Netherlands Offshore Wind Grid Connections[Draft]
How offshore wind transmission assets are planned, constructed, and financed in the Netherlands under the centralised TenneT “Net op Zee” model.
Last updated: March 2026 · Sources: TenneT, RVO, ACM, I&W · Fact-checked
Key Regime
Net op Zee (Grid at Sea) — TenneT (sole offshore TSO) builds, owns, and operates all post-2016 Net op Zee offshore grid connections. Developers only build the wind farm and inter-array cables to the TenneT offshore platform.
Key Bodies
Key Regulatory Bodies
| Body | Role | Key Functions |
|---|---|---|
| ACM | Energy regulator | Autoriteit Consument & Markt. Independent regulator for energy, telecom, and transport markets. Sets tariffs, monitors market competition, enforces energy legislation. Approves TenneT’s investment plans |
| TenneT | Transmission system operator | Sole onshore and offshore TSO for the Netherlands. Builds, owns, and operates all post-2016 Net op Zee offshore grid connections. Pre-2016 projects were developer-built. Also TSO in parts of Germany |
| EZK (Ministry of Economic Affairs and Climate Policy) | Economic affairs & climate ministry | Sets offshore wind targets, develops energy policy, issues kavelbesluit (site decisions). Minister Stientje van Veldhoven-van der Meer (from 23 Feb 2026) |
| RVO | Enterprise agency | Rijksdienst voor Ondernemend Nederland. Manages offshore wind tenders, SDE++ subsidy scheme. The minister grants the permit; RVO administers the process on behalf of the ministry |
| Rijkswaterstaat | Public works authority | Manages North Sea infrastructure, maritime spatial planning, environmental monitoring, waterway management. Part of I&W ministry |
| I&W (Ministry of Infrastructure & Water) | Infrastructure ministry | Responsible for maritime spatial planning (Programma Noordzee), offshore infrastructure coordination, water management |
| SodM | Mining safety regulator | Staatstoezicht op de Mijnen. Safety oversight for offshore installations including wind farms and platforms. Inspects construction and operation |
| Commissie m.e.r. | EIA review commission | Independent commission reviewing environmental impact assessments for offshore wind projects. Advisory role on scope and quality of EIAs |
| Raad van State | Highest administrative court | Hears appeals against kavelbesluit (site decisions) and environmental permits. Final arbiter of planning disputes |
Primary Regime — Net op Zee (Grid at Sea)
The Netherlands operates a centralised TSO-build model for offshore wind grid connections, branded “Net op Zee” (Grid at Sea). TenneT, as the Netherlands' sole transmission system operator, is responsible for designing, constructing, owning, and operating all offshore grid connections — from the offshore transformer platform to the onshore grid connection point. Wind farm developers are only responsible for the wind farm itself and inter-array cables to the TenneT platform.
Phase 1: HVAC 700 MW Platforms (2019–2025)
The first generation of standardised offshore platforms used 220 kV HVAC technology with a capacity of ~700 MW each. Seven platforms were built for the Borssele, Hollandse Kust Zuid (HKZ), Hollandse Kust Noord (HKN), and Hollandse Kust West (HKW) wind farm zones. These platforms set a global benchmark for cost-efficient, standardised grid connections.
Phase 2: HVDC 2 GW Programme (2025+)
The second generation uses HVDC 525 kV technology with a capacity of 2 GW per system. The 2GW Programme represents an investment of approximately €30 billion and will deliver 14 HVDC converter stations and export cable systems. Key zones include IJmuiden Ver, Nederwiek, and Doordewind (Doorwind). The first 2 GW system (IJmuiden Ver Alpha) is expected operational by 2029.
