Statnett and Energinet.dk took the investment decision for the Skagerrak 4 HVDC interconnector between Norway and Denmark around 2010, enabling the start of construction in early 2011. Skagerrak 4 is a 700 MW, 500 kV monopolar link between Kristiansand (Norway) and Tjele (Denmark), comprising about 140 km of undersea cable and 102 km of land cable, with a total project cost of up to EUR 400 million and proposed EIB financing of up to EUR 200 million.