1973 Completion of the first submarine cable links Kos-Kalymnos (25,4 Km) ... by FULGOR on behalf of DEI (Public Power Co).
In 1973 Fulgor S.A. completed the first submarine power cable link between the Greek islands of Kos and Kalymnos on behalf of DEI (Public Power Co). The project involved delivering and installing a medium-voltage HVAC submarine distribution cable system over a 25.4 km subsea route, configured as two parallel cables, providing an essential electrical interconnection between the islands. As a cable manufacturer and turnkey supplier, Fulgor manufactured the subsea power cables and carried out their marine installation and commissioning, delivering a fully operational link to DEI. This early Aegean interconnection later formed part of Fulgor’s reference list for Greek island submarine cable projects.