Positive
Project advancing - milestone achieved
High Impact
Major milestone or critical setback
In 2016, LEF NET A/S installed a new approximately six‑kilometre subsea cable to Strynø after damage had left the island with only a single remaining electrical connection. Following completion of administrative steps, approvals, and a seabed investigation by Langelands Museum, the new cable was laid mostly directly on the seabed, restoring the desired two-sided power supply to Strynø and thereby re‑establishing the targeted level of supply security.