Finland Offshore Wind Grid Connections[Draft]

How offshore wind transmission assets are planned, constructed, and financed in Finland from the worlds first ice-designed offshore wind farm to a 40+ GW pipeline.

Last updated: March 2026 · Sources: TEM, Fingrid, Metsähallitus, Energiavirasto · Fact-checked 2026-03-15 (2 iterations)

Operational42 MW (1 farm)
Pipeline40+ GW
Grid Points7 (up to 9 GW)
EEZ ActIn force 1 Jan 2025

Key Regime

Developer-build model the project developer is responsible for building the grid connection from the offshore wind farm to Fingrid Oyjs onshore connection point. Fingrid does not build or own offshore connection infrastructure.

Key Bodies

TEMEnergiavirastoFingridMetsähallitusVALO

Key Regulatory Bodies

BodyRoleKey Functions
TEMMinistry of Economic Affairs and EmploymentSets offshore wind policy, prepares legislation (EEZ Act, Electricity Market Act amendments), coordinates the 17-point Action Plan (August 2024), sets offshore wind targets
EnergiavirastoIndependent energy regulatorOrganises EEZ competitive tenders, determines tender winners by comparing price-quality ratio, supervises electricity market, administers renewable energy support schemes
Fingrid OyjSole TSO (state-majority owned)Operates the 400/220/110 kV main grid, identifies offshore wind grid connection points, develops grid to accommodate offshore wind. Responsibility extended to EEZ from 1 Jan 2026. Seven connection points identified (up to 9 GW)
MetsähallitusState-owned enterpriseControls state-owned sea areas within territorial waters. Organises competitive tendering for territorial water offshore wind projects. Key projects: Korsnas, Ebba, Edith
Council of StateFinnish GovernmentDesignates EEZ offshore wind areas for tendering, grants exploitation permits to tender winners, grants research permits in the EEZ, decides on granting rights of use for territorial water projects
VALOConsolidated permitting authority (from 1 Jan 2026)Merges Valvira, AVIs, and ELY Centre environmental units. One-stop-shop for environmental permitting. Priority handling for offshore wind with 1-year target processing time (until 2030)
TraficomTransport & communications regulatorIssues aviation obstacle permits, publishes offshore wind and shipping coordination guidelines (minimum 1.5 km from navigation routes), assesses impacts on maritime radar and navigation safety
Finnish Defence ForcesNational defenceProvides views on project acceptability. Has effectively restricted offshore wind in the Gulf of Finland since late 2013 due to radar interference concerns
Ministry of the EnvironmentEnvironmental policyOversees maritime spatial planning, Natura 2000 assessments, EIA framework, coordinates Velmu biodiversity mapping. MSP update under way (2024–2027)
MunicipalitiesLocal planning authorityResponsible for zoning in public water areas (territorial waters). Issue construction permits under the Construction Act (751/2023, in force from 1 Jan 2025)
AVI (merged into VALO)Regional permitting (legacy)Granted water permits under the Water Act and environmental permits under the Environmental Protection Act. Merged into VALO on 1 January 2026
ELY Centres (merged into VALO)Regional development (legacy)Supervised EIA procedures. Determined whether EIA was required for projects below the mandatory threshold. Environmental units merged into VALO on 1 January 2026
2026 Authority Reform: The consolidation of AVI, ELY Centre environmental units, and Valvira into VALO on 1 January 2026 is the most significant permitting reform affecting offshore wind. Green transition projects receive priority processing until 2030.

Developer-Build Model (Primary Regime)

Finland operates a developer-build model for offshore wind grid connections: the project developer is responsible for building the grid connection from the offshore wind farm to Fingrid Oyjs onshore connection point. This aligns with Swedens approach and contrasts with the Dutch and German TSO-build models.

