Corfu - Igoumenitsa Interconnection (Corfu - Mainland 3)
Date TBD
Positive
Project advancing - milestone achieved
High Impact
Major milestone or critical setback
Greek TSO IPTO has awarded Hellenic Cables a turnkey contract to design, supply, install, protect and commission a 150 kV cable system interconnecting Igoumenitsa and Corfu, consisting of approximately 18 km of three-core submarine cable and 13 km of single-core underground cable. Hellenic Cables plans to complete the works and commission the interconnection within 22 months of contract signing, after which the new link is intended to enhance transmission capacity and reliability for Corfu and the neighboring Epirus region.