Comparison: NL vs FR vs DE
| Feature | Netherlands (Net op Zee) | France (TSO-Build) | Germany (Multi-TSO) |
|---|---|---|---|
| Who builds grid connection | TenneT (post-2016 Net op Zee) | RTE (sole TSO) | TSO (TenneT / 50Hertz / Amprion) |
| Who operates grid connection | TenneT (permanent) | RTE (permanent) | TSO (permanent) |
| Number of offshore TSOs | 1 (TenneT) | 1 (RTE) | 3 (TenneT, 50Hertz, Amprion) |
| Cost recovery | Offshore grid tariff (socialised) | TURPE network tariff (socialised) | Offshore grid levy (socialised) |
| Grid connection risk | TenneT bears construction risk | RTE bears construction risk | TSO bears construction risk |
| Delay compensation | TenneT compensates developer | Capped at 3 years equivalent | TSO pays developer (§17e EnWG) |
| Site planning | State-led (Programma Noordzee) | State-led (DSF zones) | Centralised (BSH FEP) |
| Technology (current) | HVAC 220 kV (700 MW) | HVAC 225 kV (~500 MW) | HVAC/HVDC (various) |
| Technology (next gen) | HVDC 525 kV (2 GW) | HVDC ±320/525 kV | HVDC 525 kV (2 GW) |
Key Legislation
| Law / Instrument | Scope |
|---|---|
| Wet wind op zee (Offshore Wind Energy Act, 2015) | Primary legislation governing offshore wind development. Establishes kavelbesluit (site decision) system, tender procedures, and TenneT’s grid connection obligation |
| Energiewet (Energy Act, 2026) | Replacement for Elektriciteitswet 1998 and Gaswet. Modernises energy market regulation, strengthens TSO obligations, implements EU Clean Energy Package |
| Programma Noordzee (North Sea Programme) | Maritime spatial plan designating offshore wind zones, shipping routes, nature areas. Updated every 6 years. Current: 2022–2027 |
| Besluit procesgang projecten van nationaal belang | Procedure for projects of national importance. Applies to all Net op Zee grid connections |
| Wet natuurbescherming (Nature Protection Act) | Natura 2000 protection, species protection, nitrogen deposition rules (PAS/AERIUS). Key constraint for cable routing |
Tender System
The Netherlands allocates offshore wind capacity through competitive tenders managed by RVO (Rijksdienst voor Ondernemend Nederland). The tender system has undergone a remarkable evolution: from SDE+ subsidy-based auctions to the world’s first zero-subsidy tender (HKZ, 2018), then to negative bidding, and most recently back to subsidised tenders following the Nederwiek failure.
Tender History
| Tender | Year | Zone | Capacity | Price / Mechanism | Status |
|---|---|---|---|---|---|
| Borssele I/II | 2016 | Borssele | 752 MW | €72.70/MWh (SDE+) | Operational |
| Borssele III/IV | 2016 | Borssele | 731 MW | €54.50/MWh (SDE+) | Operational |
| Borssele V | 2016 | Borssele | 19 MW | Innovation site | Operational |
| HKZ I/II | 2018 | Hollandse Kust Zuid | 760 MW | Zero subsidy (world first) | Operational |
| HKZ III/IV | 2019 | Hollandse Kust Zuid | 760 MW | Zero subsidy | Operational |
| HKN V | 2020 | Hollandse Kust Noord | 759 MW | Zero subsidy | Operational |
| HKW VI | 2022 | Hollandse Kust West | 760 MW | Negative bid (€55M) | Construction |
| HKW VII | 2022 | Hollandse Kust West | 760 MW | Negative bid (€24M) | Construction |
| IJV Alpha | 2023 | IJmuiden Ver | 2 GW | Negative bid (€403M) | Development |
| IJV Beta | 2023 | IJmuiden Ver | 2 GW | Negative bid (€58M) | Development |
| Nederwiek Alpha | 2024 | Nederwiek | 2 GW | Failed (zero qualifying bids) | Failed |
| IJV Gamma-A | 2026 | IJmuiden Ver | 2 GW | Subsidised (SDE++ return) | Tender open |
Tender Mechanism Evolution
| Era | Period | Mechanism | Example |
|---|---|---|---|
| SDE+ subsidy | 2016–2017 | Bidders compete on lowest strike price. Government pays CfD subsidy | Borssele I–IV (€54–73/MWh) |
| Zero subsidy | 2018–2020 | Comparative assessment (beauty contest). No subsidy payment | HKZ I–IV, HKN V |
| Negative bidding | 2022–2023 | Developers pay government. Ranked on price + qualitative criteria | HKW VI/VII, IJV Alpha/Beta |
| Return to subsidy | 2026+ | SDE++ CfD subsidy reintroduced after Nederwiek failure | IJV Gamma-A (2026) |
Tender Process Flow
Dutch Offshore Wind Tender Lifecycle
Zone Designation
Government designates wind farm zones in Programma Noordzee
Kavelbesluit
Minister issues site decision with environmental conditions
Tender Launch
3–6 months
RVO publishes tender with criteria
Bid Evaluation
RVO evaluates bids on criteria (price, ecology, system integration)
Permit Award
Minister awards wind farm permit to winning bidder
Grid Connection
TenneT builds offshore platform and export cable
Construction
Developer builds wind farm, connects to TenneT platform
The kavelbesluit (site decision) is issued by the Minister and includes all environmental conditions. The government conducts the EIA before the tender, removing environmental risk from developers.
