Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
By August 2004, the installation of the in-array and export cables at the Scroby Sands offshore wind farm had been completed, finishing the offshore cabling campaign that ran from May to August 2004 and enabling power export to shore.