Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
By early August 2024, ONE-Dyas had commenced installation of a subsea cable on the North Sea between the N05-A gas production platform and the German offshore wind farm RIFFGAT. A German court decision on 7 August 2024 subsequently prohibited ONE-Dyas from beginning or further continuing with the cable installation pending additional review, implying that installation activities had already started before this date.