There are two distinct regulatory zones, each with its own area allocation process but the same developer-build principle for grid connection:

ZoneGoverning LawArea Allocation
EEZAct on Offshore Wind Power in the EEZ (937/2024), in force 1 Jan 2025Government designates areas for competitive tendering. Energiavirasto organises tenders. Winners receive exploitation permit
Territorial WatersExisting legislation (Water Act, Construction Act)Metsähallitus organises competitive tendering for state-owned public water areas. Municipalities handle zoning

EEZ Tendering Process

The 2025 Act replaced the previous open-door/research-permit system with a state-led tendering regime:

StepDescription
1. Government selects areasCouncil of State designates offshore wind power areas for tendering based on the maritime spatial plan, national objectives, grid availability, and coordination with other maritime activities
2. Strategic Environmental AssessmentGovernment conducts an SEA of the proposed areas before the area decision
3. Government DecreeDetailed tendering rules established by decree (expected October 2025)
4. Energy Authority runs tenderSingle-round sealed-bid format. Energiavirasto evaluates bids on a 100-point scale
5. Winner receives exploitation permitCouncil of State grants the exploitation permit (~30-year duration). Does not authorise construction
6. Developer obtains permitsDeveloper must subsequently obtain water permits, complete EIA, and obtain other permits

Tender Selection Criteria (100-Point System)

ComponentWeightDetails
Price (exploitation fee)50 pointsAnnual fee offered in EUR per installed MW
Project expertise~16.7 pointsDevelopment and construction experience with minimum 100 MW wind capacity (offshore weighted higher); experience cannot exceed 8 years old
Environmental measures~16.7 pointsRenewable energy use during operations, bird radar monitoring commitments
Energy system flexibility~16.7 pointsBattery storage construction or frequency reserve participation commitments

Pre-Qualification Requirements

RequirementThreshold
Financial capacity (Option A)EUR 600 million balance sheet with minimum 15% equity ratio
Financial capacity (Option B)EUR 1 billion in assets under management
ExperienceProject management of minimum 100 MW wind turbine capacity (both development and construction)
Participation securityEUR 1 million per tender, due at bid submission
Performance securityEUR 1M (years 1–2), EUR 3M (years 3–5), EUR 5M (year 6+) until 400 MW installed
Participation fee~EUR 20,000 (non-refundable)
Winning limitsMax 1 win if holding 2 existing permits; max 2 wins if holding 1 existing permit
Runner-up mechanism: If the winner fails to apply for the exploitation permit within 4 months, the runner-up has 6 months to apply. This provides a safeguard against tender failures.

Key EEZ Timeline

DateMilestone
1 January 2025Act on Offshore Wind Power in the EEZ enters into force
July 2025SEA assessment plan open for statements
October 2025SEA completed; Government Decree on tendering enters into force
End 2025Government decision on first areas (4 areas proposed: 2 in Bothnian Sea, 2 in Bothnian Bay)
January 2026First competitive tender commences
Summer 2026Winner of first tender selected

Key Legislation

LawStatusScope
Act on Offshore Wind Power in the EEZ (937/2024)In force 1 Jan 2025Area selection, tendering, exploitation permits, research permits in EEZ
Electricity Market Act (588/2013, amended)Amended; in force 1 Jan 2026Extends TSO responsibility to EEZ, enables connection grids for generation, allows third-party high-voltage grid construction
Water Act (587/2011)In forceWater permits for all offshore wind construction
Environmental Protection Act (527/2014)In forceEnvironmental permits
Act on EIA Procedure (252/2017)In forceMandatory EIA for projects ≥ 45 MW or ≥ 10 turbines
Construction Act (751/2023)In force from 1 Jan 2025Construction permits in territorial waters
Act on the EEZ of Finland (1058/2004)In forceGeneral EEZ governance; cable construction in EEZ
Aviation Act (864/2014)In forceObstacle permits for wind turbines

Territorial Waters & Legacy Routes

For projects in Finnish territorial waters (out to 12 nautical miles), state-owned public water areas are managed by Metsähallitus. The framework differs significantly from the EEZ regime.

Metsähallitus Competitive Tendering

StepDescription
1. Policy confirmationMinisterial Committee on Economic Policy confirmed tendering principles (December 2021)
2. Area approvalCouncil of State approved five offshore wind power areas (end of 2023)
3. Competitive tenderingMetsähallitus launches tenders, seeking commercial partners who purchase development rights, lease offshore sites, and build/operate wind farms
4. ZoningMunicipalities handle zoning (same as for onshore projects)
5. Construction permitsBuilding permits issued by the municipality
Key difference from EEZ: Metsähallitus acts as property owner/landlord rather than a regulator. The process is governed by private law (property management) rather than public administrative law. Government decides on granting rights of use after the tender process.

