Danish Offshore Wind Grid Connections[Draft]

How offshore wind transmission assets are planned, constructed, and financed in Denmark from the worlds first offshore wind farm to energy island pioneer.

Last updated: March 2026 · Sources: DEA, Energinet, KEFM · Fact-checked 2026-03-15 (2 iterations)

Operational Capacity~2.7 GW
2030 Target12.9 GW
CfD Support CapDKK 55.2B
Energy IslandsBornholm 3 GW + North Sea 3–10 GW

Key Regime

Evolving Model Energinet historically built offshore grid (TSO model). From Thor (2021) onwards, developer-pays for entire offshore grid connection. Current tenders use two-sided CfD.

Key Bodies

DEAEnerginetKEFMDURDMA

Key Regulatory Bodies

BodyRoleKey Functions
DEA (Energistyrelsen)One-stop-shop authorityIssues all four offshore wind permits (preliminary investigation, EIA approval, establishment, electricity production). Manages tender procedures. Conducts environmental impact assessments
EnerginetTransmission system operatorOwns and operates national grid. Built offshore grid for early projects (HR1–Kriegers Flak). From Thor onwards, developer-pays model. Operates Kriegers Flak Combined Grid Solution
KEFM (Klima-, Energi- og Forsyningsministeriet)Ministry of Climate, Energy and UtilitiesSets national offshore wind targets and energy policy. Issues political energy agreements. Oversees DEA. Leads international energy cooperation including NSEC
Miljøstyrelsen (EPA)Environmental authorityAdministers EIA procedures, issues environmental permits, oversees Natura 2000 compliance for offshore projects
Søfartsstyrelsen (DMA)Maritime authorityMaritime spatial planning, navigation safety, shipping lane exclusion zones around wind farms
Forsyningstilsynet (DUR)Utility regulatorRegulates Energinet’s tariffs and allowed revenue. Approves grid connection cost methodology
EnergiklagenævnetEnergy Board of AppealHears appeals against DEA and DUR decisions. Administrative tribunal with quasi-judicial function
KystdirektoratetCoastal authorityIssues permits for seabed use and cable landfalls. Administers Continental Shelf Act

Evolving Grid Model TSO to Developer-Pays

Denmarks offshore wind grid connection model has undergone a fundamental evolution. Early projects used a TSO-build model where Energinet constructed offshore substations and export cables, with costs socialised through grid tariffs. From the Thor tender (2021) onwards, Denmark shifted to a developer-pays model where the wind farm developer is responsible for the entire offshore grid connection.

Model shift significance: The change from TSO-build to developer-pays was a deliberate policy choice to reduce public spending on offshore wind infrastructure. However, combining developer-pays with negative bidding contributed to the 3 GW tender failure in December 2024.

How It Works (Current Model Thor Onwards)

StepActorDescription
1. Site designationKEFM / DEAGovernment identifies offshore wind zones via maritime spatial planning
2. TenderDEADEA manages competitive tender process (currently CfD model)
3. Grid connectionDeveloperDeveloper designs, procures, and constructs the full offshore grid connection (substations + export cables)
4. Wind farmDeveloperDeveloper builds the wind farm and connects to the grid
5. Grid transferEnerginetExport cables may transfer to Energinet or remain with developer depending on tender terms

Comparison: Denmark vs UK vs Germany

FeatureDenmark (Developer-Pays)UK (OFTO)Germany (Multi-TSO)
Who builds grid connectionDeveloper (since Thor)DeveloperTSO (TenneT / 50Hertz / Amprion)
Who operates grid connectionTransfer to Energinet or developerOFTO (25-year licence)TSO (permanent)
Number of offshore TSOs1 (Energinet)N/A (OFTO regime)3 (TenneT, 50Hertz, Amprion)
Cost recoveryDeveloper-borne (in bid price)TNUoS charges (socialised)Offshore grid levy (socialised)
Grid connection riskDeveloper bears full riskDeveloper bears construction riskTSO bears risk
Site planningState-led (DEA)Developer-ledCentralised (BSH FEP)

Key Legislation

Law / InstrumentScope
RE Promotion ActPrimary law governing offshore wind tenders, support schemes, and grid connection obligations
Electricity Supply ActFramework for electricity market, grid access, TSO obligations, and tariff regulation
Marine Environment ActEnvironmental protection in Danish waters including EIA requirements
Environmental Assessment ActImplements EU EIA and SEA Directives for offshore wind projects
Continental Shelf ActGoverns installations and cables on the Danish continental shelf
Maritime Spatial Planning ActImplements EU MSP Directive. Framework for Danish maritime spatial planning
Climate Act (2020)Legally binding 70% GHG reduction by 2030. Drives offshore wind expansion

Tender System

Denmarks offshore wind tender system has evolved dramatically, from government-directed projects (Horns Rev 1) through competitive subsidy auctions (HR3, Kriegers Flak) to negative bidding (Thor) to the current two-sided CfD model (2025 tenders). The 3 GW tender failure in December 2024 triggered a fundamental restructuring.