Consenting & Permitting
The Netherlands uses a unique “kavelbesluit” (site decision) system that front-loads environmental assessment before the tender. The government conducts the EIA and obtains the kavelbesluit, then tenders the site to developers with environmental conditions already defined. This significantly de-risks projects for developers compared to systems where developers must obtain their own environmental permits.
Kavelbesluit System
| Step | Actor | Description |
|---|---|---|
| 1. Zone designation | Government (I&W) | Programma Noordzee identifies zones suitable for offshore wind. Strategic Environmental Assessment (plan-MER) conducted at zone level |
| 2. Site preparation | Government (RVO / EZK) | Government conducts site-specific EIA (project-MER), geotechnical and geophysical surveys, and metocean studies |
| 3. Kavelbesluit | Minister (EZK) | Minister issues site decision with all environmental conditions, turbine parameters, and restrictions. Open for appeal to Raad van State |
| 4. Tender | RVO | Site tendered to developers with kavelbesluit conditions pre-set. Developer does not need separate environmental permit |
| 5. Construction permit | SodM / Rijkswaterstaat | Safety and construction permits for actual construction works |
Environmental Framework
| Requirement | Authority | Notes |
|---|---|---|
| KEC (Kader Ecologie en Cumulatie) | RWS / Commissie m.e.r. | Cumulative effects framework assessing total ecological impact of all offshore wind in the Dutch North Sea. Updated regularly |
| WOZEP (Wind op Zee Ecologisch Programma) | RVO / RWS | Ecological research programme for offshore wind. Funds studies on marine mammals, birds, bats, fish, and seabed ecology. Informs kavelbesluit conditions |
| Noise thresholds | EZK / RWS | Underwater noise limits during pile driving: SEL threshold for harbour porpoise protection. Mandatory use of noise mitigation (bubble curtains, slow start) |
| Nature-inclusive design | EZK / Tender criteria | Mandatory requirement since HKW tenders. Developers must incorporate measures to enhance marine biodiversity (e.g. reef structures, bird perches) |
| Natura 2000 assessment | EZK / Provinces | Required when projects may affect Natura 2000 sites. Particular concern for Voordelta and Noordzeekustzone |
| Nitrogen deposition (AERIUS) | Provinces | Construction activities must demonstrate negligible nitrogen deposition on sensitive habitats. Major constraint for cable landfalls |
Appeals
Appeals against kavelbesluit decisions go directly to the Raad van State (Council of State), the Netherlands' highest administrative court. The Raad van State typically decides within 6–12 months. To date, no kavelbesluit has been overturned, though conditions have occasionally been adjusted following judicial review.
Grid Connection & System Planning
Programma Noordzee (North Sea Programme)
The Programma Noordzee is the Netherlands' maritime spatial plan, designating zones for offshore wind, shipping, fishing, nature, and other uses. The current programme (2022–2027) identifies sufficient zones to achieve the 21 GW target by the early 2030s. The programme is updated every 6 years and is coordinated by the Ministry of Infrastructure & Water (I&W).
