Positive
Project advancing - milestone achieved
High Impact
Major milestone or critical setback
PGE's 27 January 2020 press release states that on 24 January 2020 the Regional Director for Environmental Protection in Gdańsk "issued an environmental consent for two offshore wind farm projects belonging to PGE, namely Baltica 2 and Baltica 3". This environmental consent decision constitutes the key planning consent for the Baltica 2 offshore wind farm.