Following installation of the Valhall PH process and hotel platform in 2011 and its start‑up in January 2013, the Valhall redevelopment and power‑from‑shore project was considered complete, making Valhall the first field on the Norwegian continental shelf to base its power supply entirely on electricity transmitted via submarine cable from land. From 2013 onward, all routine power for the Valhall complex has been provided by the Lista–Valhall HVDC Light link rather than offshore gas turbines, establishing the scheme as a pioneer full‑electrification project.