Government Targets
| Target Year | Capacity | Source |
|---|---|---|
| 2023 (achieved) | ~4.7 GW installed | Energieakkoord + Klimaatakkoord |
| 2030 | ~11.5 GW installed | Klimaatakkoord / Aanvullend Routekaart 2030 |
| 2031–2033 | 21 GW installed | Routekaart Windenergie op Zee 2030 + additional rounds |
| 2040 (under review) | ~50 GW (proposed, under review) | Coalition agreement / policy debate |
| 2050 | To be determined | Long-term energy strategy |
Wind Farm Zones
| Zone | Total Capacity | Technology | Status |
|---|---|---|---|
| Borssele | ~1.5 GW | HVAC 220 kV | Operational |
| Hollandse Kust Zuid (HKZ) | ~1.5 GW | HVAC 220 kV | Operational |
| Hollandse Kust Noord (HKN) | ~0.76 GW | HVAC 220 kV | Operational |
| Hollandse Kust West (HKW) | ~1.5 GW | HVAC 220 kV | Construction |
| IJmuiden Ver | ~6 GW (3 sites) | HVDC 525 kV | Development |
| Nederwiek | ~4 GW (2 sites) | HVDC 525 kV | Development |
| Doordewind | ~4 GW | HVDC 525 kV | Planning |
| Ten noorden van de Waddeneilanden (TNvdW) | ~1 GW | HVDC 525 kV | Planning |
2GW Programme Consortia
TenneT’s 2GW Programme is one of the largest offshore grid programmes globally, with an estimated investment of €30 billion. The programme uses standardised 2 GW HVDC converter stations with 525 kV subsea cables. Key supply chain contracts have been awarded to consortia including:
| Component | Supplier(s) | Details |
|---|---|---|
| HVDC converter stations | Hitachi Energy / GE Vernova | Framework contracts for multiple 2 GW converter stations |
| HVDC subsea cables | Prysmian / NKT | 525 kV XLPE HVDC cables |
| HVAC platforms (Phase 1) | Multiple | Standardised 700 MW transformer platforms |
PAWOZ-Eemshaven (Wadden Sea Crossing)
The Programma Aansluiting Wind op Zee Eemshaven (PAWOZ) addresses one of the most challenging aspects of the Dutch offshore grid: routing cables through or around the UNESCO World Heritage Wadden Sea to reach the Eemshaven grid connection point. Cable routes for the Ten noorden van de Waddeneilanden (TNvdW) zone and parts of Doordewind must cross this sensitive area. Horizontal directional drilling (HDD) under the Wadden Sea islands is the preferred solution, but the environmental and engineering challenges are significant.
Hydrogen Integration
The Netherlands is exploring offshore hydrogen production as an alternative to full electrical grid connection. The TNvdW zone has been designated as a potential site for a 500 MW offshore electrolyser, with hydrogen transported to shore via the existing Gasunie gas pipeline network. This concept could reduce the need for onshore grid reinforcement and utilise decommissioned gas infrastructure.
Financial & Commercial Framework
Tender Price Evolution
| Tender | Year | Price Mechanism | Developer Payment |
|---|---|---|---|
| Borssele I/II | 2016 | SDE+ subsidy | €72.70/MWh strike price |
| Borssele III/IV | 2016 | SDE+ subsidy | €54.50/MWh strike price |
| HKZ I/II | 2018 | Zero subsidy | No subsidy, no payment |
| HKZ III/IV | 2019 | Zero subsidy | No subsidy, no payment |
| HKN V | 2020 | Zero subsidy | No subsidy, no payment |
| HKW VI | 2022 | Negative bid | Developer pays €55M to government |
| HKW VII | 2022 | Negative bid | Developer pays €24M to government |
| IJV Alpha | 2023 | Negative bid | Developer pays €403M to government |
| IJV Beta | 2023 | Negative bid | Developer pays €58M to government |
| Nederwiek Alpha | 2024 | Negative bid | Failed — zero qualifying bids |
| IJV Gamma-A | 2026 | SDE++ subsidy | Return to subsidy model |
Beauty Contest Criteria
For zero-subsidy and negative-bid tenders, RVO evaluates bids on qualitative criteria as well as price. The criteria have evolved over time and now include:
| Criterion | Weight (indicative) | Description |
|---|---|---|
| Financial bid (positive or negative) | Varies | SDE+ strike price, zero, or negative bid amount |
| System integration | High | Contribution to energy system (e.g. storage, hydrogen, demand response) |
| Ecology / nature-inclusive design | High | Measures to enhance marine biodiversity beyond minimum requirements |
| Supply chain & innovation | Medium | Industrial strategy, local content, innovation plans |
| Stakeholder engagement | Medium | Fisheries coexistence, community benefits |
Grid Cost Allocation
| Parameter | Detail |
|---|---|
| Who bears grid connection costs | TenneT bears 100% of offshore grid connection costs |
| Phase 1 cost recovery | Costs recovered via SDE+ levy on electricity bills (until 2024), then via network tariffs |
| Phase 2 cost recovery | Costs recovered via regulated network tariffs (approved by ACM) |
| Developer costs | Inter-array cables from turbines to TenneT offshore platform only |
| Delay compensation | TenneT compensates developers for grid connection delays |
TenneT Ownership & Financing
TenneT is 100% owned by the Dutch state. To finance the massive investment programme (~€30B for the 2GW Programme alone), the Dutch government has:
| Financing Measure | Detail |
|---|---|
| State ownership | 100% Dutch state-owned (Ministry of Finance) |
| Capital injection | Dutch government provided €25B in shareholder loans and equity, plus a €17.1B extension, to support the 2GW Programme and beyond |
| Germany partial sale | Sale of TenneT’s German operations to the German state (KfW) completed 2024. Proceeds support Dutch offshore investment |
| Bond issuance | TenneT issues green bonds for offshore grid investment, backed by regulated asset base |
| Regulated returns | ACM sets WACC for TenneT’s offshore assets, providing predictable investment returns |
Bilateral & International Cooperation
North Seas Energy Cooperation (NSEC)
The Netherlands is a founding member of the NSEC (established 2016) and served as co-chair from 2022–2023. Members: Belgium, Denmark, France, Germany, Ireland, Luxembourg, the Netherlands, Norway, and the European Commission.
