60 km 150 kV three-phase HVAC export cable
NKT supplied the 150 kV HVAC export cable system (60 km) and the 30 kV inter-array cable system (20 km) for Baltic 1 during the 2009-2011 construction period. Per NKT's own reference page: "supplying a reliable infield and export cable system" — scope was manufacture and supply only; marine installation was performed under a separate contract.