On 29 August 2022, the Skiathos–Euboea electrical interconnection was officially inaugurated at the Skiathos High Voltage Substation. The ceremony, held after the link had already been in full operation since 11 July 2022, highlighted that the 150 kV submarine and land cable system supplied by and installed by Hellenic Cables was successfully delivering reliable power to Skiathos and the Northern Sporades and recognised the project as a major milestone for Greece’s transmission system.
On 11 July 2022, IPTO put into operation the new Mantoudi Evia–Skiathos 150 kV transmission line and the Skiathos GIS substation, with the interconnection starting to transport the first electric loads from the Greek National Transmission System to Skiathos and the wider Northern Sporades island group via Evia.
The Skiathos–Evia 150 kV electrical interconnection entered full operation on 11 July 2022, following completion of construction and testing, and since then has been providing reliable electricity from the mainland transmission system to Skiathos and the Northern Sporades, enhancing the islands’ energy security during peak tourist demand.
By July 2022, IPTO had completed construction of the Skiathos–Evia interconnection, a technically complex project implemented during the pandemic that enhanced the energy security of the Northern Sporades islands by establishing a 150 kV link between Skiathos and the mainland system via Evia.
On 28 January 2021, Cenergy Holdings announced that its subsidiary Hellenic Cables had successfully completed the electrical tests of the 150 kV high-voltage submarine cable connecting Skiathos to the Greek National Transmission System at Mantoudi, Evia, marking a key system testing milestone for the Skiathos interconnection and confirming that the cable system met the required performance and quality specifications ahead of full project completion.
First Subsea reports that Greek contractor Asso.subsea, working for developer IPTO and main contractor Hellenic Cables/Fulgor on the Mantoudi–Skiathos interconnection, finished laying the 30 km subsea cable and installing the cable protection system, with cable laying operations successfully wrapped up on Christmas Eve 2020.
IPTO’s project timeline for the Mantoudi–Skiathos interconnection records that the submarine cable landing was completed in December 2020, marking completion of the shore landing operations for the 150 kV cable between Evia and Skiathos.
IPTO/ADMIE selected Hellenic Cables and its subsidiary Fulgor as the cable contractor for the Mantoudi–Skiathos interconnection, awarding a contract of about EUR 42.8–43 million covering the design, supply and installation of approximately 30 km of 150 kV submarine and underground cable between Skiathos and Evia, including subsea protection and connection to the mainland 150 kV transmission system at Mantoudi. The award was publicly announced in January 2020 and the contract for the cable parts was formally signed on 21 February 2020 at the operator’s headquarters, marking the transition of the project into the implementation phase.
Hellenic Cables and its subsidiary Fulgor planned to commence implementation of the Skiathos interconnection submarine works in January 2020, under an approximately EUR 43 million contract from Greek TSO ADMIE/IPTO covering design, manufacturing and subsea installation of about 30 km of 150 kV cable between Skiathos and the Mantoudi area of Evia.
As part of the same turnkey contract awarded by ADMIE/IPTO, Hellenic Cables and Fulgor expected to begin in January 2020 the onshore implementation works for the Skiathos interconnection, including supply and installation of the underground land cable sections connecting the submarine cable to the 150 kV Transmission System in the Mantoudi area of Evia.
| Evia Regional Unit (Central Greece) | Magnisia Regional Unit (Thessaly) | |
|---|---|---|
| Landfall | Mantoudi, Euboea (Mantoudi landing / connection to 150 kV system), Greece | Skiathos (Skiathos High Voltage Substation / GIS 150/20 kV), Greece |
| Grid Connection | Mantoudi 150 kV substation (Mantoudi, Euboea) | Skiathos 150/20 kV GIS Substation (new) |
Evia Regional Unit (Central Greece)
Magnisia Regional Unit (Thessaly)