Significant progress or notable issue
TenneT awarded VBMS, in consortium with NKT Cables, the Borssele Alpha contract to supply and install two 61‑kilometre 220 kV AC export cables that will connect the Borssele I & II offshore wind farms to TenneT’s onshore grid, with the export cable installation campaign routed via the Western Scheldt estuary to landfall near the existing Borssele high-voltage substation and scheduled to be carried out during 2018–2019.