Current Metsähallitus Projects

ProjectDeveloperCapacityStatus
KorsnasVattenfall1.3–2.5 GWReservation agreement (Dec 2022). Geophysical/geotechnical surveys underway. Finland’s most advanced large-scale project
EbbaMetsähallitus (seeking partner)TBDPartner tender concluded Sep 2025 without a winner. Arenso Oy engaged for EIA programme planning. Will relaunch
EdithMetsähallitus (seeking partner)TBDPartner tender concluded without a winner. Will be relaunched

Municipal Water Areas

Where offshore areas fall within municipal water areas (not state-owned public water areas), the municipality itself can grant water area use rights. This applies in limited areas close to shore.

Research Permits in EEZ (Pre-2025 Legacy)

Before the EEZ Act entered into force, the Government could grant research permits in the EEZ allowing developers to conduct surveys and studies. These were non-exclusive and did not guarantee construction rights.

ProjectDeveloperLocationCapacityValidity
VoimaIlmatar Energy OyOff Jakobstad, EEZNot specifiedUntil 30 Oct 2024
NorrskarIlmatar Energy OyOff Kaskinen, EEZNot specifiedUntil 30 Oct 2024
TuuliaEolus Finland Oy / Tuulia Offshore Ab34 km west of Pori, EEZ1,500 MWUntil 30 Oct 2024
WellamoWellamo Offshore Ab88 km west of Pori, EEZ2,000 MWUntil 30 Oct 2027
Åland Islands: The autonomous Åland Islands have their own legislative framework. Major projects include OX2/Ålandsbankens Noatun North (~5 GW) and Noatun South (~5 GW). Coordination with mainland Finnish authorities (especially Defence Forces) is required.

Consenting & Permitting

The offshore wind permitting process differs between territorial waters and the EEZ. Both require multiple permits from different authorities, but the EEZ route has the Government as the primary permitting authority rather than municipalities.

Territorial Waters Permit Stack

Permit / AssessmentAuthorityLegal BasisNotes
Zoning planMunicipalityLand Use and Building ActOffshore areas zoned like land areas
EIAELY Centre (from 2026: VALO)EIA Act (252/2017)Mandatory for ≥ 45 MW or ≥ 10 turbines
Natura assessmentELY Centre / VALONature Conservation ActRequired if project may affect Natura 2000 sites
Water permitAVI (from 2026: VALO)Water Act (587/2011)Always required for offshore wind
Environmental permitAVI (from 2026: VALO)Environmental Protection ActRequired if significant environmental impacts
Construction permitMunicipalityConstruction Act (751/2023)Verifies technical compliance with zoning (in force from 1 Jan 2025)
Aviation obstacle permitTraficomAviation Act (864/2014)Required for turbines and tall structures
Defence assessmentDefence CommandVariousGeotechnical surveys require a permit
Water area use agreementMetsähallitusProperty managementPrivate-law agreement for use of state-owned sea areas

EEZ Permit Stack

Permit / AssessmentAuthorityLegal BasisNotes
Exploitation permit (from tender)Council of StateEEZ Act (937/2024)Exclusive right to develop; ~30-year duration; does not authorise construction
EIAELY Centre / VALOEIA Act (252/2017)Always required for EEZ projects. May trigger transboundary EIA (Espoo Convention)
Water permitAVI / VALOWater Act (587/2011)Always required; covers every turbine
Aviation obstacle permitTraficomAviation Act (864/2014)Same requirements as territorial waters
Defence assessmentDefence CommandVariousDefence Forces provide views on project acceptability to Government
Cable permitsVariousEEZ Act (1058/2004)Cable construction in EEZ governed by existing EEZ legislation
No zoning required in EEZ: Unlike territorial waters, EEZ projects do not require a municipal zoning plan. Area designation is by Government decision.

Defence Forces Constraints

AreaStatus
Gulf of FinlandEffectively closed to offshore wind since late 2013 due to radar interference concerns
West coast / Bothnian BayGenerally more permissive, though Defence Forces assessment still required
Åland areaAssessed per project — Noatun North has received approval, Noatun South has not

Priority Processing (2026 Onwards)

Under the new VALO authority, green transition projects including offshore wind receive priority handling with a target processing time of one year for environmental permits, water permits, or joint proceedings. This priority provision extends through 2030.

