Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
In the period up to 2014, NKT completed final testing of the 155 kV HVAC export cable system for the Riffgat (NOR-0-1) offshore grid connection, as part of a turnkey contract for TenneT Offshore GmbH covering planning, manufacturing, cable-laying and testing of the approximately 48 km cable route linking the Borkum Riffgat offshore wind farm in the German North Sea to the German electricity grid.