Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
On 22 August 2016 contractor vessels completed Campaign 1 of the Western HVDC Link subsea cable works. The Giulio Verne recovered a 28 km wet‑stored section, joined it to the installed cable, laid it on the seabed and completed burial works; post‑lay survey activity by support vessel Go Pegasus was then scheduled. Notices to mariners and contractor progress updates recorded the recovery, jointing, laying and burial as completing the first installation campaign along the route.