TKF’s inter-array cable installation for Luxcara’s 296 MW Waterkant offshore wind farm on German BSH site N-6.7 is scheduled to start in 2027, as part of a 2027–2028 campaign to install about 130 km of 66 kV aluminium-core inter-array cables and accessories connecting the turbines to Amprion’s converter platform.