Key Declarations
| Declaration | Year | Key Commitments |
|---|---|---|
| Esbjerg Declaration | 2022 | Committed to 65 GW North Sea offshore wind by 2030, 150 GW by 2050. NL–BE–DK–DE summit |
| Ostend Declaration | 2023 | Extended to 120 GW by 2030, 300 GW by 2050. Added FR, IE, NO, LU. Hybrid project support |
| The Hague Declaration | 2023 | NL co-hosted. Focus on grid infrastructure, hydrogen, supply chain, nature-inclusive design |
| Hamburg Declaration | 2026 | 100 GW cross-border offshore generation. Accelerated hybrid project development |
Key Cross-Border Projects
| Project | Partners | Capacity | Status | Notes |
|---|---|---|---|---|
| LionLink | NL – GB (TenneT / National Grid) | 1.8 GW | Approved | Hybrid interconnector connecting NL and GB offshore wind zones. PCI status. First Dutch hybrid project |
| BritNed | NL – GB | 1,000 MW | Operational | Existing HVDC interconnector (2011). No hybrid component |
| NorNed | NL – NO | 700 MW | Operational | Existing HVDC interconnector (2008). 580 km — one of world’s longest subsea cables at commissioning |
| COBRAcable | NL – DK | 700 MW | Operational | HVDC interconnector (2019). Connects Eemshaven (NL) to Endrup (DK) |
North Sea Wind Power Hub
The North Sea Wind Power Hub concept, originally proposed by TenneT, Gasunie, and the Port of Rotterdam, envisages artificial energy islands in the North Sea serving as hubs for offshore wind power collection, HVDC transmission, and hydrogen production. While the full island concept has not progressed, elements of the vision — particularly offshore hydrogen production and meshed grids — are being incorporated into future Dutch offshore grid planning.
Denmark Cooperation
The Netherlands and Denmark have a bilateral cooperation agreement on North Sea energy, building on the COBRAcable interconnector. Potential future collaboration includes hybrid projects connecting Dutch and Danish offshore wind zones, and coordination on the Dogger Bank area where both countries have wind development interests.
