Positive
Project advancing - milestone achieved
High Impact
Major milestone or critical setback
ENTSO-E’s TYNDP 2012 monitoring update (Annex 1, dated 1 July 2013) lists the Statnett Oslofjord Teigen–Evje 420 kV subsea cable project and notes that commissioning, originally planned for 2013, was delayed to 2014 due to technical difficulties with cable delivery (“Teigen – Evje originally planned commissioning 2013 delayed to 2014”). Later ENTSO-E planning documents treat the link as part of the existing Oslofjord cable system, with no further delay notices. Given that the interconnector is now in operation and no subsequent sources indicate additional postponements, 2014 is taken as the commissioning / full commercial operation year (year-level precision; exact day not specified).