Belgian Offshore Wind Grid Connections[Draft]
How offshore wind transmission assets are planned, constructed, and financed in Belgium under the federal concession model with centralised TSO grid.
Last updated: March 2026 · Sources: FPS Economy, CREG, Elia, RBINS/MUMM · Fact-checked 2026-03-15 (2 iterations)
Key Regime
Federal Concession + TSO Grid — Federal minister grants domain concessions. Elia builds and owns all offshore grid infrastructure (MOG, Princess Elisabeth Island).
Key Bodies
Key Regulatory Bodies
| Body | Role | Key Functions |
|---|---|---|
| FPS Economy (DG Energy) | Federal ministry | Administers offshore wind domain concessions. Organises PEZ tenders. Issues cable-laying permits. Advises Minister of Energy on applications |
| CREG | Federal energy regulator | Issues Green Certificates (1 per MWh). Proposes LCOE/strike prices for CfD. Approves transmission tariffs. Advises on concessions and network development plans |
| Elia | TSO & offshore grid owner | Sole TSO (20-year designation, renewed Sep 2022). Builds and operates MOG, MOG II, and Princess Elisabeth Island. 8,903 km of HV lines. Green Certificate purchase obligation |
| Minister of Energy | Federal minister | Grants domain concessions. Issues cable permits. Approves network development plan (jointly with Minister of North Sea). Sets maximum CfD strike price |
| RBINS / OD Nature / MUMM | Marine science & EIA | Receives Environmental Impact Studies. Produces independent EIA. Recommends to Minister on environmental permits. Coordinates WinMon.BE monitoring programme (since 2008) |
| FPS Health (Marine Environment) | Environmental permits | Issues marine protection permits via Minister for Marine Environment. Coordinates Marine Spatial Plan (MSP 2020–2026). Administers Natura 2000 marine approvals |
| Flemish Government / VREG | Onshore permitting | Environmental and spatial planning permits for onshore cable landfall and grid reinforcement (e.g., Ventilus 380 kV line). VREG regulates onshore grid access/tariffs |
| Belgian Coast Guard | Maritime safety | Coordinates maritime safety around wind farms. Monitors exclusion zones. Joint Flemish-federal body (est. 2003–2005) |
Primary Regime — Federal Concession Model
Belgium operates a federal concession model for offshore wind. The federal Minister of Energy grants domain concessions giving developers the right to build and operate wind farms in designated marine areas. Elia builds and owns all offshore grid infrastructure separately.
How It Works
| Step | Actor | Description |
|---|---|---|
| 1. Marine spatial planning | FPS Health | Marine Spatial Plan designates offshore wind zones (original zone + Princess Elisabeth Zone) |
| 2. Domain concession | Minister of Energy | Grants concession for wind farm development. Open-door (Zone 1) or competitive tender (PEZ) |
| 3. Environmental permit | Minister for Marine Environment | Marine protection permit based on EIA by RBINS/MUMM. 45-day public consultation |
| 4. Cable permit | Minister of Energy | Cable-laying permit for submarine export cables |
| 5. Grid connection | Elia | TSO builds offshore grid hub (MOG/MOG II/Princess Elisabeth Island). Wind farms connect to the hub |
Key Legislation
| Law | Scope |
|---|---|
| Electricity Act (29 April 1999) | Primary offshore wind law. Articles 6–7: domain concessions, cable permits, support scheme |
| Law of 12 May 2019 | Amended Electricity Act to introduce competitive tenders for PEZ |
| Marine Environment Protection Act (20 Jan 1999) | Environmental permits for offshore installations. EIA requirements |
| Royal Decree of 20 December 2000 | Domain concession application procedure and award criteria |
| Royal Decree of 12 March 2002 | Cable-laying permit procedure |
| Royal Decree of 20 March 2014 | Marine Spatial Plan establishing offshore wind zones |
| Royal Decree of 3 June 2024 | New offshore grid framework: Elia builds all PEZ grid; costs fully socialised |
Comparison: Belgium vs UK vs Germany
| Feature | Belgium (Concession) | UK (OFTO Model) | Germany (TSO Model) |
|---|---|---|---|
| Who plans sites | Federal MSP (FPS Health) | Developer-led (Crown Estate) | BSH via FEP |
| Who builds grid | Elia (TSO) — MOG/PEI | Developer (transfers to OFTO) | TSO (TenneT / 50Hertz / Amprion) |
| Who operates grid | Elia (permanent) | OFTO (25-year licence) | TSO (permanent) |
| Cost recovery (PEZ) | Fully socialised via tariffs | TNUoS charges | Offshore grid levy |
| Support mechanism | Green Certificates (Zone 1) / CfD (PEZ) | Two-way CfD (AR rounds) | Zero-subsidy / negative bidding |
| Federal/regional split | Yes — North Sea federal, onshore Flemish | No — single jurisdiction | Yes — EEZ federal, territorial waters Länder |
Zone 1 & Princess Elisabeth Zone
Zone 1: Original Offshore Wind Zone (2008–2020)
Belgium’s first offshore wind zone (~238 km²) was designated in the Marine Spatial Plan of March 2014. Nine wind farms were built between 2008 and 2020, reaching a total installed capacity of 2,261 MW. Early farms had individual export cables to shore; later farms connected via Elia’s Modular Offshore Grid (MOG) platform.
