Danish Offshore Wind Grid Connections[Draft]
How offshore wind transmission assets are planned, constructed, and financed in Denmark — from the world’s first offshore wind farm to energy island pioneer.
Last updated: March 2026 · Sources: DEA, Energinet, KEFM · Fact-checked 2026-03-15 (2 iterations)
Key Regime
Evolving Model — Energinet historically built offshore grid (TSO model). From Thor (2021) onwards, developer-pays for entire offshore grid connection. Current tenders use two-sided CfD.
Key Bodies
Key Regulatory Bodies
| Body | Role | Key Functions |
|---|---|---|
| DEA (Energistyrelsen) | One-stop-shop authority | Issues all four offshore wind permits (preliminary investigation, EIA approval, establishment, electricity production). Manages tender procedures. Conducts environmental impact assessments |
| Energinet | Transmission system operator | Owns and operates national grid. Built offshore grid for early projects (HR1–Kriegers Flak). From Thor onwards, developer-pays model. Operates Kriegers Flak Combined Grid Solution |
| KEFM (Klima-, Energi- og Forsyningsministeriet) | Ministry of Climate, Energy and Utilities | Sets national offshore wind targets and energy policy. Issues political energy agreements. Oversees DEA. Leads international energy cooperation including NSEC |
| Miljøstyrelsen (EPA) | Environmental authority | Administers EIA procedures, issues environmental permits, oversees Natura 2000 compliance for offshore projects |
| Søfartsstyrelsen (DMA) | Maritime authority | Maritime spatial planning, navigation safety, shipping lane exclusion zones around wind farms |
| Forsyningstilsynet (DUR) | Utility regulator | Regulates Energinet’s tariffs and allowed revenue. Approves grid connection cost methodology |
| Energiklagenævnet | Energy Board of Appeal | Hears appeals against DEA and DUR decisions. Administrative tribunal with quasi-judicial function |
| Kystdirektoratet | Coastal authority | Issues permits for seabed use and cable landfalls. Administers Continental Shelf Act |
Evolving Grid Model — TSO to Developer-Pays
Denmark’s offshore wind grid connection model has undergone a fundamental evolution. Early projects used a TSO-build model where Energinet constructed offshore substations and export cables, with costs socialised through grid tariffs. From the Thor tender (2021) onwards, Denmark shifted to a developer-pays model where the wind farm developer is responsible for the entire offshore grid connection.
How It Works (Current Model — Thor Onwards)
| Step | Actor | Description |
|---|---|---|
| 1. Site designation | KEFM / DEA | Government identifies offshore wind zones via maritime spatial planning |
| 2. Tender | DEA | DEA manages competitive tender process (currently CfD model) |
| 3. Grid connection | Developer | Developer designs, procures, and constructs the full offshore grid connection (substations + export cables) |
| 4. Wind farm | Developer | Developer builds the wind farm and connects to the grid |
| 5. Grid transfer | Energinet | Export cables may transfer to Energinet or remain with developer depending on tender terms |
Comparison: Denmark vs UK vs Germany
| Feature | Denmark (Developer-Pays) | UK (OFTO) | Germany (Multi-TSO) |
|---|---|---|---|
| Who builds grid connection | Developer (since Thor) | Developer | TSO (TenneT / 50Hertz / Amprion) |
| Who operates grid connection | Transfer to Energinet or developer | OFTO (25-year licence) | TSO (permanent) |
| Number of offshore TSOs | 1 (Energinet) | N/A (OFTO regime) | 3 (TenneT, 50Hertz, Amprion) |
| Cost recovery | Developer-borne (in bid price) | TNUoS charges (socialised) | Offshore grid levy (socialised) |
| Grid connection risk | Developer bears full risk | Developer bears construction risk | TSO bears risk |
| Site planning | State-led (DEA) | Developer-led | Centralised (BSH FEP) |
Key Legislation
| Law / Instrument | Scope |
|---|---|
| RE Promotion Act | Primary law governing offshore wind tenders, support schemes, and grid connection obligations |
| Electricity Supply Act | Framework for electricity market, grid access, TSO obligations, and tariff regulation |
| Marine Environment Act | Environmental protection in Danish waters including EIA requirements |
| Environmental Assessment Act | Implements EU EIA and SEA Directives for offshore wind projects |
| Continental Shelf Act | Governs installations and cables on the Danish continental shelf |
| Maritime Spatial Planning Act | Implements EU MSP Directive. Framework for Danish maritime spatial planning |
| Climate Act (2020) | Legally binding 70% GHG reduction by 2030. Drives offshore wind expansion |
Tender System
Denmark’s offshore wind tender system has evolved dramatically, from government-directed projects (Horns Rev 1) through competitive subsidy auctions (HR3, Kriegers Flak) to negative bidding (Thor) to the current two-sided CfD model (2025 tenders). The 3 GW tender failure in December 2024 triggered a fundamental restructuring.
