Belgian Offshore Wind Grid Connections[Draft]

How offshore wind transmission assets are planned, constructed, and financed in Belgium under the federal concession model with centralised TSO grid.

Last updated: March 2026 · Sources: FPS Economy, CREG, Elia, RBINS/MUMM · Fact-checked 2026-03-15 (2 iterations)

Installed Capacity2.26 GW
PEZ Pipeline~3.5 GW
2030 Target~5.8 GW
Wind Farms9 operational

Key Regime

Federal Concession + TSO Grid Federal minister grants domain concessions. Elia builds and owns all offshore grid infrastructure (MOG, Princess Elisabeth Island).

Key Bodies

FPS EconomyCREGEliaRBINS/MUMMFlemish Gov

Key Regulatory Bodies

BodyRoleKey Functions
FPS Economy (DG Energy)Federal ministryAdministers offshore wind domain concessions. Organises PEZ tenders. Issues cable-laying permits. Advises Minister of Energy on applications
CREGFederal energy regulatorIssues Green Certificates (1 per MWh). Proposes LCOE/strike prices for CfD. Approves transmission tariffs. Advises on concessions and network development plans
EliaTSO & offshore grid ownerSole TSO (20-year designation, renewed Sep 2022). Builds and operates MOG, MOG II, and Princess Elisabeth Island. 8,903 km of HV lines. Green Certificate purchase obligation
Minister of EnergyFederal ministerGrants domain concessions. Issues cable permits. Approves network development plan (jointly with Minister of North Sea). Sets maximum CfD strike price
RBINS / OD Nature / MUMMMarine science & EIAReceives Environmental Impact Studies. Produces independent EIA. Recommends to Minister on environmental permits. Coordinates WinMon.BE monitoring programme (since 2008)
FPS Health (Marine Environment)Environmental permitsIssues marine protection permits via Minister for Marine Environment. Coordinates Marine Spatial Plan (MSP 2020–2026). Administers Natura 2000 marine approvals
Flemish Government / VREGOnshore permittingEnvironmental and spatial planning permits for onshore cable landfall and grid reinforcement (e.g., Ventilus 380 kV line). VREG regulates onshore grid access/tariffs
Belgian Coast GuardMaritime safetyCoordinates maritime safety around wind farms. Monitors exclusion zones. Joint Flemish-federal body (est. 2003–2005)
Belgium has a constitutionally entrenched federal/regional split: the federal government has exclusive jurisdiction over the North Sea (offshore licensing, EIA, grid), while Flanders handles all onshore permitting from the coastline inland. The Ventilus 380 kV lines Flemish environmental permit has been the primary bottleneck delaying the Princess Elisabeth Zone.

Primary Regime Federal Concession Model

Belgium operates a federal concession model for offshore wind. The federal Minister of Energy grants domain concessions giving developers the right to build and operate wind farms in designated marine areas. Elia builds and owns all offshore grid infrastructure separately.

How It Works

StepActorDescription
1. Marine spatial planningFPS HealthMarine Spatial Plan designates offshore wind zones (original zone + Princess Elisabeth Zone)
2. Domain concessionMinister of EnergyGrants concession for wind farm development. Open-door (Zone 1) or competitive tender (PEZ)
3. Environmental permitMinister for Marine EnvironmentMarine protection permit based on EIA by RBINS/MUMM. 45-day public consultation
4. Cable permitMinister of EnergyCable-laying permit for submarine export cables
5. Grid connectionEliaTSO builds offshore grid hub (MOG/MOG II/Princess Elisabeth Island). Wind farms connect to the hub

Key Legislation

LawScope
Electricity Act (29 April 1999)Primary offshore wind law. Articles 6–7: domain concessions, cable permits, support scheme
Law of 12 May 2019Amended Electricity Act to introduce competitive tenders for PEZ
Marine Environment Protection Act (20 Jan 1999)Environmental permits for offshore installations. EIA requirements
Royal Decree of 20 December 2000Domain concession application procedure and award criteria
Royal Decree of 12 March 2002Cable-laying permit procedure
Royal Decree of 20 March 2014Marine Spatial Plan establishing offshore wind zones
Royal Decree of 3 June 2024New offshore grid framework: Elia builds all PEZ grid; costs fully socialised

