Cyclades Interconnection Phase A : Siros - Mykonos
1 January 2015
Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
Following the signing of the first Cyclades interconnection contract in September 2014, IPTO (ADMIE) moved the project into its development and construction phase from 2015, initiating work on the first-phase submarine links including the 35 km, 150 kV Syros–Mykonos cable for which Hellenic Cables had been commissioned to supply and lay the cables and make the necessary network connections.