Support Mechanism Evolution
| Vintage | Mechanism | Price | Duration |
|---|---|---|---|
| C-Power, Belwind, Northwind, Nobelwind | Green Certificates (fixed) | €107/MWh (first 216 MW); €90/MWh above | 20 years |
| Rentel | Green Certificates (LCOE-based) | €129.80/MWh | 19 years |
| Norther | Green Certificates (LCOE-based) | €124/MWh | 19 years |
| Mermaid, SeaStar, Northwester 2 | Green Certificates (LCOE-based) | €79/MWh | 17 years |
| PEZ (from 2026) | Two-sided CfD | Max €95/MWh (tender) | 20 years |
Princess Elisabeth Zone (PEZ)
Designated in the Marine Spatial Plan 2020–2026, the PEZ is a 285 km²zone at the border with France, ~45 km offshore. It will add 3.15–3.5 GW across three lots, bringing Belgium’s total to ~5.8 GW.
| Lot | Area | Capacity | Status |
|---|---|---|---|
| Lot 1 (Noordhinder North) | ~46 km² | 700 MW | Tender launched Nov 2024; postponed to Q1 2026 |
| Lot 2 (Noordhinder South) | TBC | 1,225–1,400 MW | Planned 2026–2028 |
| Lot 3 (Fairybank) | TBC | 1,225–1,400 MW | Planned 2026–2028; delayed ~3 years (HVDC issues) |
PEZ Tender Framework
| Parameter | Detail |
|---|---|
| Mechanism | Two-sided Contract for Difference (CfD) |
| Maximum strike price | €95/MWh |
| Contract duration | 20 years |
| Award criteria | 90% strike price, 10% business model innovation |
| EU State aid approval | €682 million scheme approved September 2024 |
| Minimum experience | 300 MW realised offshore wind (Lot 1) |
| Commissioning deadline | 42 months (max 48) after bid announcement |
Consenting & Permitting
Belgium’s offshore wind consenting involves three federal permits plus onshore Flemish permits. The federal/regional split means offshore and onshore consenting run on separate tracks.
Federal Permits (Offshore)
| Permit | Authority | Description |
|---|---|---|
| Domain Concession | Minister of Energy (FPS Economy) | Right to build and operate a wind farm in a designated marine area. Up to 20 years, extendable to max 30. Open-door (Zone 1) or competitive tender (PEZ) |
| Environmental Permit (Marine Protection) | Minister for Marine Environment | Based on EIA by RBINS/MUMM. 45-day public consultation including neighbouring countries. Construction authorisation (5 years, extendable); operating licence (20 years) |
| Cable Permit | Minister of Energy | For submarine power cable laying. Impact study on existing grid required. Proof of financial/technical capacity |
Regional Permits (Onshore — Flanders)
| Permit | Authority | Notes |
|---|---|---|
| Environmental permit (onshore) | Flemish Government | For cable landfall, converter stations, onshore grid reinforcement |
| Spatial planning permit | Flemish Government | For onshore infrastructure siting |
| Ventilus 380 kV line | Flemish Minister of Environment | Critical onshore reinforcement. 5 permit applications submitted Sep 2025. Decision expected end Apr 2026 |
Environmental Assessment
| Assessment | Authority | Notes |
|---|---|---|
| Environmental Impact Study (EIS) | Applicant submits to RBINS/MUMM | Mandatory for all offshore wind projects |
| Environmental Impact Assessment (EIA) | RBINS/MUMM produces independently | Formal procedure ~155 days. Recommendations to Minister |
| WinMon.BE monitoring | RBINS coordinates | Long-term marine ecosystem monitoring since 2008 |
| Natura 2000 assessment | FPS Health | Required for projects near/in Natura 2000 sites |
Typical Timeline
| Phase | Duration | Description |
|---|---|---|
| Marine spatial planning | Multi-year | Government-led zone designation via MSP |
| Tender process (PEZ) | ~12 months | From launch to winner announcement |
| Environmental permit | 6–8 months | EIS submission, EIA, public consultation, ministerial decision |
| Domain concession | Several months | Application, evaluation, ministerial grant |
| Onshore permits (Flemish) | 12–24 months | Environmental and spatial planning permits |
| Construction | 2–3 years | Wind farm and grid connection |
| Total (PEZ: tender to power) | ~4\u20135 years | 42–48 months from bid to commissioning (target) |
Grid Connection & System Planning
Elia as Offshore Grid Builder
Elia is Belgium’s sole TSO and builds, owns, and operates all offshore grid infrastructure. The grid model has evolved from individual radial connections (early farms) to centralised hubs (MOG, Princess Elisabeth Island).