Comparison: Belgium vs UK vs Germany

FeatureBelgium (Concession)UK (OFTO Model)Germany (TSO Model)
Who plans sitesFederal MSP (FPS Health)Developer-led (Crown Estate)BSH via FEP
Who builds gridElia (TSO) — MOG/PEIDeveloper (transfers to OFTO)TSO (TenneT / 50Hertz / Amprion)
Who operates gridElia (permanent)OFTO (25-year licence)TSO (permanent)
Cost recovery (PEZ)Fully socialised via tariffsTNUoS chargesOffshore grid levy
Support mechanismGreen Certificates (Zone 1) / CfD (PEZ)Two-way CfD (AR rounds)Zero-subsidy / negative bidding
Federal/regional splitYes — North Sea federal, onshore FlemishNo — single jurisdictionYes — EEZ federal, territorial waters Länder

Zone 1 & Princess Elisabeth Zone

Zone 1: Original Offshore Wind Zone (20082020)

Belgiums first offshore wind zone (~238 km²) was designated in the Marine Spatial Plan of March 2014. Nine wind farms were built between 2008 and 2020, reaching a total installed capacity of 2,261 MW. Early farms had individual export cables to shore; later farms connected via Elias Modular Offshore Grid (MOG) platform.

Support Mechanism Evolution

VintageMechanismPriceDuration
C-Power, Belwind, Northwind, NobelwindGreen Certificates (fixed)€107/MWh (first 216 MW); €90/MWh above20 years
RentelGreen Certificates (LCOE-based)€129.80/MWh19 years
NortherGreen Certificates (LCOE-based)€124/MWh19 years
Mermaid, SeaStar, Northwester 2Green Certificates (LCOE-based)€79/MWh17 years
PEZ (from 2026)Two-sided CfDMax €95/MWh (tender)20 years

Princess Elisabeth Zone (PEZ)

Designated in the Marine Spatial Plan 20202026, the PEZ is a 285 km²zone at the border with France, ~45 km offshore. It will add 3.153.5 GW across three lots, bringing Belgiums total to ~5.8 GW.

LotAreaCapacityStatus
Lot 1 (Noordhinder North)~46 km²700 MWTender launched Nov 2024; postponed to Q1 2026
Lot 2 (Noordhinder South)TBC1,225–1,400 MWPlanned 2026–2028
Lot 3 (Fairybank)TBC1,225–1,400 MWPlanned 2026–2028; delayed ~3 years (HVDC issues)

PEZ Tender Framework

ParameterDetail
MechanismTwo-sided Contract for Difference (CfD)
Maximum strike price€95/MWh
Contract duration20 years
Award criteria90% strike price, 10% business model innovation
EU State aid approval€682 million scheme approved September 2024
Minimum experience300 MW realised offshore wind (Lot 1)
Commissioning deadline42 months (max 48) after bid announcement
The Lot 1 tender was launched in November 2024 but postponed by Minister Bihet in July 2025 due to legal uncertainties, an unrealistic calendar, and a vague financial framework. Relaunch planned for Q1 2026.

Consenting & Permitting

Belgiums offshore wind consenting involves three federal permits plus onshore Flemish permits. The federal/regional split means offshore and onshore consenting run on separate tracks.

Federal Permits (Offshore)

PermitAuthorityDescription
Domain ConcessionMinister of Energy (FPS Economy)Right to build and operate a wind farm in a designated marine area. Up to 20 years, extendable to max 30. Open-door (Zone 1) or competitive tender (PEZ)
Environmental Permit (Marine Protection)Minister for Marine EnvironmentBased on EIA by RBINS/MUMM. 45-day public consultation including neighbouring countries. Construction authorisation (5 years, extendable); operating licence (20 years)
Cable PermitMinister of EnergyFor submarine power cable laying. Impact study on existing grid required. Proof of financial/technical capacity

Regional Permits (Onshore Flanders)

PermitAuthorityNotes
Environmental permit (onshore)Flemish GovernmentFor cable landfall, converter stations, onshore grid reinforcement
Spatial planning permitFlemish GovernmentFor onshore infrastructure siting
Ventilus 380 kV lineFlemish Minister of EnvironmentCritical onshore reinforcement. 5 permit applications submitted Sep 2025. Decision expected end Apr 2026

