LMR Drilling GmbH was selected to perform controlled drilling works for four pipeline sections below the seawall south of the Maasgeul channel to enable the safe onshore cable connection from landfall to the onshore high-voltage substation at Maasvlakte 2 for the Hollandse Kust (zuid) Alpha grid connection. The activities were scheduled to start in 2019.