Corfu - Igoumenitsa Interconnection (Corfu - Mainland 3)
12 September 2025
Positive
Project advancing - milestone achieved
High Impact
Major milestone or critical setback
In September 2025, Greek transmission system operator IPTO/ADMIE took investment decision and signed a turnkey contract for the third 150 kV Igoumenitsa–Corfu interconnector, committing just over €61 million for the project. The contract, awarded to FULGOR S.A. (Hellenic Cables), covers design, supply and installation of a composite submarine and underground cable system linking Corfu with the mainland, with works scheduled to be completed within 22–24 months of contract signing.