Environmental Assessment

AssessmentAuthorityNotes
Environmental Impact Study (EIS)Applicant submits to RBINS/MUMMMandatory for all offshore wind projects
Environmental Impact Assessment (EIA)RBINS/MUMM produces independentlyFormal procedure ~155 days. Recommendations to Minister
WinMon.BE monitoringRBINS coordinatesLong-term marine ecosystem monitoring since 2008
Natura 2000 assessmentFPS HealthRequired for projects near/in Natura 2000 sites

Typical Timeline

PhaseDurationDescription
Marine spatial planningMulti-yearGovernment-led zone designation via MSP
Tender process (PEZ)~12 monthsFrom launch to winner announcement
Environmental permit6–8 monthsEIS submission, EIA, public consultation, ministerial decision
Domain concessionSeveral monthsApplication, evaluation, ministerial grant
Onshore permits (Flemish)12–24 monthsEnvironmental and spatial planning permits
Construction2–3 yearsWind farm and grid connection
Total (PEZ: tender to power)~4\u20135 years42–48 months from bid to commissioning (target)

Grid Connection & System Planning

Elia as Offshore Grid Builder

Elia is Belgiums sole TSO and builds, owns, and operates all offshore grid infrastructure. The grid model has evolved from individual radial connections (early farms) to centralised hubs (MOG, Princess Elisabeth Island).

Modular Offshore Grid (MOG)

ParameterDetail
CommissionedSeptember 2019
Technology220 kV HVAC switching platform
Capacity~1,030 MW (4 wind farms: Rentel, SeaStar, Mermaid, Northwester 2)
Export cablesThree 220 kV submarine cables to Zeebrugge (Stevin substation)
Investment~€400 million
Availability99.998% (2020); effectively 100% in other years
Energy transported>14.75 TWh since commissioning

Princess Elisabeth Island (MOG II)

ParameterDetail
TypeWorld’s first artificial energy island
Location~45 km offshore in the PEZ
CapacityUp to 3.5 GW (PEZ wind farms) + international interconnectors
TechnologyBoth HVAC and HVDC — first island to combine both
HVDC capacityUpgraded from 1,400 MW to 2,000 MW
Construction23 concrete caissons (~22,000 tonnes each). First placed April 2025
InterconnectorsLanding point for Nautilus (BE–UK) and TritonLink (BE–DK)
InvestmentOriginally €3.6bn; escalated to €7–8bn (HVDC supply chain costs)
EIB financing€650 million green credit facility (October 2024)
Target readyFirst wind farms ~2030
HVDC contracts for the Princess Elisabeth Island were postponed in February 2025 and shelved in June 2025 due to cost escalation. Lot 3 (HVDC-connected) is delayed ~3 years. Lots 1 and 2 (HVAC-connected) proceed on schedule.

Grid Connection Costs

ZoneCost Model
Zone 1 (original)Partially socialised: Elia funds up to 1/3 of cable costs (max €25M for ≥216 MW). Developer bears remaining 2/3
PEZ (new regime, RD 3 June 2024)Fully socialised: Elia builds entire offshore grid. Costs recovered via regulated transmission tariffs from all consumers

Onshore Reinforcements

ProjectSpecificationStatus
Ventilus380 kV HVAC, ~82 km (Zeebrugge–Avelgem)5 Flemish permit applications Sep 2025. Public enquiry Feb–Mar 2026. Decision expected end Apr 2026
Boucle du Hainaut380 kV reinforcement in HainautFacing public resistance. Required for full PEZ integration

Financial & Commercial Framework

Zone 1: Green Certificate Scheme

Zone 1 wind farms receive federal Green Certificates (1 per MWh of net production) issued by CREG. Elia has a legal purchase obligation at a guaranteed minimum price set by the Federal Government. The dramatic price drop from 107/MWh to 79/MWh across vintages reflects technology cost reductions.

