Neutral
Informational - no clear directional impact
Low Impact
Minor progress or informational
On 29 August 2022, the Skiathos–Euboea electrical interconnection was officially inaugurated at the Skiathos High Voltage Substation. The ceremony, held after the link had already been in full operation since 11 July 2022, highlighted that the 150 kV submarine and land cable system supplied by and installed by Hellenic Cables was successfully delivering reliable power to Skiathos and the Northern Sporades and recognised the project as a major milestone for Greece’s transmission system.