Positive
Project advancing - milestone achieved
High Impact
Major milestone or critical setback
IPTO has postponed completion of the Dodecanese interconnection, which includes the Kos–Rhodes–Karpathos links underpinning the Rhodes Grid Connection, by one year, so the grid interconnection is now planned to be fully completed and operational in 2030 instead of the original 2029 target, mainly due to sharp cost increases for specialised submarine cables and related materials.