Tender History
| Project | Year | Capacity | Price | Model | Status |
|---|---|---|---|---|---|
| Horns Rev 1 | 2002 | 160 MW | Negotiated FiT | Government-directed | Operational |
| Horns Rev 2 | 2009 | 209 MW | Negotiated FiT | Government-directed | Operational |
| Anholt | 2013 | 400 MW | ~DKK 1.05/kWh | Feed-in premium | Operational |
| Horns Rev 3 | 2019 | 407 MW | 77 øre/kWh | Subsidy auction | Operational |
| Kriegers Flak | 2021 | 605 MW | 37.2 øre/kWh | Subsidy auction | Operational |
| Thor | 2021 | ~1 GW | 0.01 øre/kWh | Negative bidding (lottery) | Construction |
| Nordsøen I/II/III | 2024 | 3 GW | — | Negative bidding | Failed (zero bids) |
| Nordsøen Midt | 2025 | 1 GW | TBC | Two-sided CfD | Tendered (Nov 2025) |
| Hesselø | 2025 | 800 MW | TBC | Two-sided CfD | Tendered (Nov 2025) |
| Nordsøen Syd | 2025 | 1 GW | TBC | Two-sided CfD | Tendered (Nov 2025) |
Tender Process Flow (Current Model)
Danish Offshore Wind Tender Lifecycle
Site Designation
KEFM/DEA identify zones via MSP
SEA
Strategic environmental assessment
Tender Launch
DEA publishes tender
Evaluation
DEA evaluates bids (CfD criteria)
Award
Minister designates winner
Permitting
Three DEA permits issued
Construction
Developer builds farm + grid
Under the current developer-pays model, the developer is responsible for both wind farm and grid connection construction.
Price Evolution
Denmark’s offshore wind prices followed a dramatic downward trajectory from negotiated feed-in tariffs through the world’s first subsidy-free/negative-bid offshore wind tenders. Horns Rev 3 (77 øre/kWh, 2019) and Kriegers Flak (37.2 øre/kWh, 2021) set successive records. Thor was awarded at effectively zero subsidy (0.01 øre/kWh) after a lottery among multiple zero-subsidy bids. The subsequent 3 GW failure demonstrated that pushing developers to pay the government was unsustainable.
Consenting & Permitting
Denmark operates a genuine one-stop-shop permitting model through the DEA (Energistyrelsen), which is widely regarded as one of Europe’s most streamlined frameworks. Three sequential permits cover the full project lifecycle.
Three-Permit System
| Permit | Scope | Typical Duration |
|---|---|---|
| Preliminary Investigation | Authorises site investigations: geotechnical surveys, metocean measurements, environmental baseline studies | 2–3 years validity |
| Establishment | Authorises construction of wind farm and grid connection. Includes environmental conditions, construction methods, noise limits | Issued after EIA |
| Electricity Production | Authorises commercial electricity generation. Issued after commissioning and compliance verification | 25–30 years validity |
Environmental Impact Assessment
| Requirement | Authority | Notes |
|---|---|---|
| Strategic Environmental Assessment (SEA) | DEA | Required for new offshore wind zones before site designation |
| Project-level EIA | DEA | Mandatory for all offshore wind projects. Covers marine mammals, seabirds, fish, benthos, seascape, navigation |
| Natura 2000 screening | DEA / Miljøstyrelsen | Required when project is within or adjacent to Natura 2000 sites |
| Espoo Convention (transboundary) | DEA | Required for projects near international boundaries (e.g., Kriegers Flak, Bornholm) |
| Harbour porpoise noise protection | DEA | Strict 183 dB cumulative SEL PTS-onset threshold. Among Europe’s most stringent |
Open-Door Scheme (Suspended)
Denmark’s open-door scheme, which allowed developers to propose their own offshore wind sites outside government-designated areas, was suspended on 1 February 2023 due to EU state aid concerns. As of 2026, it remains suspended with no confirmed reinstatement timeline.