Modular Offshore Grid (MOG)
| Parameter | Detail |
|---|---|
| Commissioned | September 2019 |
| Technology | 220 kV HVAC switching platform |
| Capacity | ~1,030 MW (4 wind farms: Rentel, SeaStar, Mermaid, Northwester 2) |
| Export cables | Three 220 kV submarine cables to Zeebrugge (Stevin substation) |
| Investment | ~€400 million |
| Availability | 99.998% (2020); effectively 100% in other years |
| Energy transported | >14.75 TWh since commissioning |
Princess Elisabeth Island (MOG II)
| Parameter | Detail |
|---|---|
| Type | World’s first artificial energy island |
| Location | ~45 km offshore in the PEZ |
| Capacity | Up to 3.5 GW (PEZ wind farms) + international interconnectors |
| Technology | Both HVAC and HVDC — first island to combine both |
| HVDC capacity | Upgraded from 1,400 MW to 2,000 MW |
| Construction | 23 concrete caissons (~22,000 tonnes each). First placed April 2025 |
| Interconnectors | Landing point for Nautilus (BE–UK) and TritonLink (BE–DK) |
| Investment | Originally €3.6bn; escalated to €7–8bn (HVDC supply chain costs) |
| EIB financing | €650 million green credit facility (October 2024) |
| Target ready | First wind farms ~2030 |
Grid Connection Costs
| Zone | Cost Model |
|---|---|
| Zone 1 (original) | Partially socialised: Elia funds up to 1/3 of cable costs (max €25M for ≥216 MW). Developer bears remaining 2/3 |
| PEZ (new regime, RD 3 June 2024) | Fully socialised: Elia builds entire offshore grid. Costs recovered via regulated transmission tariffs from all consumers |
Onshore Reinforcements
| Project | Specification | Status |
|---|---|---|
| Ventilus | 380 kV HVAC, ~82 km (Zeebrugge–Avelgem) | 5 Flemish permit applications Sep 2025. Public enquiry Feb–Mar 2026. Decision expected end Apr 2026 |
| Boucle du Hainaut | 380 kV reinforcement in Hainaut | Facing public resistance. Required for full PEZ integration |
Financial & Commercial Framework
Zone 1: Green Certificate Scheme
Zone 1 wind farms receive federal Green Certificates (1 per MWh of net production) issued by CREG. Elia has a legal purchase obligation at a guaranteed minimum price set by the Federal Government. The dramatic price drop from €107/MWh to €79/MWh across vintages reflects technology cost reductions.
