Neutral
Informational - no clear directional impact
Low Impact
Minor progress or informational
On 27 February 2026 it was reported that IPTO had officially revised the budget for the Dodecanese Interconnection, which covers the island links including Rhodes, increasing the estimated cost by €900 million to a new total of €2.95 billion and postponing the targeted completion date for both the Dodecanese and Northern Aegean interconnections from 2029 to 2030 due to sharply higher submarine cable prices.