Grid Connection & System Planning

Under Finnish law, the developer is responsible for building and financing the grid connection from the offshore wind farm to Fingrid Oyjs designated onshore substation. This includes all offshore cables (array and export), offshore substations/platforms, and any onshore cable from landfall to the TSO connection point.

Fingrid is responsible for reinforcing the main grid (400 kV) to accommodate new offshore wind connections. These reinforcement costs are recovered through regulated grid tariffs paid by all grid users not charged directly to the developer.

Fingrids Seven Connection Points

Connection PointRegionSubstation StatusTimelineNotes
InkooSouthern FinlandExistingN/A currentlyGulf of Finland; restricted by Defence Forces
RaisioSouthwest FinlandExisting (Lieto)Late 2020s
UlvilaSatakunta (west coast)Existing2020sNear Pori / Tahkoluoto area
NärpiöOstrobothniaPlannedEarly 2030sUnder Fingrid investment programme
Vaasa (Tuovila)OstrobothniaExistingEarly 2030sNear Korsnas project
KokkolaCentral OstrobothniaNew requiredEarly 2030sConditional on local electricity consumption increase
Raahe (Hanhela)Northern OstrobothniaPlannedMid-late 2030sConditional on local electricity consumption increase
1.3 GW connection limit: Under Fingrids current connection framework, the maximum generation capacity at any single grid connection point is limited to 1.3 GW. This is a Fingrid operational limit/modelling assumption, not a statutory cap enacted in law.

Grid Reinforcement Investment

ItemAmount
Fingrid existing investment programme~EUR 4 billion
Additional offshore wind reinforcement~EUR 600–700 million
New/reinforced 400 kV lines needed~1,000–1,100 km
Primary reinforcement areasCentral Ostrobothnia, Southwest Finland, Uusimaa

Electricity Market Act Amendments (In Force 1 Jan 2026)

ChangeDetail
TSO responsibility extended to EEZFingrid’s obligations now cover the Finnish EEZ, not just territorial waters
Connection grids for generationMultiple power plants may share a common connection grid without requiring an electricity network licence
Third-party HV constructionDistribution system operators and third parties can now build grids above 110 kV
Flexible connection agreementsStaged grid capacity connections are permitted
Hybrid connections enabledFingrid can enable hybrid connections with a maximum of 1,300 MW generation to the main grid

Financial & Commercial Framework

No Active Offshore Wind Subsidy

Finland does not currently operate a dedicated subsidy scheme for offshore wind. The country has taken a deliberately market-driven approach. Since 2018, all new wind power in Finland has been developed on fully merchant/subsidy-free terms.

EraMechanismNotes
2011–2017Feed-in tariff (Act 1396/2010)Sliding premium tariff for renewable energy. Closed to new wind power at end of 2017
2018Single technology-neutral auctionSeven projects accepted. No further auctions held or planned
2018–presentFully merchant / PPA-basedRevenue from wholesale electricity market (Nord Pool) and/or corporate PPAs. No CfDs or feed-in premiums

Exploitation Fee (EEZ)

Under the new EEZ tendering regime, the exploitation fee offered by the winning bidder is payable to the state. This fee (EUR per installed MW annually) is a cost to the developer, not a subsidy. It represents the price paid for the exclusive right to develop the area.

Grid Tariffs & Connection Costs

Cost CategoryDetail
Developer-borne costsFull cost of offshore-to-onshore grid connection infrastructure + standard Fingrid connection charges
Fingrid-borne costsReinforcement costs downstream of the connection point, recovered through regulated grid tariffs
Socialised costs~EUR 600–700 million in offshore wind grid reinforcements ultimately socialised across all tariff payers

Property Tax Reform

ElementDetail
Proposed effective dateValuation Act from tax year 2025; Real Estate Tax Act from tax year 2030
Power plant rateWeighted average 3.09% (based on current municipal rates)
General building rateWeighted average 1.14%
Revenue timingProperty tax revenues expected from the 2030s once EEZ projects are operational
EUR 200M demonstration grant (20262029): A EUR 200 million grant allocation supports large demonstration energy projects. Suomen Hyötytuuli received EUR 30M for the Tahkoluoto demo, though this demo phase was subsequently cancelled.