PEZ: Two-Sided CfD
| Parameter | Detail |
|---|---|
| Mechanism | Two-sided Contract for Difference |
| Maximum strike price | €95/MWh |
| Duration | 20 years |
| EU State aid approval | €682 million scheme (September 2024) |
| Green certificates | Not granted to PEZ concessionaires |
| Consumer protection | Developer pays back when market price exceeds strike price |
Grid Cost Recovery
| Mechanism | Detail |
|---|---|
| Offshore surcharge | On electricity bills since 2012 to fund GC purchase obligation |
| Nuclear levy offset | Two-thirds of offshore surcharge funded via nuclear levy |
| Solidarity contribution | From 2023: offshore wind revenues capped; excess returned to consumers |
| PEI infrastructure costs | Classified as essential infrastructure under EU rules; Elia recovers via tariffs over several years |
Historical Evolution
First concession zone designated
Belgium designates a 156 km² area in its EEZ for offshore wind.C-Power Phase 1 installed
First 6 turbines at Thornton Bank (30 MW). Belgium’s first offshore wind electricity fed to the grid in 2009.Belwind commissioned (165 MW)
Second Belgian offshore wind farm, completed December 2010.C-Power reaches full capacity (325 MW)
Phases 2 and 3 completed with jacket foundations.Northwind + first Marine Spatial Plan
Northwind commissioned (216 MW). Belgium adopts MSP 2014–2020, one of the first countries globally to do so.Nobelwind commissioned (165 MW)
Fifth wind farm in Zone 1.Rentel commissioned (309 MW)
First farm connected via the Modular Offshore Grid (MOG).MOG commissioned + PEZ designated
Elia’s MOG platform operational (September). Marine Spatial Plan 2020–2026 designates the Princess Elisabeth Zone (285 km²).Zone 1 fully built out (2,261 MW)
SeaMade (Mermaid + SeaStar, 487 MW) and Northwester 2 (219 MW) complete. Nine wind farms, 100% on time and budget.Esbjerg Declaration signed (May)
Belgium among 4 countries committing to 65 GW by 2030, 150 GW by 2050.Ostend Summit hosted by Belgium (April)
9 countries sign Ostend Declaration: 120 GW by 2030, 300 GW by 2050. Princess Elisabeth Island receives environmental permit (October).PEZ tender + EU State aid approval
EU approves €682M CfD scheme (September). PEZ Lot 1 tender launched (November). EIB commits €650M for PEI. Nautilus approved by Ofgem (November).PEI construction + tender delay
First caissons placed at sea (April). PEZ Lot 1 tender postponed by Minister Bihet (July). HVDC contracts shelved (June) due to cost escalation. Ventilus permit applications submitted (September).Hamburg Investment Pact signed (January)
Belgium signs €1 trillion collective offshore wind commitment. PEZ Lot 1 tender relaunch planned Q1 2026. Ventilus decision expected April 2026.
Current & Planned Grid Connection Systems
Zone 1 — Operational (2,261 MW)
| Wind Farm | Capacity | Turbines | Commissioned | Grid Connection |
|---|---|---|---|---|
| C-Power | 325 MW | 54 | 2009–2013 | Direct to shore |
| Belwind | 171 MW | 56 | 2010 | Direct to shore |
| Northwind | 216 MW | 72 × 3 MW | 2014 | Direct to shore |
| Nobelwind | 165 MW | 50 × 3.3 MW | 2017 | Direct to shore |
| Norther | 370 MW | 44 | 2019 | Direct to shore |
| Rentel | 309 MW | 42 × 7.35 MW | 2018 | Via MOG |
| SeaStar (SeaMade) | ~252 MW | — | 2020 | Via MOG |
| Mermaid (SeaMade) | ~235 MW | — | 2020 | Via MOG |
| Northwester 2 | 219 MW | 23 × 9.5 MW | 2020 | Via MOG |
Princess Elisabeth Zone — Planned (~3.5 GW)
| Lot | Capacity | Grid Connection | Expected COD |
|---|---|---|---|
| Lot 1 (Noordhinder North) | 700 MW | HVAC via PEI | ~2029–2030 |
| Lot 2 (Noordhinder South) | 1,225–1,400 MW | HVAC via PEI | ~2030 |
| Lot 3 (Fairybank) | 1,225–1,400 MW | HVDC via PEI | ~2033 (delayed) |
Capacity Summary
| Category | Capacity |
|---|---|
| Zone 1 operational | 2,261 MW |
| PEZ planned | ~3,150–3,500 MW |
| Total (by ~2030\u20132033) | ~5,400\u20135,800 MW |
| Further ambition (2040) | ~8,000 MW |
Supranational Dimension
NSEC Leadership
Belgium is a founding member of the North Seas Energy Cooperation (NSEC) and has been one of its most active participants. Belgium hosted the Ostend North Sea Summit (April 2023) where 9 countries committed to 300 GW by 2050.
