First Subsea reports that Greek contractor Asso.subsea, working for developer IPTO and main contractor Hellenic Cables/Fulgor on the Mantoudi–Skiathos interconnection, finished laying the 30 km subsea cable and installing the cable protection system, with cable laying operations successfully wrapped up on Christmas Eve 2020.