Positive
Project advancing - milestone achieved
High Impact
Major milestone or critical setback
HEP planned to bring the new 35 kV, 12 km submarine cable line Podgora–Pogorila into full operation by integrating it into the existing 10 kV network by the end of 2020, so that it could supply the future Bogomolje transformer station and improve voltage quality and supply reliability in the eastern part of Hvar island.