North Sea Summits
| Summit | Location | Key Commitment |
|---|---|---|
| Esbjerg (May 2022) | Denmark | 4 countries: 65 GW by 2030, 150 GW by 2050 |
| Ostend (April 2023) | Belgium (host) | 9 countries: 120 GW by 2030, 300 GW by 2050 |
| Hamburg (January 2026) | Germany | €1 trillion Investment Pact. 100 GW by 2050 joint target |
Hybrid Interconnector Projects
| Project | Partners | Capacity | Target | Status |
|---|---|---|---|---|
| Nautilus | Elia + National Grid | TBC | 2028+ | PCI/PMI. Ofgem approved Nov 2024. Study phase |
| TritonLink | Elia + Energinet | 2 GW (up to 10 GW) | 2036 | PCI. Feasibility confirmed. ~1,000 km via PEI |
| BE–NO link | Elia + Statnett | TBC | 2035 | MoU signed Nov 2023. Feasibility study underway |
EU Regulatory Framework
| Framework | Relevance to Belgium |
|---|---|
| TEN-E Regulation (EU 2022/869) | Nautilus (PCI/PMI) and TritonLink (PCI). Princess Elisabeth Island as interconnection hub |
| RED III (2023/2413) | Binding 42.5% EU renewable target. Accelerated permitting timelines |
| EU Offshore RE Strategy (2020) | 300 GW by 2050 across EU. Belgium a key contributor |
| EU MSP Directive (2014/89/EU) | Implemented via Belgian Marine Spatial Plan |
| CWE Market Coupling | Belgium in Central Western Europe coupling since 2006. Flow-based since May 2015 |
Existing Interconnectors
| Interconnector | Capacity | Route | Commissioned |
|---|---|---|---|
| Nemo Link | 1,000 MW | Belgium–UK (HVDC) | 2019 |
| ALEGrO | 1,000 MW | Belgium–Germany (HVDC) | 2020 |
Reform & Future Direction
Princess Elisabeth Zone Delivery
The PEZ remains Belgium’s primary offshore wind growth vector. Lot 1 tender relaunch is planned for Q1 2026, with Lots 2 and 3 to follow. However, HVDC cost escalation (island costs up from€3.6bn to €7–8bn) has forced a rethink: Lot 3 (HVDC-connected) is delayed ~3 years while Lots 1 and 2 (HVAC) proceed on schedule.
Ventilus — The Onshore Bottleneck
The Ventilus 380 kV line (~82 km, Zeebrugge to Avelgem) is critical for bringing PEZ power onshore. Elia submitted 5 Flemish environmental permit applications in September 2025. The Flemish Minister of Environment must decide by end of April 2026. Without Ventilus, no PEZ wind farm can deliver power to consumers.
Key Challenges
| Challenge | Detail |
|---|---|
| HVDC cost escalation | Princess Elisabeth Island costs doubled to €7–8bn due to global HVDC supply chain constraints. Lot 3 delayed ~3 years |
| Ventilus permit | Flemish environmental permit for 380 kV onshore line facing strong local opposition. Decision expected April 2026 |
| PEZ tender delays | Lot 1 tender postponed from Nov 2024 to Q1 2026 due to legal uncertainties and unclear financial framework |
| Boucle du Hainaut | Second onshore reinforcement in Wallonia also facing public resistance |
Beyond 5.8 GW
Belgium has discussed expanding to 8 GW by 2040 in the context of REPowerEU. This would require additional marine spatial planning and potentially new offshore zones. The Princess Elisabeth Island is designed as a multi-purpose hub that can also host international interconnectors (Nautilus, TritonLink, BE–NO link), positioning Belgium as a North Sea energy crossroads.
Key Sources
Fact Check
This page was fact-checked using automated verification (OpenAI gpt-5.4 with web search). Two iterations were run against the research document, with findings independently verified before corrections were applied.
| Iteration | Date | Errors Reported | Verified & Fixed | False Positives | Summary |
|---|---|---|---|---|---|
| 2 | 2026-03-15 | 12 | 4 | 8 | PEZ concession joint-minister authority, development plan approval clarified, Ventilus public inquiry status updated, tender relaunch softened. |
| 1 | 2026-03-15 | 20 | 10 | 10 | Key fixes: total capacity 2,262→2,261 MW, farm count 8→9, Mermaid 252→235.2 MW, Norther removed from MOG list, cable-laying permit authority corrected. |
Disclaimer: This page is for informational purposes only and does not constitute legal or regulatory advice. While every effort has been made to ensure accuracy, readers should consult primary sources (legislation, regulator publications) for definitive guidance. Information reflects the position as of March 2026.