Typical Timeline
| Phase | Duration | Description |
|---|---|---|
| Site designation + SEA | 2–4 years | Government-led zone identification and strategic environmental assessment |
| Tender process | 12–18 months | DEA-managed competitive tender |
| Preliminary investigation + surveys | 2–3 years | Environmental baseline and site-specific investigations |
| EIA + establishment permit | 1–2 years | Full EIA and construction authorisation |
| Construction | 2–4 years | Wind farm and grid connection construction |
| Total (site to power) | 7–10 years | Varies significantly by project complexity |
Grid Connection & System Planning
Energinet System Plan
Energinet publishes regular system development plans covering both onshore grid reinforcement and offshore grid connection infrastructure. Under the current developer-pays model, Energinet’s primary role is providing the onshore connection point and any required grid reinforcement.
| Parameter | Value |
|---|---|
| Current offshore wind capacity | ~2.7 GW |
| 2030 target (aspirational) | ~12.9 GW |
| 2030 target (realistic) | 4–6 GW |
| 2050 target | 35 GW |
| Current grid technology | 150–220 kV HVAC |
| Planned grid technology | ±320/525 kV HVDC (energy islands, large tenders) |
Maritime Spatial Planning
Denmark’s maritime spatial plan (havplan), adopted under the Maritime Spatial Planning Act, designates areas for offshore wind development. The plan considers navigation routes, Natura 2000 sites, military areas, oil and gas infrastructure, fishing grounds, and submarine cable corridors.
Technology Transition
| Generation | Technology | Capacity per System | Projects |
|---|---|---|---|
| Gen 1 (2002–2013) | 150 kV HVAC | 160–400 MW | Horns Rev 1/2, Anholt |
| Gen 2 (2019–2021) | 220 kV HVAC | 400–605 MW | Horns Rev 3, Kriegers Flak |
| Gen 3 (2025+) | 275 kV HVAC / HVDC | 800 MW–1 GW | Thor, Hesselø |
| Gen 4 (2030+) | ±320/525 kV HVDC | 2–3 GW | Energy islands, large-scale tenders |
The transition to HVDC is driven by the energy island concept, which requires high-capacity, long-distance transmission. The Bornholm Energy Island will use HVDC connections to both Denmark and Germany.
Financial & Commercial Framework
Revenue Model Evolution
| Era | Mechanism | Example |
|---|---|---|
| 2002–2009 | Government-directed / negotiated FiT | Horns Rev 1 & 2 |
| 2013 | Feed-in premium (negotiated) | Anholt (~DKK 1.05/kWh) |
| 2019 | Competitive subsidy auction | Horns Rev 3 (77 øre/kWh) |
| 2021 | Subsidy auction (further reduction) | Kriegers Flak (37.2 øre/kWh) |
| 2021 | Negative bidding / lottery | Thor (0.01 øre/kWh) |
| 2024 | Negative bidding (FAILED) | Nordsøen I/II/III (zero bids) |
| 2025– | Two-sided CfD | Nordsøen Midt, Hesselø, Nordsøen Syd |
Current CfD Framework (November 2025)
| Parameter | Detail |
|---|---|
| Mechanism | Two-sided Contract for Difference (capability-based) |
| Duration | 20 years from commissioning |
| Total state support cap | DKK 55.2 billion (across all three tenders) |
| Mandatory state co-ownership | Removed (was 20% in earlier drafts) |
| Grid connection costs | Developer-pays (not socialised) |
| Tenders | Nordsøen Midt (1 GW), Hesselø (800 MW), Nordsøen Syd (1 GW) |
Grid Cost Allocation
| Parameter | Detail |
|---|---|
| Early projects (HR1–Kriegers Flak) | Energinet bore 100% of offshore grid costs; recovered via regulated tariffs |
| Thor onwards | Developer-pays model. Developer responsible for offshore substation and export cables |
| Grid connection point | Developer connects to Energinet’s onshore grid at designated point |
| Onshore reinforcement | Energinet responsible; recovered via regulated tariffs |
| Tariff regulation | Forsyningstilsynet (DUR) regulates Energinet’s tariffs |
Energy Islands
Denmark pioneered the energy island concept — offshore hubs that aggregate power from multiple wind farms and distribute it to multiple countries via HVDC connections. Two projects are planned: Bornholm (advancing) and the North Sea island / VindØ (delayed due to cost escalation).