Tender History

ProjectYearCapacityPriceModelStatus
Horns Rev 12002160 MWNegotiated FiTGovernment-directedOperational
Horns Rev 22009209 MWNegotiated FiTGovernment-directedOperational
Anholt2013400 MW~DKK 1.05/kWhFeed-in premiumOperational
Horns Rev 32019407 MW77 øre/kWhSubsidy auctionOperational
Kriegers Flak2021605 MW37.2 øre/kWhSubsidy auctionOperational
Thor2021~1 GW0.01 øre/kWhNegative bidding (lottery)Construction
Nordsøen I/II/III20243 GWNegative biddingFailed (zero bids)
Nordsøen Midt20251 GWTBCTwo-sided CfDTendered (Nov 2025)
Hesselø2025800 MWTBCTwo-sided CfDTendered (Nov 2025)
Nordsøen Syd20251 GWTBCTwo-sided CfDTendered (Nov 2025)
3 GW tender failure (December 2024): The Nordsøen I/II/III tender received zero bids a watershed moment for Danish offshore wind. Causes included excessive financial burden (negative bidding + developer-pays grid), mandatory government payments, rising interest rates, and global competition for capital.
CfD restructuring (November 2025): Three new tenders launched with two-sided capability-based CfDs, 20-year duration, and a total DKK 55.2B state support cap. Mandatory state co-ownership (previously 20%) was removed.

Tender Process Flow (Current Model)

Danish Offshore Wind Tender Lifecycle

Site Designation

KEFM/DEA identify zones via MSP

SEA

Strategic environmental assessment

Tender Launch

DEA publishes tender

Evaluation

DEA evaluates bids (CfD criteria)

Award

Minister designates winner

Permitting

Three DEA permits issued

Construction

Developer builds farm + grid

Under the current developer-pays model, the developer is responsible for both wind farm and grid connection construction.

Price Evolution

Denmarks offshore wind prices followed a dramatic downward trajectory from negotiated feed-in tariffs through the worlds first subsidy-free/negative-bid offshore wind tenders. Horns Rev 3 (77 øre/kWh, 2019) and Kriegers Flak (37.2 øre/kWh, 2021) set successive records. Thor was awarded at effectively zero subsidy (0.01 øre/kWh) after a lottery among multiple zero-subsidy bids. The subsequent 3 GW failure demonstrated that pushing developers to pay the government was unsustainable.

Consenting & Permitting

Denmark operates a genuine one-stop-shop permitting model through the DEA (Energistyrelsen), which is widely regarded as one of Europes most streamlined frameworks. Three sequential permits cover the full project lifecycle.

Three-Permit System

PermitScopeTypical Duration
Preliminary InvestigationAuthorises site investigations: geotechnical surveys, metocean measurements, environmental baseline studies2–3 years validity
EstablishmentAuthorises construction of wind farm and grid connection. Includes environmental conditions, construction methods, noise limitsIssued after EIA
Electricity ProductionAuthorises commercial electricity generation. Issued after commissioning and compliance verification25–30 years validity

Environmental Impact Assessment

RequirementAuthorityNotes
Strategic Environmental Assessment (SEA)DEARequired for new offshore wind zones before site designation
Project-level EIADEAMandatory for all offshore wind projects. Covers marine mammals, seabirds, fish, benthos, seascape, navigation
Natura 2000 screeningDEA / MiljøstyrelsenRequired when project is within or adjacent to Natura 2000 sites
Espoo Convention (transboundary)DEARequired for projects near international boundaries (e.g., Kriegers Flak, Bornholm)
Harbour porpoise noise protectionDEAStrict 183 dB cumulative SEL PTS-onset threshold. Among Europe’s most stringent
Noise protection: Denmark enforces a 183 dB cumulative SEL PTS-onset threshold for harbour porpoise during pile driving one of the strictest standards globally. Bubble curtains and seasonal construction windows are commonly required.

Open-Door Scheme (Suspended)

Denmarks open-door scheme, which allowed developers to propose their own offshore wind sites outside government-designated areas, was suspended on 1 February 2023 due to EU state aid concerns. As of 2026, it remains suspended with no confirmed reinstatement timeline.

