VBNK started withdrawing the sea cable on land and early Saturday morning the cable reached the newly built transformer substation (Borssele Alpha)
VBNK carried out the onshore pull-in/withdrawal works at the landfall to connect the first Borssele Alpha submarine export cable to the newly built transformer substation at Borssele. The activity formed part of bringing the first sea cable ashore and connecting it into the onshore station, ahead of the second sea cable connection.