PEZ: Two-Sided CfD

ParameterDetail
MechanismTwo-sided Contract for Difference
Maximum strike price€95/MWh
Duration20 years
EU State aid approval€682 million scheme (September 2024)
Green certificatesNot granted to PEZ concessionaires
Consumer protectionDeveloper pays back when market price exceeds strike price

Grid Cost Recovery

MechanismDetail
Offshore surchargeOn electricity bills since 2012 to fund GC purchase obligation
Nuclear levy offsetTwo-thirds of offshore surcharge funded via nuclear levy
Solidarity contributionFrom 2023: offshore wind revenues capped; excess returned to consumers
PEI infrastructure costsClassified as essential infrastructure under EU rules; Elia recovers via tariffs over several years

Historical Evolution

  1. First concession zone designated

    Belgium designates a 156 km² area in its EEZ for offshore wind.
  2. C-Power Phase 1 installed

    First 6 turbines at Thornton Bank (30 MW). Belgiums first offshore wind electricity fed to the grid in 2009.
  3. Belwind commissioned (165 MW)

    Second Belgian offshore wind farm, completed December 2010.
  4. C-Power reaches full capacity (325 MW)

    Phases 2 and 3 completed with jacket foundations.
  5. Northwind + first Marine Spatial Plan

    Northwind commissioned (216 MW). Belgium adopts MSP 20142020, one of the first countries globally to do so.
  6. Nobelwind commissioned (165 MW)

    Fifth wind farm in Zone 1.
  7. Rentel commissioned (309 MW)

    First farm connected via the Modular Offshore Grid (MOG).
  8. MOG commissioned + PEZ designated

    Elias MOG platform operational (September). Marine Spatial Plan 20202026 designates the Princess Elisabeth Zone (285 km²).
  9. Zone 1 fully built out (2,261 MW)

    SeaMade (Mermaid + SeaStar, 487 MW) and Northwester 2 (219 MW) complete. Nine wind farms, 100% on time and budget.
  10. Esbjerg Declaration signed (May)

    Belgium among 4 countries committing to 65 GW by 2030, 150 GW by 2050.
  11. Ostend Summit hosted by Belgium (April)

    9 countries sign Ostend Declaration: 120 GW by 2030, 300 GW by 2050. Princess Elisabeth Island receives environmental permit (October).
  12. PEZ tender + EU State aid approval

    EU approves 682M CfD scheme (September). PEZ Lot 1 tender launched (November). EIB commits 650M for PEI. Nautilus approved by Ofgem (November).
  13. PEI construction + tender delay

    First caissons placed at sea (April). PEZ Lot 1 tender postponed by Minister Bihet (July). HVDC contracts shelved (June) due to cost escalation. Ventilus permit applications submitted (September).
  14. Hamburg Investment Pact signed (January)

    Belgium signs 1 trillion collective offshore wind commitment. PEZ Lot 1 tender relaunch planned Q1 2026. Ventilus decision expected April 2026.

Current & Planned Grid Connection Systems

Zone 1 Operational (2,261 MW)

Wind FarmCapacityTurbinesCommissionedGrid Connection
C-Power325 MW542009–2013Direct to shore
Belwind171 MW562010Direct to shore
Northwind216 MW72 × 3 MW2014Direct to shore
Nobelwind165 MW50 × 3.3 MW2017Direct to shore
Norther370 MW442019Direct to shore
Rentel309 MW42 × 7.35 MW2018Via MOG
SeaStar (SeaMade)~252 MW2020Via MOG
Mermaid (SeaMade)~235 MW2020Via MOG
Northwester 2219 MW23 × 9.5 MW2020Via MOG

Princess Elisabeth Zone Planned (~3.5 GW)

LotCapacityGrid ConnectionExpected COD
Lot 1 (Noordhinder North)700 MWHVAC via PEI~2029–2030
Lot 2 (Noordhinder South)1,225–1,400 MWHVAC via PEI~2030
Lot 3 (Fairybank)1,225–1,400 MWHVDC via PEI~2033 (delayed)

Capacity Summary

CategoryCapacity
Zone 1 operational2,261 MW
PEZ planned~3,150–3,500 MW
Total (by ~2030\u20132033)~5,400\u20135,800 MW
Further ambition (2040)~8,000 MW

Supranational Dimension

NSEC Leadership

Belgium is a founding member of the North Seas Energy Cooperation (NSEC) and has been one of its most active participants. Belgium hosted the Ostend North Sea Summit (April 2023) where 9 countries committed to 300 GW by 2050.

