Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
By 18 September 2025, Prysmian had finished laying both circuits of the 66 kV, 36 km submarine cable interconnection between Tenerife and La Gomera, completing the subsea cable installation phase, after which only protection campaigns, onshore terminations and testing remained before full commissioning.