Positive
Project advancing - milestone achieved
Low Impact
Minor progress or informational
Ahead of export cable installation for the Hywind Scotland Pilot Park, additional UXO surveys and verification were carried out along the export cable route. These campaigns were used to remove potential seabed obstructions such as boulders and debris including old fishing gear and wires, and to support micro‑siting of the final route; no UXO was found.