North Sea Summits

SummitLocationKey Commitment
Esbjerg (May 2022)Denmark4 countries: 65 GW by 2030, 150 GW by 2050
Ostend (April 2023)Belgium (host)9 countries: 120 GW by 2030, 300 GW by 2050
Hamburg (January 2026)Germany€1 trillion Investment Pact. 100 GW by 2050 joint target

Hybrid Interconnector Projects

ProjectPartnersCapacityTargetStatus
NautilusElia + National GridTBC2028+PCI/PMI. Ofgem approved Nov 2024. Study phase
TritonLinkElia + Energinet2 GW (up to 10 GW)2036PCI. Feasibility confirmed. ~1,000 km via PEI
BE–NO linkElia + StatnettTBC2035MoU signed Nov 2023. Feasibility study underway

EU Regulatory Framework

FrameworkRelevance to Belgium
TEN-E Regulation (EU 2022/869)Nautilus (PCI/PMI) and TritonLink (PCI). Princess Elisabeth Island as interconnection hub
RED III (2023/2413)Binding 42.5% EU renewable target. Accelerated permitting timelines
EU Offshore RE Strategy (2020)300 GW by 2050 across EU. Belgium a key contributor
EU MSP Directive (2014/89/EU)Implemented via Belgian Marine Spatial Plan
CWE Market CouplingBelgium in Central Western Europe coupling since 2006. Flow-based since May 2015

Existing Interconnectors

InterconnectorCapacityRouteCommissioned
Nemo Link1,000 MWBelgium–UK (HVDC)2019
ALEGrO1,000 MWBelgium–Germany (HVDC)2020

Reform & Future Direction

Princess Elisabeth Zone Delivery

The PEZ remains Belgiums primary offshore wind growth vector. Lot 1 tender relaunch is planned for Q1 2026, with Lots 2 and 3 to follow. However, HVDC cost escalation (island costs up from3.6bn to 78bn) has forced a rethink: Lot 3 (HVDC-connected) is delayed ~3 years while Lots 1 and 2 (HVAC) proceed on schedule.

Ventilus The Onshore Bottleneck

The Ventilus 380 kV line (~82 km, Zeebrugge to Avelgem) is critical for bringing PEZ power onshore. Elia submitted 5 Flemish environmental permit applications in September 2025. The Flemish Minister of Environment must decide by end of April 2026. Without Ventilus, no PEZ wind farm can deliver power to consumers.

Key Challenges

ChallengeDetail
HVDC cost escalationPrincess Elisabeth Island costs doubled to €7–8bn due to global HVDC supply chain constraints. Lot 3 delayed ~3 years
Ventilus permitFlemish environmental permit for 380 kV onshore line facing strong local opposition. Decision expected April 2026
PEZ tender delaysLot 1 tender postponed from Nov 2024 to Q1 2026 due to legal uncertainties and unclear financial framework
Boucle du HainautSecond onshore reinforcement in Wallonia also facing public resistance

Beyond 5.8 GW

Belgium has discussed expanding to 8 GW by 2040 in the context of REPowerEU. This would require additional marine spatial planning and potentially new offshore zones. The Princess Elisabeth Island is designed as a multi-purpose hub that can also host international interconnectors (Nautilus, TritonLink, BENO link), positioning Belgium as a North Sea energy crossroads.

Key Sources

Fact Check

This page was fact-checked using automated verification (OpenAI gpt-5.4 with web search). Two iterations were run against the research document, with findings independently verified before corrections were applied.

IterationDateErrors ReportedVerified & FixedFalse PositivesSummary
22026-03-151248PEZ concession joint-minister authority, development plan approval clarified, Ventilus public inquiry status updated, tender relaunch softened.
12026-03-15201010Key fixes: total capacity 2,262→2,261 MW, farm count 8→9, Mermaid 252→235.2 MW, Norther removed from MOG list, cable-laying permit authority corrected.

Disclaimer: This page is for informational purposes only and does not constitute legal or regulatory advice. While every effort has been made to ensure accuracy, readers should consult primary sources (legislation, regulator publications) for definitive guidance. Information reflects the position as of March 2026.