DELAYED +0mo (May 2026): TenneT's offshore grid connection transparency page lists NOR-9-2 (BalWin3) connection for OWP Windbostel West (site N-9.2) with a 'voraussichtlicher Fertigstellungstermin' of 31.12.2031, not 2029 as previously projected/assumed. Updating the regulatory/grid milestone accordingly. --- Transmission system operator TenneT has published on its transparency portal that the BalWin3 offshore HVDC grid connection (project NOR-9-2), which will connect the 2,000 MW Windbostel West offshore wind farm on site N-9.2 to shore, has an expected completion date of 31 December 2031.