30 steel monopile foundations; piles reported as Ø ~4.2 m and driven up to ~30 m into seabed. Foundation weight reported up to ~200 tonnes (reported as 'up to 200 t' in multiple project reports).
100% ROC
Authority: Marine Management Organisation and The Crown Estate · Licence: Licensing agreements/approvals for removal and deconstruction works on fire‑damaged turbine T06 at Scroby Sands Offshore Wind Farm
By September 2025, RWE had secured the necessary licensing agreements from the UK Marine Management Organisation and The Crown Estate to remove and deconstruct the fire‑damaged turbine T06 at the Scroby Sands Offshore Wind Farm, with works undertaken as part of the site’s summer maintenance campaign and notices to mariners issued.
Authority: RWE · Licence: Notice to Mariners for removal of turbine T06 components
By late September 2025, RWE had issued a Notice to Mariners covering removal works at the Scroby Sands offshore wind farm, following the August 2023 nacelle fire that destroyed turbine T06’s generator, gearbox and blades. The notice, referenced in marine communications and news reports, set out the timetable for deconstructing the non-operational turbine using the WaveWalker 1 jack-up barge and transporting removed components to the Port of Great Yarmouth for recycling, while its foundation remained in place.
On 15 August 2023, turbine T06 at the Scroby Sands offshore wind farm caught fire in the nacelle, destroying its generator, gearbox and blades and resulting in total loss of operation of that turbine; the incident also required six neighbouring turbines to be taken out of commission for about a week until cables at the site could be isolated, after which the damaged nacelle, blades and upper tower section were later deconstructed and sent to EMR for high‑rate material recycling under RWE’s circular‑economy programme.
CRC Walrus amphibious crew transfer vessel entered service at Scroby Sands after completing land and sea trials; Commercial Rib Charter said RWE would deploy the vessel at the end of the week of 2 Feb 2023, indicating the operational start slipped from the previously planned September 2022.
In late 2015, Norfolk Marine installed its TFN scour remediation system on five monopile foundations at E.ON’s Scroby Sands offshore wind farm, deploying sediment‑retention nets around the bases to prevent further seabed scouring and to protect cables at the critical transition between the export cable trench and J‑tubes, following development and scale‑model testing at HR Wallingford’s Fast Flow Facility.
In early 2008, Oceanteam Power and Umbilical engaged Osiris Marine Services to provide specialist diving support for the Scroby Sands offshore wind farm export cable replacement project, covering deburial, recovery, replacement and reburial of one of the three export cables, as well as shore-end and I-tube works on the 33 kV export connection to Great Yarmouth.
During the summer of 2008, Osiris Marine Services carried out a major repair and replacement campaign on one of the three 33 kV export cables for the Scroby Sands offshore wind farm connection to Great Yarmouth. Working for Oceanteam Power and Umbilical, divers deburied the existing export cable, recovered the redundant section, supervised laying of a new export cable, and then used OPU’s vertical injector and diver operations to rebury the cable up to the I-tube, completing the subsea tie-in and shore-end works.
Export cable replacement/repair campaign for one of Scroby Sands’ three export cables was executed during the summer of 2008, including deburial, recovery of the redundant cable, laying the new cable, reburial and shore-end/tie-in works (diving support provided during the campaign).
By 21 January 2008, one of the three high‑voltage export cables bringing power ashore from the Scroby Sands offshore wind farm had failed, reducing export capability, although E.ON reported that around 95% of the energy generated could still be delivered via the remaining two cables.
In summer 2007, E.ON excavated part of the promenade on Great Yarmouth’s North Parade to repair one of Scroby Sands’ 33 kV export cables after moisture ingress at an onshore connection joint caused the cable to fail, with one worker treated in hospital for burns from an electrical flash during the repair works.