Positive
Project advancing - milestone achieved
High Impact
Major milestone or critical setback
By early July 2025, HEP-ODS had laid and put into service three new 20 kV submarine cable links in the waters around Rab, replacing older cables to enhance the security of electricity supply, with the new connections now serving as reserve supply for part of the island and assisting in feeding TS 35/20 kV Biluća as part of a wider Adriatic submarine cable renewal programme co-financed by EU recovery funds.