 2 terminology, NEP naming corrected, O-NEP integration date (2017 not 2023), Hamburg Summit 100 GW wording, Bornholm date 2034.
This reference is provided for informational purposes. Regulatory frameworks are complex and subject to change. Always consult primary sources and professional advisors for decisions. Last reviewed March 2026.