Positive
Project advancing - milestone achieved
High Impact
Major milestone or critical setback
As of March 8, 2018, Ios and neighboring Cycladic islands, including Paros which acts as the hub for indirect links to Ios, began receiving their electricity directly from the mainland Greek grid via the new Cyclades underwater cable system from Lavrio to Syros and onward connections, marking full commercial operation of the Paros–Ios interconnection within the Cyclades scheme’s first stage.