Positive
Project advancing - milestone achieved
High Impact
Major milestone or critical setback
First power from the Middelgrunden offshore wind farm was exported to Copenhagen’s grid in December 2000, when the first turbines began producing electricity and transmitting it via the 30 kV subsea cable from the central turbine to the transformer at the Amager power station 3.5 km away, supplied and installed by NKT Cables.