Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
In 2011, following construction of the converter stations between April 2009 and December 2010 and installation of the cables, the ROMULO interconnection linking the Morvedre and Santa Ponsa substations underwent testing and was put into service, marking the commissioning of the onshore converter/substation facilities required for operation of the link.