Historical Evolution
OWEZ commissioned
Offshore Windpark Egmond aan Zee (OWEZ), 108 MW — the Netherlands’ first commercial offshore wind farm. Developer-built grid connection.NorNed interconnector operational
NorNed (NL–NO, 700 MW) commissioned — at 580 km, one of the world’s longest subsea cables.BritNed interconnector operational
BritNed (NL–GB, 1,000 MW) commissioned.Energieakkoord signed
National Energy Agreement setting 4,450 MW offshore wind target by 2023. Established the policy framework for the Borssele and Hollandse Kust zones.Wet wind op zee enacted
Offshore Wind Energy Act establishes the kavelbesluit system, centralised TSO grid connection model, and competitive tender framework.Borssele tenders awarded
Borssele I/II (€72.70/MWh) and III/IV (€54.50/MWh) awarded via SDE+ — record-low prices at the time. First projects under the new kavelbesluit system.World's first zero-subsidy offshore wind tender
Vattenfall wins HKZ I/II with a zero-subsidy bid — a global milestone demonstrating offshore wind grid parity.Klimaatakkoord and COBRAcable
Climate Agreement raises target to ~11.5 GW by 2030. COBRAcable (NL–DK, 700 MW) commissioned. Borssele wind farms begin commissioning.HKN V and Routekaart expansion
HKN V tender awarded (zero subsidy). Government announces additional roadmap to reach 21 GW by early 2030s. TenneT begins 2GW Programme planning.Negative bidding introduced
HKW VI and VII awarded with negative bids (€55M and €24M). Borssele fully operational (~1.5 GW). HKZ fully operational (~1.5 GW). Esbjerg Declaration commits to 65 GW North Sea wind.IJV tenders and peak negative bids
IJV Alpha (€403M negative bid) and Beta (€58M) awarded. The Hague Declaration. HKN operational (~760 MW). Total operational: ~4.7 GW.Nederwiek failure and TenneT Germany sale
Nederwiek Alpha receives zero qualifying bids, triggering policy reset. TenneT Germany sale to KfW completed. HKW under construction. Operational capacity reaches ~5.9 GW with HKW partial commissioning.2GW Programme construction begins
First 2 GW HVDC platform (IJV Alpha) construction advancing. LionLink (NL–GB hybrid) progressing. PAWOZ Eemshaven cable route planning underway.Energiewet and return to subsidy
Energiewet (new Energy Act) enters force, replacing 1998 Electricity Act. IJV Gamma-A tender launched with SDE++ subsidy model — marking the return to subsidised offshore wind after the Nederwiek failure.
Current Grid Connection Systems
Operational
| System | Zone | Capacity | Technology | Commissioned |
|---|---|---|---|---|
| Borssele Alpha | Borssele I/II | 700 MW | 220 kV HVAC | 2020 |
| Borssele Beta | Borssele III/IV/V | 700 MW | 220 kV HVAC | 2020 |
| HKZ Alpha | HKZ I/II | 700 MW | 220 kV HVAC | 2022 |
| HKZ Beta | HKZ III/IV | 700 MW | 220 kV HVAC | 2023 |
| HKN Alpha | HKN V | 700 MW | 220 kV HVAC | 2023 |
| OWEZ (legacy) | Egmond aan Zee | 108 MW | Developer-built | 2007 |
| Prinses Amalia (legacy) | Q7 | 120 MW | Developer-built | 2008 |
| Luchterduinen (legacy) | Luchterduinen | 129 MW | Developer-built | 2015 |
| Gemini (legacy) | Gemini | 600 MW | Developer-built | 2017 |
| Total operational | ~5.9 GW |
Under Construction
| System | Zone | Capacity | Technology | Expected |
|---|---|---|---|---|
| HKW Alpha | HKW VI | 700 MW | 220 kV HVAC | 2026 |
| HKW Beta | HKW VII | 700 MW | 220 kV HVAC | 2026 |
In Development
| System | Zone | Capacity | Technology | Expected |
|---|---|---|---|---|
| IJV Alpha | IJmuiden Ver Alpha | 2 GW | 525 kV HVDC | 2029 |
| IJV Beta | IJmuiden Ver Beta | 2 GW | 525 kV HVDC | 2030 |
| IJV Gamma | IJmuiden Ver Gamma | 2 GW | 525 kV HVDC | 2031 |
| Nederwiek Alpha | Nederwiek Alpha | 2 GW | 525 kV HVDC | 2031–2032 |
| Nederwiek Beta | Nederwiek Beta | 2 GW | 525 kV HVDC | 2032–2033 |
Planned
| System | Zone | Capacity | Technology | Expected |
|---|---|---|---|---|
| Doordewind A/B | Doordewind | 4 GW (2 × 2 GW) | 525 kV HVDC | 2033+ |
| TNvdW | Ten noorden van de Waddeneilanden | ~1 GW | 525 kV HVDC / H2 | 2034+ |
Capacity Summary
| Category | Systems | Capacity |
|---|---|---|
| Operational (TenneT Net op Zee) | 5 | ~3.5 GW |
| Operational (legacy developer-built) | 4 | ~957 MW |
| Under construction | 2 | ~1.4 GW |
| In development | 5 | ~10 GW |
| Planned | 3 | ~5 GW |
| Total pipeline | 19 | ~22.5 GW |
Supranational Dimension
EU Regulatory Framework
| Framework | Relevance to Netherlands |
|---|---|
| TEN-E Regulation (EU 2022/869) | PCI/PMI designation for cross-border projects (LionLink). Cross-border cost allocation mechanisms. Netherlands actively supports offshore grid PCIs |
| RED III (Revised Renewable Energy Directive) | Late transposition into Dutch law. Renewable acceleration area provisions. 42.5% RE target by 2030. Netherlands requested derogation for auction design |
| ENTSO-E ONDP | Offshore Network Development Plan. Dutch North Sea connections included in Northern Seas corridor. Netherlands co-leads ONDP working group |
| EU Offshore Transmission Coordination | Netherlands participates in cross-border offshore grid coordination. Advocates for meshed offshore grid approach |
| PCI Projects | LionLink (NL–GB) designated as PCI. Eligible for CEF Energy co-financing and accelerated permitting |
NSEC Membership
The Netherlands is a founding member and former co-chair (2022–2023) of the North Seas Energy Cooperation. The Netherlands has been one of the most active NSEC members, hosting The Hague summit in 2023 and championing the meshed offshore grid concept, hybrid projects, and nature-inclusive design as NSEC priorities.
