Neutral
Informational - no clear directional impact
Low Impact
Minor progress or informational
Windbostel West GmbH submitted an application to the Federal Maritime and Hydrographic Agency (BSH) on 30 July 2025 to initiate a plan approval procedure under the Offshore Wind Energy Act (WindSeeG) for the construction and operation of the 2,000 MW Windbostel West offshore wind farm in the German North Sea EEZ. The application covers 136 turbines and associated 66 kV internal cabling with direct connection to the future BalWin3/NOR-9-2 converter platform.