Typical Timeline

PhaseDurationDescription
Site designation + SEA2–4 yearsGovernment-led zone identification and strategic environmental assessment
Tender process12–18 monthsDEA-managed competitive tender
Preliminary investigation + surveys2–3 yearsEnvironmental baseline and site-specific investigations
EIA + establishment permit1–2 yearsFull EIA and construction authorisation
Construction2–4 yearsWind farm and grid connection construction
Total (site to power)710 yearsVaries significantly by project complexity

Grid Connection & System Planning

Energinet System Plan

Energinet publishes regular system development plans covering both onshore grid reinforcement and offshore grid connection infrastructure. Under the current developer-pays model, Energinets primary role is providing the onshore connection point and any required grid reinforcement.

ParameterValue
Current offshore wind capacity~2.7 GW
2030 target (aspirational)~12.9 GW
2030 target (realistic)4–6 GW
2050 target35 GW
Current grid technology150–220 kV HVAC
Planned grid technology±320/525 kV HVDC (energy islands, large tenders)
Target gap: The ~12.9 GW by 2030 target is widely considered aspirational. With only ~2.7 GW operational and limited construction pipeline following the 3 GW tender failure, a realistic 2030 figure is 46 GW.

Maritime Spatial Planning

Denmarks maritime spatial plan (havplan), adopted under the Maritime Spatial Planning Act, designates areas for offshore wind development. The plan considers navigation routes, Natura 2000 sites, military areas, oil and gas infrastructure, fishing grounds, and submarine cable corridors.

Technology Transition

GenerationTechnologyCapacity per SystemProjects
Gen 1 (2002–2013)150 kV HVAC160–400 MWHorns Rev 1/2, Anholt
Gen 2 (2019–2021)220 kV HVAC400–605 MWHorns Rev 3, Kriegers Flak
Gen 3 (2025+)275 kV HVAC / HVDC800 MW–1 GWThor, Hesselø
Gen 4 (2030+)±320/525 kV HVDC2–3 GWEnergy islands, large-scale tenders

The transition to HVDC is driven by the energy island concept, which requires high-capacity, long-distance transmission. The Bornholm Energy Island will use HVDC connections to both Denmark and Germany.

Financial & Commercial Framework

Revenue Model Evolution

EraMechanismExample
2002–2009Government-directed / negotiated FiTHorns Rev 1 & 2
2013Feed-in premium (negotiated)Anholt (~DKK 1.05/kWh)
2019Competitive subsidy auctionHorns Rev 3 (77 øre/kWh)
2021Subsidy auction (further reduction)Kriegers Flak (37.2 øre/kWh)
2021Negative bidding / lotteryThor (0.01 øre/kWh)
2024Negative bidding (FAILED)Nordsøen I/II/III (zero bids)
2025–Two-sided CfDNordsøen Midt, Hesselø, Nordsøen Syd

Current CfD Framework (November 2025)

ParameterDetail
MechanismTwo-sided Contract for Difference (capability-based)
Duration20 years from commissioning
Total state support capDKK 55.2 billion (across all three tenders)
Mandatory state co-ownershipRemoved (was 20% in earlier drafts)
Grid connection costsDeveloper-pays (not socialised)
TendersNordsøen Midt (1 GW), Hesselø (800 MW), Nordsøen Syd (1 GW)

Grid Cost Allocation

ParameterDetail
Early projects (HR1–Kriegers Flak)Energinet bore 100% of offshore grid costs; recovered via regulated tariffs
Thor onwardsDeveloper-pays model. Developer responsible for offshore substation and export cables
Grid connection pointDeveloper connects to Energinet’s onshore grid at designated point
Onshore reinforcementEnerginet responsible; recovered via regulated tariffs
Tariff regulationForsyningstilsynet (DUR) regulates Energinet’s tariffs
Developer-pays risk: The shift from TSO-build to developer-pays was a key contributor to the 3 GW tender failure. Future tenders may need to reconsider cost allocation to attract investment.

Energy Islands

Denmark pioneered the energy island concept offshore hubs that aggregate power from multiple wind farms and distribute it to multiple countries via HVDC connections. Two projects are planned: Bornholm (advancing) and the North Sea island / VindØ (delayed due to cost escalation).

