On 24 March 2026, the official Baltica project website reported that the controlled sea–land Horizontal Directional Drilling (HDD) works for Baltica 2 are already complete, indicating that the HDD shore-crossing works for the export cable landfalls have been finished.
By mid‑February 2026, PGE and Ørsted had completed the first stage of seabed preparation for Baltica 2, with the BOKA Falcon vessel having prepared 150 km of inter-array cable routes. The campaign included corridor clearance and trenching using the Megalodon plough, and work is now moving to prepare a 260 km export cable route ahead of later cable installation.
By February 2026, the UXO survey along Baltica 2’s planned inter-array and export cable routes had been completed with no unexploded ordnance found, clearing the way for ongoing boulder removal, trenching, and future cable installation.
Upgrade to access detailed cable specifications, supply chain data, projected timeline, financial analysis, and more.
Baltica 2 is a large-scale offshore wind farm under development in the Polish sector of the Baltic Sea as a 50/50 joint venture between PGE and Ørsted. Planned as the first phase of the wider Baltica complex, the project is being progressed to deliver roughly 1.5 GW of capacity and to be the larg...
Owners
Baltica 2 Offshore Wind Farm, EWB2, Baltica II, Baltica 2 (Phase I PSzW), Morska Farma Wiatrowa Baltica 2
By mid-February 2026, the initial campaign of geotechnical surveys along Baltica 2’s cable corridors had been completed as part of the first stage of seabed preparation, enabling subsequent boulder removal, trenching, and readiness for inter-array and export cable installation.
Developers Ørsted and PGE plan to begin offshore installation of the Baltica 2 export cables in 2026. Project communications indicate that manufacturing of the 275 kV export cables has started, with offshore installation scheduled to commence in 2026, and a February 2026 update confirms that installation of export cables and offshore substations will begin later that year. Under previously signed agreements, Boskalis will carry out the laying and burial of about 300 km of offshore export cables as part of this campaign, following the dedicated seabed preparation and corridor‑trenching works.
In 2025, Boskalis commenced cable trenching for Baltica 2’s subsea cable corridors using the multi‑mode Megalodon plough deployed from the vessel BOKA Falcon, following earlier geotechnical investigations, UXO clearance, and corridor boulder removal along both inter-array and export cable routes. This first stage of seabed preparation created trenched corridors over 150 km of inter-array routes and initiated preparation for the future 260 km export cable route needed for the Baltica 2 Export system.
Geotechnical surveys along the planned inter-array and export cable routes for Baltica 2 began as the first step in the seabed preparation campaign, providing ground condition data needed before boulder clearance, trenching, and cable installation works proceeded.
Following the initial geotechnical work for Baltica 2, contractors commenced checks for unexploded ordnance (UXO) along the planned cable corridors, a prerequisite for continuing seabed preparation and installation activities safely.
Project updates confirm that manufacturing of the Baltica 2 offshore export cables has started in advance of the planned offshore installation campaign beginning in 2026. This marks a key supply-chain milestone for the 275 kV export cable system that will connect the offshore substations to the onshore substation at Osieki Lęborskie.
By 22 December 2025, construction of the Baltica 2 export grid’s onshore substation at Osieki Lęborskie in the Choczewo commune was well advanced. A consortium of GE Vernova and Polimex Mostostal was executing works on the nearly 13‑hectare site, with main civil works completed, installation of 275 kV and 400 kV gas‑insulated switchgear buildings under way, and busbar and gantry structures linking the node to transmission operator PSE’s network already erected. In parallel, horizontal directional drilling works near the coastline were progressing to connect the offshore 275 kV export cables with the approximately six‑kilometre onshore cable route to the substation, marking substantive progress on the onshore elements of the Baltica 2 export connection.
Construction of the Baltica 2 onshore substation at Osieki Lęborskie in the Choczewo commune, which receives power from the 275 kV export cables and steps it up to 400 kV for injection into Poland’s national grid, is being executed by a consortium of GE Vernova and Polimex Mostostal under a dedicated construction contract. The consortium is delivering the nearly 13-hectare facility, including civil works and installation of high-voltage equipment, as part of the overall grid-connection infrastructure for Baltica 2.
Toward the end of 2025, offshore site preparation for Baltica 2’s cable corridors, including the export cable route, advanced significantly. Following earlier geotechnical investigations and checks for unexploded ordnance along the planned cable routes, contractors removed large boulders up to two metres in size from both inter-array and export cable corridors using the T‑Rex plough deployed from Boskalis’s vessel BOKA Falcon. At the end of 2025, cable trenching began with the Megalodon plough, preparing the seabed so that, after installation, the cables can be correctly laid and protected; this first trenching campaign covered 150 km of cable routes and formed a key part of the offshore preparation for the Baltica 2 export connection.
