The December 2025 geophysical campaign for the Western HVDC Link was completed on or about 20 December 2025 (subject to weather windows). The MV Scotia operated 24 hours to capture multibeam and ROV cable-detection data across designated locations; results were used to confirm cable integrity, burial depths and to inform any necessary follow-up inspections or interventions.
A geophysical survey campaign along the Western HVDC Link cable route commenced on 5 December 2025, carried out by the survey vessel MV Scotia at 14 locations in the Firth of Clyde, North Channel and northern Irish Sea. The scope included ROV-based cable detection, multibeam echosounder mapping and marine mammal observations to assess seabed and cable condition ahead of routine inspection or maintenance activities.
The geophysical inspection campaign that started in October 2023 concluded on or about 5 November 2023 (weather permitting). The survey delivered multibeam and side-scan sonar data across the route to assess cable burial, identify seabed changes and record any features requiring follow-up intervention or monitoring.
A detailed geophysical inspection survey along the operational WesternLink submarine HVDC interconnector began on 2 October 2023. The campaign — executed by dive-support vessel Curtis Marshall — mapped parallel survey lines along the cable route using multibeam echosounder and side-scan sonar to verify seabed condition, burial integrity and detect any exposures or anomalies along the full length of the 390 km route.
The Western HVDC Link reached full commercial handover on 22 November 2019, marking formal transfer to the operating parties and completion of commissioning activities required to deliver full commercial service. Prior to handover, the link’s full technical capability was progressively enabled (reported as ‘full use available’ from 16 October 2018 and providing full service by summer 2019); the completed link operates at a rated capacity of about 2,200 MW and was formally handed over to the operators to enter full commercial operation on 22 November 2019.
After staged commissioning and remedial works, the Western HVDC Link was made available for full use on 16 October 2018. This milestone followed further work at the Hunterston converter site and represented the completion of key converter/substation commissioning activities required to operate the link at its intended capacity.
SP Transmission (SP Energy Networks) and National Grid Electricity Transmission established a joint delivery and operating arrangement for the Western HVDC Link, a £1.2 billion, 2,200 MW bi‑directional subsea HVDC electricity link between Hunterston (Scotland) and Flintshire Bridge (Wales/England). The partnership delivered, commissioned and operated the asset, which entered commercial operation in 2017 to enable large‑scale transfer of Scottish renewable generation to England and Wales and to strengthen GB transmission capacity.
SP Transmission and National Grid placed the Western HVDC Link into service on 7 December 2017 at a reduced capacity (circa 900 MW) while further commissioning work at the Hunterston converter station continued. The partial energisation allowed the subsea HVDC link between Hunterston (Scotland) and Flintshire Bridge (Wales) to begin transmitting power during an extended commissioning and testing programme, while remaining works at the Hunterston onshore converter were completed.
The Western HVDC Link (Western Link), a joint project delivered by SP Transmission (SP Energy Networks) and National Grid Electricity Transmission, was energised and entered service on 7 December 2017 at reduced capacity. Initial operation began with an approximate 900 MW capability while final commissioning works continued at the Hunterston converter site. The energisation brought the subsea HVDC connection between Hunterston (Scotland) and Flintshire Bridge/Connah’s Quay (Wales) into service so that power could begin to flow bi-directionally across the link to support north–south transfers of low‑carbon electricity.
All submarine and onshore cable installation campaigns for the Western HVDC Link were completed by mid-2017. The 422 km cable system was installed across approximately 6 campaigns between July 2016 and mid-2017, using Prysmian's Giulio Verne CLV. The link began transmitting power in late 2017.
| United Kingdom | United Kingdom | |
|---|---|---|
| Landfall | Hunterston (coast near Hunterston, Ayrshire, Scotland) | Flintshire Bridge / Connah's Quay (coast, Flintshire, North Wales) |
| Grid Connection | Flintshire Bridge static inverter plant (Connah's Quay converter station) | — |
United Kingdom
United Kingdom