Bilateral & International Agreements

AgreementDatePartiesKey Commitment
Marienborg DeclarationAugust 20228 Baltic Sea countries19.6 GW Baltic offshore wind by 2030. Finland’s 2030 contribution: ~0.1 GW (reflecting early stage)
Vilnius DeclarationApril 20248 Baltic Sea governmentsMandate for 8 TSOs (including Fingrid) to strengthen regional cooperation on offshore wind grid infrastructure. Led to creation of BOGI
BEMIP MoU RenewalMay 2025 (Warsaw)EU Baltic Sea coastal statesRenewed the Baltic Energy Market Interconnection Plan (from 2008, reformed 2015). Updates BEMIP High-Level Group responsibilities
Common Offshore Wind Planning (FI-SE)August 2024Finland, SwedenAction Plan Measure 10: establish common planning principles for Gulf of Bothnia / Bothnian Bay offshore wind

EstLink 3 (FinlandEstonia)

ParameterDetail
Capacity700 MW
RouteFinland to Aulepa, western Estonia
TechnologyHVDC submarine cable + onshore cable + converter station + 330 kV overhead line
Target commissioning2035
Offshore wind synergyRoute option allows connecting western Estonian offshore wind development areas
StatusElering submitted building permit application (Feb 2024); EIA initiated (Jul 2024)

Aurora Line (FinlandSweden)

ParameterDetail
CapacityUp to 800 MW (SE→FI) / 900 MW (FI→SE)
RoutePyhänselkä (Muhos, Finland) via Keminmaa to Messaure (Sweden), ~380 km
Technology400 kV AC overhead line
StatusOperational
Commercial service12 November 2025 (months ahead of schedule)
FundingCEF Energy co-funding of EUR 131 million
RelevanceStrengthens grid capacity in northern Finland where offshore wind connection points (Raahe, Kokkola) are planned

Historical Evolution

  1. First offshore wind turbine

    Single pilot turbine installed at Tahkoluoto, Pori by SuomenHyötytuuli.
  2. Feed-in tariff enters force

    Feed-in tariff system (Act 1396/2010) enters into force for renewable energy.
  3. Gulf of Finland blocked

    Finnish Defence Forces effectively block offshore wind development in southeast Finland and the Gulf of Finland due to radar interference concerns.
  4. Tahkoluoto completed

    Tahkoluoto offshore wind farm completed 10 turbines (mix of 2.3 MW and 4.2 MW), 157 GWh annual production. Worlds first offshore wind farm designed for ice conditions. Feed-in tariff closed to new participants.
  5. Last renewable energy auction

    Single technology-neutral auction held by Energy Authority (7 projects accepted). Last state support auction. Corporate PPAs begin to emerge.
  6. Metsähallitus tendering confirmed

    Ministerial Committee on Economic Policy confirms principles for Metsähallitus competitive tendering in territorial waters (December).
  7. Marienborg Declaration + major deals

    Marienborg Declaration signed (August): 8 Baltic Sea countries commit to 19.6 GW offshore wind by 2030. OX2/Ålandsbanken sign MoU for Noatun (~10 GW total) near Åland Islands (November). Metsähallitus/Vattenfall Korsnas reservation agreement (December). Four EEZ research permits granted.
  8. Area approvals and working groups

    Suomen Hyötytuuli receives EUR 30M EU-funded grant for Tahkoluoto extension demo (February). Council of State approves five offshore wind areas in territorial waters (end 2023). TEM appoints working group on offshore wind competitive position (October).
  9. EEZ Act approved

    Vilnius Declaration signed (April). Government publishes 17-point Action Plan (August). Fingrid publishes final offshore wind grid connection report: 7 points, up to 9 GW, EUR 700M additional investment (October). Parliament approves EEZ Act (December 12). President approves (December 19).
  10. EEZ Act enters force

    Act on Offshore Wind Power in the EEZ enters into force (1 January). Tahkoluoto demo phase cancelled; proceeding with full-scale extension (January). OX2 submits EIA reports for Laine and Halla. BOGI roadmap presented at BEMIP meeting (May).Metsähallitus Ebba/Edith tenders conclude without winner (September). Aurora Line enters commercial service ahead of schedule (November). Electricity Market Act amendment approved (October).
  11. New era begins

    Electricity Market Act amendment enters into force (1 January). VALO consolidated permitting authority launches (1 January). BOGI publishes regional offshore system study (January 22). Aurora Line formal inauguration (January 29).