Bornholm Energy Island (3 GW)
| Parameter | Detail |
|---|---|
| Capacity | 3 GW (expandable) |
| Type | Cross-border hybrid energy island (Denmark–Germany) |
| Partners | Energinet + 50Hertz |
| Status | Under Construction |
| Location | Baltic Sea, south of Bornholm |
| Grid connection | HVDC to both Denmark (Zealand) and Germany (Mecklenburg-Vorpommern) |
| Significance | World’s first cross-border energy island combining offshore wind collection with cross-border power trading |
| Agreement | DK–DE intergovernmental agreement signed January 2026 |
North Sea Energy Island / VindØ (3–10 GW)
| Parameter | Detail |
|---|---|
| Original capacity | 3 GW (expandable to 10 GW) |
| Type | Artificial island in the North Sea (~100 km offshore) |
| Status | Stalled |
| Timeline | Delayed to 2033–2036 (from original 2030 target) |
| Cost concern | Estimates exceed DKK 200B (€27B+), prompting government review |
| Current status | Project scope being reassessed. Phased approach under consideration |
Cross-Border and Hybrid Projects
| Project | Partners | Capacity | Status | Notes |
|---|---|---|---|---|
| Bornholm Energy Island | DK–DE (Energinet + 50Hertz) | 3 GW | Under Construction | World’s first cross-border energy island. HVDC to DK and DE |
| Kriegers Flak | DK–DE (Energinet + 50Hertz) | 605 MW + 400 MW interconnection | Operational | World’s first hybrid interconnector (Combined Grid Solution) |
| Viking Link | DK–GB (Energinet + National Grid) | 1,400 MW | Operational | World’s longest HVDC interconnector (765 km). Pure interconnector |
| COBRAcable | DK–NL | 700 MW | Operational | HVDC interconnector. No hybrid component |
Historical Evolution
Vindeby commissioned
World’s first offshore wind farm (5 MW, 11 turbines) off the coast of Lolland. Operated until 2017.Middelgrunden commissioned
Iconic cooperative-owned 40 MW offshore wind farm visible from Copenhagen harbour.Horns Rev 1 commissioned
First large-scale offshore wind farm (160 MW). Government-directed project. Energinet built the grid connection.Horns Rev 2 commissioned
209 MW. Energinet-built grid connection. Expanding the North Sea portfolio.Anholt commissioned
400 MW. First project with feed-in premium model. Energinet-built grid connection.Vindeby decommissioned
World’s first offshore wind farm decommissioning after 25 years of operation.Horns Rev 3 commissioned
407 MW at 77 øre/kWh — record-low Danish offshore wind price.Climate Act enacted
Legally binding 70% GHG emissions reduction target by 2030. Drives accelerated offshore wind expansion.Kriegers Flak + Thor tender
Kriegers Flak (605 MW) commissioned at 37.2 øre/kWh. Combined Grid Solution with 50Hertz becomes world’s first hybrid interconnector. Thor awarded at 0.01 øre/kWh (negative bidding, lottery). Developer-pays grid model begins.Esbjerg Declaration
Denmark hosts the Esbjerg Declaration (May) — North Sea countries commit to 150 GW by 2050.Open-door scheme suspended
Open-door scheme suspended (1 February) due to EU state aid concerns.3 GW tender failure
December: Nordsøen I/II/III tender receives zero bids. Major policy reset triggered. Denmark co-chaired NSEC.New CfD tenders launched
November: Three CfD tenders launched (Nordsøen Midt 1 GW, Hesselø 800 MW, Nordsøen Syd 1 GW). DKK 55.2B support cap. Thor under construction.Bornholm agreement signed
January: DK–DE intergovernmental agreement for Bornholm Energy Island. Hamburg Declaration signed. Under construction.
