33 kV MVAC export cable system connecting the 49.5 MW Kentish Flats Extension array to landfall at Hampton Pier and onward to the existing onshore route to Red House Farm substation.
Nostag GmbH performed offshore cable installation for Vattenfall on the 49.5 MW Kentish Flats Extension project, including the export cable system. Operating the cable-laying vessel Nostag 10 alongside BoDo Installer, Nostag transported the array and export cables from Nordenham to the site and laid them offshore. After the array and export cables had been installed and the grid connection completed, Nostag was demobilised and left the Kentish Flats Extension site.