Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
DEME Group's cable-laying vessel Living Stone began installation of the first two 220 kV export cables for TenneT's Hollandse Kust Zuid Alpha grid connection in mid-2020, laying two approximately 34 km cables between the Alpha offshore platform and the Dutch mainland. Installation was completed in September 2020.