Bornholm Energy Island (3 GW)

ParameterDetail
Capacity3 GW (expandable)
TypeCross-border hybrid energy island (Denmark–Germany)
PartnersEnerginet + 50Hertz
StatusUnder Construction
LocationBaltic Sea, south of Bornholm
Grid connectionHVDC to both Denmark (Zealand) and Germany (Mecklenburg-Vorpommern)
SignificanceWorld’s first cross-border energy island combining offshore wind collection with cross-border power trading
AgreementDK–DE intergovernmental agreement signed January 2026

North Sea Energy Island / VindØ (3–10 GW)

ParameterDetail
Original capacity3 GW (expandable to 10 GW)
TypeArtificial island in the North Sea (~100 km offshore)
StatusStalled
TimelineDelayed to 2033–2036 (from original 2030 target)
Cost concernEstimates exceed DKK 200B (€27B+), prompting government review
Current statusProject scope being reassessed. Phased approach under consideration
Energy island significance: The concept addresses the challenge of connecting very large offshore wind capacities at 100+ km from shore. While Bornholm is advancing, the North Sea islands cost challenges may reshape the concept toward distributed hub-in-the-sea platforms rather than a single island.

Cross-Border and Hybrid Projects

ProjectPartnersCapacityStatusNotes
Bornholm Energy IslandDKDE (Energinet + 50Hertz)3 GWUnder ConstructionWorld’s first cross-border energy island. HVDC to DK and DE
Kriegers FlakDKDE (Energinet + 50Hertz)605 MW + 400 MW interconnectionOperationalWorld’s first hybrid interconnector (Combined Grid Solution)
Viking LinkDKGB (Energinet + National Grid)1,400 MWOperationalWorld’s longest HVDC interconnector (765 km). Pure interconnector
COBRAcableDK–NL700 MWOperationalHVDC interconnector. No hybrid component

Historical Evolution

  1. Vindeby commissioned

    Worlds first offshore wind farm (5 MW, 11 turbines) off the coast of Lolland. Operated until 2017.
  2. Middelgrunden commissioned

    Iconic cooperative-owned 40 MW offshore wind farm visible from Copenhagen harbour.
  3. Horns Rev 1 commissioned

    First large-scale offshore wind farm (160 MW). Government-directed project. Energinet built the grid connection.
  4. Horns Rev 2 commissioned

    209 MW. Energinet-built grid connection. Expanding the North Sea portfolio.
  5. Anholt commissioned

    400 MW. First project with feed-in premium model. Energinet-built grid connection.
  6. Vindeby decommissioned

    Worlds first offshore wind farm decommissioning after 25 years of operation.
  7. Horns Rev 3 commissioned

    407 MW at 77 øre/kWh record-low Danish offshore wind price.
  8. Climate Act enacted

    Legally binding 70% GHG emissions reduction target by 2030. Drives accelerated offshore wind expansion.
  9. Kriegers Flak + Thor tender

    Kriegers Flak (605 MW) commissioned at 37.2 øre/kWh. Combined Grid Solution with 50Hertz becomes worlds first hybrid interconnector. Thor awarded at 0.01 øre/kWh (negative bidding, lottery). Developer-pays grid model begins.
  10. Esbjerg Declaration

    Denmark hosts the Esbjerg Declaration (May) North Sea countries commit to 150 GW by 2050.
  11. Open-door scheme suspended

    Open-door scheme suspended (1 February) due to EU state aid concerns.
  12. 3 GW tender failure

    December: Nordsøen I/II/III tender receives zero bids. Major policy reset triggered. Denmark co-chaired NSEC.
  13. New CfD tenders launched

    November: Three CfD tenders launched (Nordsøen Midt 1 GW, Hesselø 800 MW, Nordsøen Syd 1 GW). DKK 55.2B support cap. Thor under construction.
  14. Bornholm agreement signed

    January: DKDE intergovernmental agreement for Bornholm Energy Island. Hamburg Declaration signed. Under construction.

Current Grid Connection Systems

Operational

ProjectCapacityTechnologyCommissioned
Horns Rev 1160 MW150 kV HVAC2002
Horns Rev 2209 MW150 kV HVAC2009
Anholt400 MW220 kV HVAC2013
Horns Rev 3407 MW220 kV HVAC2019
Kriegers Flak605 MW220 kV HVAC + CGS2021
Total operational~2.7 GW

Under Construction

ProjectCapacityTechnologyExpected
Thor~1 GWHVAC / HVDC2027

Tendered (November 2025 CfD)

TenderCapacityTechnologyExpected
Nordsøen Midt1 GWTBC2030+
Hesselø800 MWTBC2030+
Nordsøen Syd1 GWTBC2030+

Energy Islands

ProjectCapacityStatusExpected
Bornholm Energy Island3 GWDevelopment / tender preparation2030+
North Sea / VindØ3–10 GWDelayed / under review2033–2036

Capacity Summary

CategoryCountCapacity
Operational5~2.7 GW
Under construction1~1 GW
Tendered (CfD)3~2.8 GW
Energy islands (advancing)13 GW
Energy islands (delayed)13–10 GW
Total pipeline~11~12.519.5 GW
Government targets: ~12.9 GW by 2030 (aspirational, widely considered unrealistic given current pipeline), 35 GW by 2050. Realistic 2030 capacity is 46 GW.