In August 2025, Boskalis began offshore site preparation for the Baltica 2 offshore wind farm, starting boulder clearance and corridor preparation along the planned inter-array and export cable routes. Using the vessel BOKA Falcon with the T‑Rex plough, the contractor cleared the seabed following geotechnical and UXO surveys, initiating the seabed preparation campaign ahead of cable trenching and installation.
PGE confirmed it had obtained loans for its 50% share of Baltica 2 financing, including about PLN 6 billion in loans from Bank Gospodarstwa Krajowego (BGK), of which approximately PLN 5.5 billion comes from Poland’s National Recovery Plan. These BGK and NRP‑backed facilities form part of the project finance structure for Baltica 2, while Ørsted finances its share from its own capital.
PGE and Ørsted reported that construction of the onshore connection infrastructure for the Baltica 2 offshore wind farm had already started by early February 2025. This work covers the onshore transformer substation and underground cable lines in Osieki Lęborskie, Choczewo municipality, which will route electricity from the offshore wind farm into the Polish power system.
According to Ørsted's 29 January 2025 press release "Ørsted and PGE take final investment decision on Baltica 2 Offshore Wind Farm", Ørsted and PGE "have taken final investment decision (FID) on the 1.5 GW Baltica 2 Offshore Wind Farm" on that date.
In September 2024, PGE, Ørsted, and Istrana signed a lease agreement for the future T5 terminal in the Port of Gdansk, securing a pre‑assembly and installation base where turbine components for Baltica 2 will be stored, pre‑assembled, and marshalled for offshore installation.
In February 2024, PGE and Ørsted finalised a contract with Cadeler to install the second batch of turbines for Baltica 2, adding a further specialist turbine installation vessel capacity alongside previously contracted installers.
In February 2024, Ørsted and PGE awarded a contract to a Polish consortium of ROMGOS Gwiazdowscy and ZRB Janicki to execute horizontal directional drilling under the beach for routing 275 kV cable lines and to construct connection couplers for the Baltica 2 grid connection.
The Pomeranian Voivode issued a building permit for 107 offshore wind turbines and the associated electrical and telecommunications network for the Baltica 2 offshore wind farm, completing the set of offshore construction permits needed for the project.
On 14 February 2024, PGE and Ørsted signed a contract with Van Oord for the transport and installation of 111 monopile foundations at the Baltica 2 site, using the Aeolus and Svanen installation vessels to install 107 turbine foundations and four foundations for offshore substations.
In February 2024, PGE and Ørsted confirmed that they had selected a general contractor for the onshore connection infrastructure for the Baltica 2 project, in addition to contracting all necessary components and installation contracts. This marks the award of a major onshore grid connection works contract for the Baltica 2 export system.
In January 2024, Fred. Olsen Windcarrier was selected to install 48 of the 107 Siemens Gamesa turbines at Baltica 2 under a turbine installation contract that will use a specialised jack‑up vessel to lift and mount the turbines on their foundations.
Also in January 2024, GE Vernova and Polimex Mostostal were chosen as general contractors for Baltica 2’s onshore connection infrastructure, with responsibility for constructing the onshore electrical substations and transmission lines that will integrate the offshore wind farm into Poland’s national power grid.
In December 2023, DNV was awarded the component certification contract for Baltica 2, taking responsibility for certifying that the project’s major components comply with industry standards and regulatory requirements before installation.
In October 2023, Steelwind Nordenham was contracted to supply monopile foundations for the Baltica 2 offshore wind farm, providing the large‑diameter monopiles that will support the project’s turbines in the Baltic Sea.
PGE Polska Grupa Energetyczna and Ørsted finalised contracts for the marine export cable system for Baltica 2, appointing ZTT Submarine Cable & System and Hellenic Cables to supply approximately 300 km of 275 kV offshore export cables that will bring power from the wind farm to shore. Under its contract, Hellenic Cables will deliver 148 km of 275 kV XLPE-insulated export cables including jointing, termination, and testing, with manufacturing to take place at its Corinth, Greece facility. These export cable supply agreements secure the core transmission link between the offshore substations and the onshore grid connection for Baltica 2.
On 5 September 2023, Boskalis announced it had been awarded two large EPCI‑style contracts by the Ørsted–PGE joint venture for Baltica 2, covering transportation and installation of 107 inter‑array cables and four 275 kV export cables (nearly 300 km in total), along with seabed levelling, pre‑trenching, boulder removal, and post‑lay rock placement using its cable‑lay vessels and support fleet.
