two 50-kilometre long export cables; VBMS to carry out installation with its own two cable laying vessels
VBMS signed a EUR 80 million Preferred Supplier and Early Works Agreement for the Triton Knoll offshore electricity transmission works, covering the installation of export and inter-array cables. VBMS stated it would execute the cable installation using its own two cable-laying vessels, with project execution scheduled to start in 2020. The published scope referenced two 50-kilometre-long export cables and 66 kV inter-array cables.