Positive
Project advancing - milestone achieved
Low Impact
Minor progress or informational
Cable protection works for the Kårehamn export connection included nearshore trenching and protection of the two export cables in limestone and hard till, with installation of 690 four‑tonne gravelbag filter units (rockbags) in 5–25 m water depth; a supplier reference list records Karehamn as receiving cable protection using offshore rockbags in 2014.