Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
On 7 July 2022, IPTO advanced procurement for the upgrade of the Kyllini–Zakynthos electrical interconnection by unsealing the tender envelope and naming Fulgor S.A., a member of the Hellenic Cables Group, as the candidate contractor. This step marked the start of bid review for the turnkey project to replace the ageing 150 kV subsea cable, after which construction of the new interconnection could commence.