Current Grid Connection Systems

Operational: Tahkoluoto (42 MW)

ParameterDetail
NameTahkoluoto Offshore Wind Farm
LocationTahkoluoto, Pori (west coast, Satakunta region)
Owner / OperatorSuomen Hyötytuuli Oy (now Tahkoluoto Offshore Oy following 2024 demerger)
Capacity~42 MW (11 turbines: mix of 2.3 MW and 4.2 MW)
First turbine2010 (single pilot)
Full completion2017
Annual production157 GWh (~8,600 electrically heated homes)
DistinctionWorld’s first offshore wind farm designed for frozen sea conditions
Grid connectionConnected to local distribution grid, with link to Fingrid main grid

Under Development: Territorial Waters

ProjectDeveloperCapacityStatusConnection Point
KorsnasVattenfall / Metsähallitus1.3–2.5 GWSurveys underway, EIA in progress. Construction planned 2030sVaasa (Tuovila)
Tahkoluoto ExtensionTahkoluoto Offshore Oy~600+ MW (40 x 15+ MW)Demo phase cancelled Jan 2025; full-scale development. Est. completion 2027Ulvila
EbbaMetsähallitusTBDEIA programme planning commenced autumn 2025; partner tender to relaunchTBD
EdithMetsähallitusTBDPartner tender to be relaunchedTBD

Under Development: EEZ Projects

ProjectDeveloperCapacityStatusNotes
LaineOX2 (51%) / Ingka Investments (49%)2.2 GW (~150 turbines, ~11 TWh/yr)EIA report submitted April 2025Gulf of Bothnia
HallaOX2 (51%) / Ingka Investments (49%)2.4 GW (~160 turbines, ~12 TWh/yr)EIA report submitted Feb 2025First EIA for a Finnish EEZ project
TyrskyOX2 (51%) / Ingka Investments (49%)1.2 GWEIA process underwayBothnian Sea
Noatun NorthOX2 / Ålandsbanken~5 GW (~340 turbines, ~20 TWh/yr)Defence Forces approval received. Koverhar LoI signed Apr 2025Planned start 2030
Noatun SouthOX2 / Ålandsbanken~5 GW (~310 turbines, ~18 TWh/yr)Defence Forces approval NOT received

Industry Capacity Targets (Renewables Finland)

YearTarget Capacity
20301 GW
20357 GW
204016 GW
204524 GW
Pipeline overview: Approximately 32 offshore wind projects are in the Finnish pipeline with combined capacity exceeding 40 GW. However, only 42 MW is operational (Tahkoluoto) and no large-scale projects are under construction. First large-scale commissioning is targeted for the early 2030s.
Risk scenario: If Finland fails to create a favourable investment environment, Renewables Finland estimates capacity could stagnate at just 1 GW by 2035 and 2 GW by 2040. The Government has indicated 1526 GW by 2050 is possible but has not set a formal quantitative offshore wind target.

Supranational Dimension

BOGI Baltic Offshore Grid Initiative

The most significant supranational framework for Finnish offshore wind is the Baltic Offshore Grid Initiative (BOGI), a cooperation between eight Baltic Sea TSOs.

TSOCountry
FingridFinland
50HertzGermany
ASTLatvia
EleringEstonia
EnerginetDenmark
LitgridLithuania
PSEPoland
Svenska kraftnätSweden

BOGI Key Milestones

DateMilestoneDetail
April 2024Vilnius DeclarationGovernments mandate TSO cooperation on offshore grids
May 2025BOGI Roadmap (Warsaw)Up to EUR 90 billion investment by 2050. Three connection approaches: point-to-point, hybrid, cross-border radial
January 2026Regional System Study~13 GW of new cross-border interconnectors and up to 50 GW additional offshore wind by 2040