Supranational Dimension

EU Regulatory Framework

FrameworkRelevance to Denmark
TEN-E Regulation (EU 2022/869)PCI/PMI designation for cross-border energy island projects (Bornholm DK–DE). Hybrid offshore wind projects eligible for PCI status
RED III (Renewable Energy Directive)Denmark is among the most advanced EU member states in transposing RED III (as of early 2026). Includes renewable acceleration areas
EU Offshore RE Strategy (2020)300 GW offshore wind by 2050 across EU. Denmark among leading contributors
ENTSO-E ONDPDenmark’s energy island projects are central to offshore network corridor planning
Esbjerg Declaration (May 2022)Hosted by Denmark. North Sea countries commit to 65 GW by 2030 and 150 GW by 2050

NSEC Leadership Role

Denmark is a founding member and one of the most active participants in the North Seas Energy Cooperation. Key contributions include: hosting the Esbjerg Declaration (May 2022), co-chairing NSEC in 2024, pioneering energy island concepts that have shaped NSEC thinking on offshore grid architecture, and deploying the worlds first hybrid interconnector (Kriegers Flak CGS).

Key International Declarations

DeclarationYearDenmark’s RoleKey Commitment
Esbjerg Declaration2022Host150 GW North Sea offshore wind by 2050
Ostend Declaration2023Signatory120 GW by 2030, 300 GW by 2050
Hamburg Declaration2026Signatory100 GW cross-border offshore wind by 2050. TSOs to identify 20 GW projects by 2027

Regime Reform & Future Direction

Post-Failure Restructuring

The December 2024 tender failure forced a fundamental rethink of Denmarks offshore wind policy. The government responded by abandoning the negative bidding model in favour of two-sided CfDs with a DKK 55.2B support cap. The 20% mandatory state co-ownership requirement was also removed to improve investor appeal.

Developer-Pays Model Under Scrutiny

The shift from TSO-build (Energinet bears grid costs) to developer-pays (developer bears grid costs) remains a key policy question. While developer-pays reduces public spending, it increases developer risk and bid prices. The sustainability of this model will be tested by the outcomes of the November 2025 CfD tenders.

Energy Island Pathway

The Bornholm Energy Island is advancing through development and tender preparation, but the North Sea island (VindØ) faces a critical juncture. Cost estimates exceeding DKK 200B have prompted the government to reassess the project scope. A phased approach or pivot to distributed hub-in-the-sea platforms may replace the original single-island concept.

Reform AreaStatus
Tender modelShifted from negative bidding to two-sided CfD (Nov 2025)
State co-ownershipRemoved (was 20% mandatory)
CfD support capDKK 55.2B across three tenders
Developer-pays gridRetained but under scrutiny after 3 GW failure
Open-door schemeSuspended since 1 Feb 2023 (EU state aid concerns)
Bornholm Energy IslandDevelopment / tender preparation. DK–DE agreement signed Jan 2026
North Sea / VindØDelayed to 2033–2036. Scope under review (>DKK 200B cost)
RED III transpositionAmong most advanced EU states in transposing RED III
35 GW by 2050 pathwayRequires unprecedented construction rate from ~2.7 GW base

Fact Check

This page was fact-checked using automated verification (OpenAI gpt-5.4 with web search). Two iterations were run against the research document, with findings independently verified before corrections were applied.

IterationDateErrors ReportedVerified & FixedFalse PositivesSummary
22026-03-151266KEFM full name corrected, DEA three→four licences, RED III transposition claim softened, 2050 target 35–52→35 GW per DEA.
12026-03-1519109Key fixes: Horns Rev 3 EUR conversion €10.3→€103/MWh (10x error), Kriegers Flak €5→€50/MWh, open-door suspension 2022→1 Feb 2023, Bornholm not artificial island, Bornholm status→tender prep, Climate Act 2019→2020.
This reference is provided for informational purposes. Regulatory frameworks are complex and subject to change. Always consult primary sources and professional advisors for decisions. Last reviewed March 2026.