Cable manufacturing and logistics for the Kentish Flats Extension export system progressed in early May 2015, with cable load-out starting on 1 May 2015 at NSW’s facility in Nordenham, Germany, and the cable-laying vessel BoDo Installer completing loading of the export cables on 5 May 2015 despite weather-related delays, ahead of transit to the offshore site for installation later in the month.