Current Grid Connection Systems
Operational
| Project | Capacity | Technology | Commissioned |
|---|---|---|---|
| Horns Rev 1 | 160 MW | 150 kV HVAC | 2002 |
| Horns Rev 2 | 209 MW | 150 kV HVAC | 2009 |
| Anholt | 400 MW | 220 kV HVAC | 2013 |
| Horns Rev 3 | 407 MW | 220 kV HVAC | 2019 |
| Kriegers Flak | 605 MW | 220 kV HVAC + CGS | 2021 |
| Total operational | ~2.7 GW |
Under Construction
| Project | Capacity | Technology | Expected |
|---|---|---|---|
| Thor | ~1 GW | HVAC / HVDC | 2027 |
Tendered (November 2025 CfD)
| Tender | Capacity | Technology | Expected |
|---|---|---|---|
| Nordsøen Midt | 1 GW | TBC | 2030+ |
| Hesselø | 800 MW | TBC | 2030+ |
| Nordsøen Syd | 1 GW | TBC | 2030+ |
Energy Islands
| Project | Capacity | Status | Expected |
|---|---|---|---|
| Bornholm Energy Island | 3 GW | Development / tender preparation | 2030+ |
| North Sea / VindØ | 3–10 GW | Delayed / under review | 2033–2036 |
Capacity Summary
| Category | Count | Capacity |
|---|---|---|
| Operational | 5 | ~2.7 GW |
| Under construction | 1 | ~1 GW |
| Tendered (CfD) | 3 | ~2.8 GW |
| Energy islands (advancing) | 1 | 3 GW |
| Energy islands (delayed) | 1 | 3–10 GW |
| Total pipeline | ~11 | ~12.5–19.5 GW |
Supranational Dimension
EU Regulatory Framework
| Framework | Relevance to Denmark |
|---|---|
| TEN-E Regulation (EU 2022/869) | PCI/PMI designation for cross-border energy island projects (Bornholm DK–DE). Hybrid offshore wind projects eligible for PCI status |
| RED III (Renewable Energy Directive) | Denmark is among the most advanced EU member states in transposing RED III (as of early 2026). Includes renewable acceleration areas |
| EU Offshore RE Strategy (2020) | 300 GW offshore wind by 2050 across EU. Denmark among leading contributors |
| ENTSO-E ONDP | Denmark’s energy island projects are central to offshore network corridor planning |
| Esbjerg Declaration (May 2022) | Hosted by Denmark. North Sea countries commit to 65 GW by 2030 and 150 GW by 2050 |
NSEC Leadership Role
Denmark is a founding member and one of the most active participants in the North Seas Energy Cooperation. Key contributions include: hosting the Esbjerg Declaration (May 2022), co-chairing NSEC in 2024, pioneering energy island concepts that have shaped NSEC thinking on offshore grid architecture, and deploying the world’s first hybrid interconnector (Kriegers Flak CGS).
Key International Declarations
| Declaration | Year | Denmark’s Role | Key Commitment |
|---|---|---|---|
| Esbjerg Declaration | 2022 | Host | 150 GW North Sea offshore wind by 2050 |
| Ostend Declaration | 2023 | Signatory | 120 GW by 2030, 300 GW by 2050 |
| Hamburg Declaration | 2026 | Signatory | 100 GW cross-border offshore wind by 2050. TSOs to identify 20 GW projects by 2027 |
Regime Reform & Future Direction
Post-Failure Restructuring
The December 2024 tender failure forced a fundamental rethink of Denmark’s offshore wind policy. The government responded by abandoning the negative bidding model in favour of two-sided CfDs with a DKK 55.2B support cap. The 20% mandatory state co-ownership requirement was also removed to improve investor appeal.
Developer-Pays Model Under Scrutiny
The shift from TSO-build (Energinet bears grid costs) to developer-pays (developer bears grid costs) remains a key policy question. While developer-pays reduces public spending, it increases developer risk and bid prices. The sustainability of this model will be tested by the outcomes of the November 2025 CfD tenders.
Energy Island Pathway
The Bornholm Energy Island is advancing through development and tender preparation, but the North Sea island (VindØ) faces a critical juncture. Cost estimates exceeding DKK 200B have prompted the government to reassess the project scope. A phased approach or pivot to distributed hub-in-the-sea platforms may replace the original single-island concept.
| Reform Area | Status |
|---|---|
| Tender model | Shifted from negative bidding to two-sided CfD (Nov 2025) |
| State co-ownership | Removed (was 20% mandatory) |
| CfD support cap | DKK 55.2B across three tenders |
| Developer-pays grid | Retained but under scrutiny after 3 GW failure |
| Open-door scheme | Suspended since 1 Feb 2023 (EU state aid concerns) |
| Bornholm Energy Island | Development / tender preparation. DK–DE agreement signed Jan 2026 |
| North Sea / VindØ | Delayed to 2033–2036. Scope under review (>DKK 200B cost) |
| RED III transposition | Among most advanced EU states in transposing RED III |
| 35 GW by 2050 pathway | Requires unprecedented construction rate from ~2.7 GW base |
Key Sources
Fact Check
This page was fact-checked using automated verification (OpenAI gpt-5.4 with web search). Two iterations were run against the research document, with findings independently verified before corrections were applied.
| Iteration | Date | Errors Reported | Verified & Fixed | False Positives | Summary |
|---|---|---|---|---|---|
| 2 | 2026-03-15 | 12 | 6 | 6 | KEFM full name corrected, DEA three→four licences, RED III transposition claim softened, 2050 target 35–52→35 GW per DEA. |
| 1 | 2026-03-15 | 19 | 10 | 9 | Key fixes: Horns Rev 3 EUR conversion €10.3→€103/MWh (10x error), Kriegers Flak €5→€50/MWh, open-door suspension 2022→1 Feb 2023, Bornholm not artificial island, Bornholm status→tender prep, Climate Act 2019→2020. |