Regime Reform & Future Direction
Return to Subsidy
The Nederwiek Alpha tender failure (2024) forced a fundamental policy reset. The government acknowledged that the negative bidding model had become unsustainable in the context of rising interest rates, supply chain inflation, and grid connection uncertainty. The IJV Gamma-A tender (2026) marks a return to the SDE++ Contract for Difference subsidy model, with the government effectively accepting that offshore wind again requires public financial support.
CfD Legislation
New legislation is being prepared to establish a dedicated offshore wind CfD framework, separate from the broader SDE++ scheme. This will provide more tailored contract terms for offshore wind, including longer contract durations, inflation indexation, and provisions for grid connection delays.
2040 Target Under Review
The ambitious ~50 GW 2040 target is under review. Grid constraints, onshore reinforcement bottlenecks, the Nederwiek failure, and questions about the pace of demand growth have led to a policy debate about whether the target should be reduced or the timeline extended. The outcome is expected in 2026.
Hydrogen Integration
Offshore hydrogen production is increasingly seen as part of the solution to grid constraints. The TNvdW zone has been designated for a 500 MW electrolyser pilot, and the government is exploring whether offshore-produced hydrogen could serve as an alternative to full electrical grid connection for remote wind farm zones. Gasunie’s existing offshore gas pipeline infrastructure could be repurposed for hydrogen transport.
PAWOZ Challenges
Routing cables through the Wadden Sea (UNESCO World Heritage Site) to reach Eemshaven remains one of the most contentious aspects of the Dutch offshore grid programme. Environmental groups, fishing communities, and the Wadden Sea Authority have raised concerns about cable installation impacts. The government is exploring horizontal directional drilling (HDD) under the Wadden Sea islands, but the technical and environmental challenges are significant.
| Reform Area | Status |
|---|---|
| Return to subsidy | IJV Gamma-A (2026) uses SDE++ CfD. Dedicated offshore CfD framework in preparation |
| 2040 target review | ~50 GW target under review. Decision expected 2026 |
| Energiewet | New Energy Act entered force 2026. Replaces 1998 Electricity Act |
| Hydrogen integration | TNvdW 500 MW electrolyser designated. Gasunie pipeline reuse under study |
| PAWOZ Wadden Sea | Cable routing through/around Wadden Sea under environmental review |
| Nederwiek re-tender | Nederwiek Alpha to be re-tendered under revised conditions |
| Meshed offshore grid | Long-term vision for interconnected North Sea grid. LionLink as first step |
| RED III transposition | Late transposition into Dutch law. Implementation ongoing |
Key Sources
Fact Check
This page was fact-checked using automated verification (OpenAI gpt-5.4 with web search). Two iterations were run against the research document, with findings independently verified before corrections were applied.
| Iteration | Date | Errors Reported | Verified & Fixed | False Positives | Summary |
|---|---|---|---|---|---|
| 2 | 2026-03-15 | 14 | 7 | 7 | RVO permit authority clarified (minister grants permit), ACM code adoption terminology, Hamburg Declaration moved to 2026, CfD timeline softened, TenneT financing updated (€25B + €17.1B extension). |
| 1 | 2026-03-15 | 22 | 12 | 10 | Key fixes: KGG/Hermans→EZK/van Veldhoven (Jetten govt 23 Feb 2026), RVO institutional attribution, TenneT post-2016 role, kavelbesluit vs permit distinction, permit duration up to 40yr, TNvdW AC confirmed, Programma Noordzee revision updated. |