Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
Submarine cable installation for the Mantoudi–Skiathos 150 kV AC interconnection began in December 2020, after Fulgor subcontracted Asso.subsea to execute the laying, landing and protection of approximately 29–35 km of HV submarine cable between Mantoudi (Evia) and Skiathos. According to ADMIE-related reporting and a subsequent reference letter, the accelerated installation campaign was carried out over about one week in the last quarter of 2020 and concluded with the landfall of the high-voltage cable at Xanemos beach on Skiathos.