BOGI Capacity Targets

MetricValue
Currently installed (Baltic Sea)Less than 5 GW
By 203026.7 GW (set in 2024)
By 2040~45 GW
Estimated total potential~93 GW

BEMIP PCI/PMI Projects Involving Finland

ProjectTypeStatus
Aurora Line 1 & 2 (Finland–Sweden AC)Electricity interconnectionOperational
EstLink 3 (Finland–Estonia HVDC)Electricity interconnectionPlanned 2035
Nordic Hydrogen Route (Sweden–Finland)Hydrogen interconnectorPCI status
Nordic-Baltic Hydrogen Corridor (FI–EE–LV–LT–PL–DE)Hydrogen corridorPCI status
Baltic Sea Hydrogen Collector (SE–FI–DE)Hydrogen collectorPCI status

EU Framework

FrameworkRelevance to Finland
TEN-E Regulation (EU 2022/869)Framework for PCI/PMI selection, including offshore grid corridors in the Baltic Sea
EU Offshore RE Strategy (2020)60 GW by 2030, 300 GW by 2050 across EU
Baltic Sea Declaration (2022)8 Baltic countries commit to 19.6 GW offshore wind by 2030
ENTSO-E TYNDP / ONDPFingrid participates in Ten-Year Network Development Plan. TYNDP 2024 includes BEMIP offshore network analysis
Hydrogen dimension: The Baltic region is positioned as a net exporter of electricity to the rest of Europe. Three PCI hydrogen projects involving Finland (Nordic Hydrogen Route, Nordic-Baltic Hydrogen Corridor, Baltic Sea Hydrogen Collector) reflect the growing importance of offshore wind for both electricity and hydrogen systems.

Reform & Future Direction

Areas of Uncertainty

AreaDetail
No formal national targetFinland has not set a binding quantitative offshore wind target. Industry targets (Renewables Finland) and government scenarios (15–26 GW by 2050) exist but are not legislated
EEZ tender timingFirst tender expected early 2026 with winner by summer 2026. Exact timeline depends on decree finalisation
Gulf of FinlandDefence Forces restrictions have blocked southern coast development since 2013; any relaxation would significantly change the pipeline
Grid connection capacityFingrid’s 7 connection points (up to 9 GW) are preliminary assessments; no investment decisions have been made
Ebba / Edith relaunchBoth Metsähallitus territorial water tenders concluded without selecting a partner; relaunch timing uncertain
VALO operational capacityNew consolidated authority launched 1 Jan 2026; processing capacity for offshore wind permits still being established
Support schemeNo dedicated offshore wind subsidy; market-based development depends on PPA availability and electricity prices
Hydrogen integrationSeveral PCI hydrogen corridor projects involve Finland but timelines and feasibility remain uncertain

Upcoming Developments

TimelineDevelopment
Summer 2026Winner of first EEZ tender expected
2026–2027Maritime spatial plan update under way
2027Tahkoluoto extension targeted completion
Early 2030sFirst large-scale offshore wind commissioning
2030Industry target: 1 GW operational capacity
2035EstLink 3 commissioning; industry target: 7 GW
2040Industry target: 16 GW
2050Government scenario: 15–26 GW (not a formal target)
Critical success factors: Finlands offshore wind ambitions depend on successful EEZ tender launch, Defence Forces accommodation, timely grid reinforcement, and a stable investment framework without subsidies. The gap between the 40+ GW pipeline and 42 MW operational capacity is enormous.

Fact Check

This page was fact-checked using automated verification (OpenAI gpt-5.4 with web search). Two iterations were run against the research document, with findings independently verified before corrections were applied.

IterationDateErrors ReportedVerified & FixedFalse PositivesSummary
22026-03-151257Key fixes: Metsähallitus territorial waters role corrected, EEZ Act approval date 27 Dec→19 Dec 2024, MSP update timeline corrected, EEZ tender scoring details flagged as provisional.
12026-03-151587Key fixes: removed unsupported EEZ building permit from Council of State role, updated Land Use and Building Act references to Construction Act (751/2023), 1.3 GW reframed as Fingrid operational limit not statutory cap, BEMIP dating corrected.
This reference is provided for informational purposes. Regulatory frameworks are complex and subject to change. Always consult primary sources and professional advisors for decisions. Last reviewed March 2026.