PGE Polska Grupa Energetyczna and Ørsted signed contracts with Boskalis for the transportation, laying, burial, and protection of the Baltica 2 offshore cables, including about 300 km of export cables and roughly 170 km of inter-array cables. Boskalis’ scope covers seabed preparation (boulder removal, seabed levelling, and pre-trenching), installation of the four 275 kV export cables in pre-cut trenches using the Megalodon plough from the construction support vessel Falcon, and post-lay rock placement to stabilise cable protection systems, with preparatory works starting in 2025 and offshore installation planned from 2027.
On 8 August 2023, the European Investment Bank’s Board of Directors approved in-principle financing of the Baltica Offshore Wind Farm project implemented by PGE Group, with a total package of EUR 1.4 billion. This development bank loan support is a key step in securing an optimal financing structure to enable construction of PGE’s first offshore wind projects in the Baltic Sea, including the Baltica 2 stage and its associated grid connection assets.
Also in June 2023, Semco Maritime and PTSC Mechanical & Construction (PTSC M&C) were awarded a contract for Baltica 2 to design, manufacture, and commission the project’s offshore substations, which will collect power from the turbines and export it to the onshore grid.
In June 2023, the Ørsted–PGE joint venture signed a contract with Navantia‑Windar covering the delivery of foundations for the Baltica 2 offshore wind farm, as part of a wider package for foundations and array cables.
In June 2023, Ørsted and PGE signed a supply contract with Orient Cable (NBO) for 66 kV subsea array cables for Baltica 2, as part of agreements covering foundations and array cable deliveries for the 1.5 GW project.
In May 2023, Ørsted and PGE selected a consortium of Biuro Studiów, Projektów i Realizacji "Energoprojekt‑Katowice" SA and Energopomiar as contract engineer for the Baltica 2 land connection, tasking it with supervising the general contractor’s work on the onshore transmission line and substation components of the grid connection.
In April 2023, Ørsted and PGE signed a turbine supply agreement with Siemens Gamesa Renewable Energy for Baltica 2, under which Siemens Gamesa will deliver 107 SG 14‑222 offshore wind turbines (14 MW each), securing the project’s main turbine technology for the 1.5 GW wind farm in the Polish Baltic Sea.
PGE and Ørsted appointed a consortium of Biuro Studiów, Projektów i Realizacji "Energoprojekt‑Katowice" SA and "Energopomiar" Sp. z o.o. as Contract Engineer to perform investor’s supervision over construction of the land connection for the Baltica Offshore Wind Farm, including the onshore grid connection associated with the Baltica 2 export cable system. The consortium will oversee design and construction quality for the onshore cable route and substation works that link the offshore export cables into Poland’s transmission network.
In 2022, an environmental decision was issued for the connection infrastructure of the Baltica Offshore Wind Farm, covering grid connection works for the Baltica 2 and Baltica 3 phases.
Ørsted and PGE Polska Grupa Energetyczna formed a 50/50 joint venture to develop, construct, and operate the Baltica Offshore Wind Farm, including the Baltica 2 and Baltica 3 phases. According to later project overviews, the partnership was established in 2019, with the joint venture agreement to develop the two phases signed in May 2021, creating the co-development structure that now owns and advances the 1.5 GW Baltica 2 project.
The Polish Energy Regulatory Office (ERO) awarded a Contract for Difference (CfD) to the 1.5 GW Baltica 2 offshore wind farm (together with Baltica 3), securing a regulated strike price under Poland’s Offshore Wind Act. The CfD, later confirmed as a 25‑year inflation‑protected revenue support mechanism with the Polish state, underpins long‑term revenue stability for Baltica 2 ahead of its planned 2027 commissioning.
An environmental decision for the Baltica Offshore Wind Farm, covering both the Baltica 2 and Baltica 3 phases, was issued in 2020, marking approval of the project’s environmental impact assessment for the offshore wind farm itself.
PGE's 27 January 2020 press release states that on 24 January 2020 the Regional Director for Environmental Protection in Gdańsk "issued an environmental consent for two offshore wind farm projects belonging to PGE, namely Baltica 2 and Baltica 3". This environmental consent decision constitutes the key planning consent for the Baltica 2 offshore wind farm.
As part of the first phase of preparing the Baltica 2 cable corridor in the Baltic Sea, geotechnical surveys were carried out along the planned cable routes, covering the corridors that will host both inter-array and export cables for the project’s offshore grid connection.
Following the initial geotechnical work on the Baltica 2 cable corridor, contractors completed unexploded ordnance checks along the planned cable routes for the inter-array and export cables, confirming that no UXO were present and allowing subsequent corridor clearance and trenching works to proceed.
Showing historic events only. Subscribe for the full timeline including projected milestones.