Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
In August 2021, Liander and its contractors, including Verkley, commenced installation of two new electricity cables between Holwerd and Ameland. Work started with laying parallel land cables from the Liander substation in Holwerd to the transition joint to the sea cable on the salt marsh and a parallel land cable on Ameland from the transition joint to the station near Buren, with offshore and dike-crossing activities scheduled in the mid‑August to late‑November 2021 window to respect the bird breeding season.